Work Sanctioned
मा0मु0घो0 संख्या-176/2018 के अन्तर्गत घनसाली-तिलवाड़ा-केदारनाथ मोटर मार्ग के सुमार्थ नामे तोक से पांवलेश्वर मन्दिर कोटी भासों तक मोटर मार्ग का निर्माण कार्य।
on Friday, October 28th 2022, 6:30:00 pm
3.91%
Financial Progress
1st Expenditure
of ₹ 279964 (2.80 Lacs ) done.
Cummulative ₹ 2.80Lacs ( against 71.67Lacs )
on Tuesday, February 21st 2023, 6:30:00 pm
25.70%
Financial Progress
2nd Expenditure
of ₹ 1562000 (15.62 Lacs ) done.
Cummulative ₹ 18.42Lacs ( against 71.67Lacs )
on Thursday, September 7th 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 1st time
on Friday, September 29th 2023, 6:30:00 pm
47.55%
Financial Progress
3rd Expenditure
of ₹ 1565818 (15.66 Lacs ) done.
Cummulative ₹ 34.08Lacs ( against 71.67Lacs )
on Sunday, October 29th 2023, 6:30:00 pm
57.55%
Financial Progress
4th Expenditure
of ₹ 716770 (7.17 Lacs ) done.
Cummulative ₹ 41.25Lacs ( against 71.67Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
74.80%
Financial Progress
5th Expenditure
of ₹ 1236237 (12.36 Lacs ) done.
Cummulative ₹ 53.61Lacs ( against 71.67Lacs )