12 years ago

on Thursday, November 21st 2013, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा संख्या-403/2013 के अन्तर्गत बूढाकेदार तोली मोटर मार्ग का विनकखाल तक रिंग रोड का निर्माण कार्य।

12 years ago

on Friday, February 28th 2014, 6:30:00 pm
0.40%
Financial Progress

1st Expenditure
of ₹ 9016 (0.09 Lacs ) done.
Cummulative ₹ 0.09Lacs ( against 22.79Lacs )

11 years ago

on Saturday, January 31st 2015, 6:30:00 pm
0.98%
Financial Progress

2nd Expenditure
of ₹ 13420 (0.13 Lacs ) done.
Cummulative ₹ 0.22Lacs ( against 22.79Lacs )

11 years ago

on Saturday, February 28th 2015, 6:30:00 pm
8.90%
Financial Progress

3rd Expenditure
of ₹ 180325 (1.80 Lacs ) done.
Cummulative ₹ 2.03Lacs ( against 22.79Lacs )

9 years ago

on Tuesday, February 28th 2017, 6:30:00 pm
22.31%
Financial Progress

4th Expenditure
of ₹ 305612 (3.06 Lacs ) done.
Cummulative ₹ 5.08Lacs ( against 22.79Lacs )

4 years ago

on Monday, January 10th 2022, 6:30:00 pm
23.56%
Financial Progress

5th Expenditure
of ₹ 28620 (0.29 Lacs ) done.
Cummulative ₹ 5.37Lacs ( against 22.79Lacs )

3 years ago

on Saturday, December 31st 2022, 6:30:00 pm
27.97%
Financial Progress

6th Expenditure
of ₹ 100546 (1.01 Lacs ) done.
Cummulative ₹ 6.38Lacs ( against 22.79Lacs )

3 years ago

on Tuesday, January 31st 2023, 6:30:00 pm
30.12%
Financial Progress

7th Expenditure
of ₹ 48861 (0.49 Lacs ) done.
Cummulative ₹ 6.86Lacs ( against 22.79Lacs )

3 years ago

on Tuesday, February 28th 2023, 6:30:00 pm
34.42%
Financial Progress

8th Expenditure
of ₹ 98000 (0.98 Lacs ) done.
Cummulative ₹ 7.84Lacs ( against 22.79Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
62.60%
Financial Progress

9th Expenditure
of ₹ 642306 (6.42 Lacs ) done.
Cummulative ₹ 14.27Lacs ( against 22.79Lacs )

2 years ago

on Tuesday, December 19th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

9 months ago

on Tuesday, December 24th 2024, 6:30:00 pm
71.77%
Financial Progress

10th Expenditure
of ₹ 209040 (2.09 Lacs ) done.
Cummulative ₹ 16.36Lacs ( against 22.79Lacs )

7 months ago

on Thursday, February 13th 2025, 6:30:00 pm
71.95%
Financial Progress

11th Expenditure
of ₹ 4020 (0.04 Lacs ) done.
Cummulative ₹ 16.40Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
75.13%
Financial Progress

15th Expenditure
of ₹ 24790 (0.25 Lacs ) done.
Cummulative ₹ 17.12Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
72.48%
Financial Progress

12th Expenditure
of ₹ 12060 (0.12 Lacs ) done.
Cummulative ₹ 16.52Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
73.16%
Financial Progress

13th Expenditure
of ₹ 15410 (0.15 Lacs ) done.
Cummulative ₹ 16.67Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
76.83%
Financial Progress

18th Expenditure
of ₹ 14740 (0.15 Lacs ) done.
Cummulative ₹ 17.51Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
76.18%
Financial Progress

17th Expenditure
of ₹ 10720 (0.11 Lacs ) done.
Cummulative ₹ 17.36Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
75.71%
Financial Progress

16th Expenditure
of ₹ 13400 (0.13 Lacs ) done.
Cummulative ₹ 17.26Lacs ( against 22.79Lacs )

7 months ago

on Friday, February 14th 2025, 6:30:00 pm
74.04%
Financial Progress

14th Expenditure
of ₹ 20100 (0.20 Lacs ) done.
Cummulative ₹ 16.87Lacs ( against 22.79Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
76.83%
Financial Progress

19th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 17.51Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
78.87%
Financial Progress

22nd Expenditure
of ₹ 15730 (0.16 Lacs ) done.
Cummulative ₹ 17.98Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
89.22%
Financial Progress

26th Expenditure
of ₹ 35872 (0.36 Lacs ) done.
Cummulative ₹ 20.33Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
87.65%
Financial Progress

25th Expenditure
of ₹ 75000 (0.75 Lacs ) done.
Cummulative ₹ 19.98Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
84.36%
Financial Progress

24th Expenditure
of ₹ 57500 (0.57 Lacs ) done.
Cummulative ₹ 19.23Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
81.84%
Financial Progress

23rd Expenditure
of ₹ 67500 (0.68 Lacs ) done.
Cummulative ₹ 18.65Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
78.18%
Financial Progress

21st Expenditure
of ₹ 13400 (0.13 Lacs ) done.
Cummulative ₹ 17.82Lacs ( against 22.79Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
77.60%
Financial Progress

20th Expenditure
of ₹ 17420 (0.17 Lacs ) done.
Cummulative ₹ 17.68Lacs ( against 22.79Lacs )

5 months ago

on Friday, April 18th 2025, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 2nd time