on Tuesday, October 31st 2023, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा के अन्तर्गत जनपद टिहरी गढवाल के ब्लाॅक थौलधार के छाम मैण्डखाल छाम (जसपुर) मोटर मार्ग में आवश्यक सुरक्षात्मक कार्य।
on Tuesday, December 5th 2023, 5:57:42 am
Technical Sanction
of ₹ 189.43 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. SE LETTER NO- 6316/42C-8/2023
on Sunday, March 24th 2024, 6:30:00 pm
34.10%
Financial Progress
1st Expenditure
of ₹ 6460500 (64.61 Lacs ) done.
Cummulative ₹ 64.61Lacs ( against 189.43Lacs )
on Friday, April 5th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, May 9th 2024, 6:30:00 pm
52.40%
Financial Progress
2nd Expenditure
of ₹ 3465110 (34.65 Lacs ) done.
Cummulative ₹ 99.26Lacs ( against 189.43Lacs )
on Saturday, June 15th 2024, 9:54:29 am
PWD UttarakahndPhoto (ID 44951) from Site Received
Uploader : Amit Rusia, Assistant Engineer Civil ,CD Chamba
Landmark : Km. 3.00
Remark : Road Safety work on Chham maindkhal motor road
on Saturday, June 15th 2024, 9:57:52 am
PWD UttarakahndPhoto (ID 44939) from Site Received
Uploader : Rohit Singh Panwar, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Km 5
Remark : Road Safety Work on Cham Mendkhal MDR
on Sunday, June 23rd 2024, 6:30:00 pm
73.96%
Financial Progress
3rd Expenditure
of ₹ 4084079 (40.84 Lacs ) done.
Cummulative ₹ 140.10Lacs ( against 189.43Lacs )
on Saturday, July 13th 2024, 7:35:35 am
PWD UttarakahndPhoto (ID 50713) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : 46W653
Remark : Inspection of Road with AE and JE incharge
on Saturday, July 13th 2024, 7:50:14 am
PWD UttarakahndPhoto (ID 50714) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : 46W653
Remark : Checking the thickness of spacer=5.15mm, vertical post=5.20mm, width of W beam=312mm, and height of vertical post above GL=700mm, All measurements found ok
on Saturday, July 13th 2024, 8:14:37 am
PWD UttarakahndPhoto (ID 50716) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : 6.450
Remark : Km 6.450, thickness of spacer/vertical post=5.10mm, and W beam=3.10mm, quality and thermoplastic paint and Cat eyes, All items are found OK
on Saturday, July 13th 2024, 8:25:22 am
PWD UttarakahndPhoto (ID 50719) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : 5.300
Remark : Km 5.300, View of Road Safety Items
on Friday, August 2nd 2024, 11:10:00 am
PWD UttarakahndPhoto (ID 51529) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : Km 11.075
Remark : Third party Inspection with SE Sir..
on Sunday, September 8th 2024, 6:30:00 pm
85.83%
Financial Progress
4th Expenditure
of ₹ 2249834 (22.50 Lacs ) done.
Cummulative ₹ 162.60Lacs ( against 189.43Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
90.63%
Financial Progress
5th Expenditure
of ₹ 908815 (9.09 Lacs ) done.
Cummulative ₹ 171.68Lacs ( against 189.43Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
91.83%
Financial Progress
6th Expenditure
of ₹ 226560 (2.27 Lacs ) done.
Cummulative ₹ 173.95Lacs ( against 189.43Lacs )
on Tuesday, January 28th 2025, 6:30:00 pm
92.39%
Financial Progress
7th Expenditure
of ₹ 106200 (1.06 Lacs ) done.
Cummulative ₹ 175.01Lacs ( against 189.43Lacs )
on Wednesday, February 5th 2025, 6:30:00 pm
92.48%
Financial Progress
8th Expenditure
of ₹ 18290 (0.18 Lacs ) done.
Cummulative ₹ 175.19Lacs ( against 189.43Lacs )
on Thursday, February 13th 2025, 6:30:00 pm
93.14%
Financial Progress
9th Expenditure
of ₹ 123900 (1.24 Lacs ) done.
Cummulative ₹ 176.43Lacs ( against 189.43Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
94.37%
Financial Progress
10th Expenditure
of ₹ 232810 (2.33 Lacs ) done.
Cummulative ₹ 178.76Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.76%
Financial Progress
18th Expenditure
of ₹ 6026 (0.06 Lacs ) done.
Cummulative ₹ 179.50Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.73%
Financial Progress
17th Expenditure
of ₹ 3881 (0.04 Lacs ) done.
Cummulative ₹ 179.44Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.71%
Financial Progress
16th Expenditure
of ₹ 4657 (0.05 Lacs ) done.
Cummulative ₹ 179.40Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.68%
Financial Progress
15th Expenditure
of ₹ 8337 (0.08 Lacs ) done.
Cummulative ₹ 179.36Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.64%
Financial Progress
14th Expenditure
of ₹ 6154 (0.06 Lacs ) done.
Cummulative ₹ 179.27Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.61%
Financial Progress
13th Expenditure
of ₹ 19116 (0.19 Lacs ) done.
Cummulative ₹ 179.21Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.50%
Financial Progress
12th Expenditure
of ₹ 20768 (0.21 Lacs ) done.
Cummulative ₹ 179.02Lacs ( against 189.43Lacs )
on Monday, March 24th 2025, 6:30:00 pm
94.39%
Financial Progress
11th Expenditure
of ₹ 5099 (0.05 Lacs ) done.
Cummulative ₹ 178.81Lacs ( against 189.43Lacs )
on Sunday, June 8th 2025, 6:30:00 pm
94.85%
Financial Progress
19th Expenditure
of ₹ 16500 (0.17 Lacs ) done.
Cummulative ₹ 179.67Lacs ( against 189.43Lacs )