on Tuesday, January 8th 2019, 6:30:00 pm
Work Sanctioned
जनपद टिहरी गढवाल के विधानसभा क्षेत्र नरेन्द्रनगर में गजा-डांडाचली मोटर मार्ग से माणदा टोली मोटर मार्ग का नवनिर्माण कार्य।(प्रथम चरण)
on Wednesday, February 6th 2019, 6:30:00 pm
Technical Sanction
of ₹ 41.82 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE. 824/7C
on Monday, September 30th 2019, 6:30:00 pm
4.07%
Financial Progress
1st Expenditure
of ₹ 239500 (2.40 Lacs ) done.
Cummulative ₹ 2.40Lacs ( against 58.8Lacs )
on Monday, July 19th 2021, 3:23:06 am
PWD UttarakahndPhoto (ID 371) from Site Received
Uploader : Jai Prakash Bhatt, Additional Assistant Engineer Civil ,PD Haridwar
Landmark : 2.000
Remark : Trial pic
on Tuesday, May 31st 2022, 6:30:00 pm
5.20%
Financial Progress
2nd Expenditure
of ₹ 66000 (0.66 Lacs ) done.
Cummulative ₹ 3.06Lacs ( against 58.8Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
29.94%
Financial Progress
3rd Expenditure
of ₹ 1455000 (14.55 Lacs ) done.
Cummulative ₹ 17.61Lacs ( against 58.8Lacs )