Work Sanctioned
जनपद-टिहरी गढवाल के विधानसभा क्षेत्र घनसाली के अन्तर्गत घुत्तू-गवाणा तल्ला मोटर मार्ग का सुधारीकरण एवं डामरीकरण का कार्य।
on Thursday, May 18th 2023, 6:38:10 am
Technical Sanction
of ₹ 189.94 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2483(1)/984C-8/2022 Dt. 18-05-2023
on Tuesday, December 12th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, January 27th 2024, 6:30:00 pm
1.77%
Financial Progress
1st Expenditure
of ₹ 335632 (3.36 Lacs ) done.
Cummulative ₹ 3.36Lacs ( against 189.94Lacs )
on Saturday, January 27th 2024, 6:30:00 pm
15.45%
Financial Progress
2nd Expenditure
of ₹ 2599845 (26.00 Lacs ) done.
Cummulative ₹ 29.35Lacs ( against 189.94Lacs )
on Monday, February 19th 2024, 6:30:00 pm
29.02%
Financial Progress
3rd Expenditure
of ₹ 2577053 (25.77 Lacs ) done.
Cummulative ₹ 55.13Lacs ( against 189.94Lacs )
on Wednesday, February 21st 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, February 28th 2024, 6:30:00 pm
29.02%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 55.13Lacs ( against 189.94Lacs )
on Friday, March 29th 2024, 6:30:00 pm
42.27%
Financial Progress
5th Expenditure
of ₹ 2515454 (25.15 Lacs ) done.
Cummulative ₹ 80.28Lacs ( against 189.94Lacs )
on Tuesday, April 30th 2024, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, May 31st 2024, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 4th time
on Monday, June 10th 2024, 5:16:53 am
PWD UttarakahndPhoto (ID 42697) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 0.775
Remark : OTM work Road surface
on Monday, June 10th 2024, 5:40:36 am
PWD UttarakahndPhoto (ID 42706) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 3.850
Remark : OTM work P.C surface
on Monday, June 10th 2024, 5:44:35 am
PWD UttarakahndPhoto (ID 42708) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 4.25
Remark : OTM work PC surface
on Monday, June 10th 2024, 6:57:28 am
PWD UttarakahndPhoto (ID 42746) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 1.525
Remark : OTM interlocking tiles
on Tuesday, June 11th 2024, 11:15:47 am
PWD UttarakahndPhoto (ID 43174) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 1.025
Remark : OTM work PC surface
on Tuesday, June 18th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Thursday, June 27th 2024, 6:30:00 pm
61.75%
Financial Progress
6th Expenditure
of ₹ 3700000 (37.00 Lacs ) done.
Cummulative ₹ 117.28Lacs ( against 189.94Lacs )
on Monday, July 29th 2024, 6:30:00 pm
85.47%
Financial Progress
7th Expenditure
of ₹ 4506133 (45.06 Lacs ) done.
Cummulative ₹ 162.34Lacs ( against 189.94Lacs )
on Friday, November 29th 2024, 6:30:00 pm
86.65%
Financial Progress
8th Expenditure
of ₹ 224554 (2.25 Lacs ) done.
Cummulative ₹ 164.59Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
86.97%
Financial Progress
9th Expenditure
of ₹ 61124 (0.61 Lacs ) done.
Cummulative ₹ 165.20Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
96.77%
Financial Progress
17th Expenditure
of ₹ 216034 (2.16 Lacs ) done.
Cummulative ₹ 183.80Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
95.63%
Financial Progress
16th Expenditure
of ₹ 10308 (0.10 Lacs ) done.
Cummulative ₹ 181.64Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
95.58%
Financial Progress
15th Expenditure
of ₹ 51877 (0.52 Lacs ) done.
Cummulative ₹ 181.54Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
95.30%
Financial Progress
14th Expenditure
of ₹ 17346 (0.17 Lacs ) done.
Cummulative ₹ 181.02Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
95.21%
Financial Progress
13th Expenditure
of ₹ 1034413 (10.34 Lacs ) done.
Cummulative ₹ 180.85Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
89.77%
Financial Progress
12th Expenditure
of ₹ 495717 (4.96 Lacs ) done.
Cummulative ₹ 170.50Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
87.16%
Financial Progress
11th Expenditure
of ₹ 17346 (0.17 Lacs ) done.
Cummulative ₹ 165.54Lacs ( against 189.94Lacs )
on Saturday, March 29th 2025, 6:30:00 pm
87.07%
Financial Progress
10th Expenditure
of ₹ 17346 (0.17 Lacs ) done.
Cummulative ₹ 165.37Lacs ( against 189.94Lacs )