Refresh data
on Thursday, August 22nd 2024, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2024-25 में जनपद टिहरी गढवाल केें विधानसभा क्षेत्र धनोल्टी के विकासखण्ड थौलधार में इन्द्रा गांव कटखेत मोटर मार्ग का डामरीकरण का कार्य।
on Monday, December 30th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 162.22Lacs )
on Wednesday, January 1st 2025, 8:52:42 am
PWD UttarakahndPhoto (ID 62117) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : Km 2.00
Remark : C/O Scupper at 1.250
on Wednesday, January 1st 2025, 9:08:43 am
PWD UttarakahndPhoto (ID 62118) from Site Received
Uploader : Jagdish Singh, Executive Engineer Civil ,CD Chamba
Landmark : Ch 0.000to 0.075
Remark : Collie walling and G01 Staking
on Thursday, January 2nd 2025, 6:30:00 pm
15.44%
Financial Progress
2nd Expenditure
of ₹ 2504550 (25.05 Lacs ) done.
Cummulative ₹ 25.05Lacs ( against 162.22Lacs )
on Wednesday, January 15th 2025, 7:34:28 am
PWD UttarakahndPhoto (ID 62758) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Km-1,Ch-0.200
Remark : WBM G-1 collection
on Wednesday, January 15th 2025, 10:46:08 am
PWD UttarakahndPhoto (ID 62788) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Km1 Ch-950
Remark : RCC 1 M span Culvert slab casting
on Sunday, February 2nd 2025, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, February 4th 2025, 6:30:00 pm
16.88%
Financial Progress
3rd Expenditure
of ₹ 234054 (2.34 Lacs ) done.
Cummulative ₹ 27.39Lacs ( against 162.22Lacs )
on Monday, February 10th 2025, 9:39:32 am
PWD UttarakahndPhoto (ID 64243) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 1.900
Remark : WBM G2 Grading Test
on Friday, February 14th 2025, 6:25:14 am
PWD UttarakahndPhoto (ID 64418) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 0.450
Remark : Slab casting of culvert
on Friday, February 14th 2025, 6:50:02 am
PWD UttarakahndPhoto (ID 64420) from Site Received
Uploader : Desh Raj Singh, Assistant Engineer Civil ,CD Chamba
Landmark : Ch 0.450
Remark : Slab casting of R C C culvert
on Friday, February 14th 2025, 9:49:01 am
PWD UttarakahndPhoto (ID 64435) from Site Received
Uploader : Desh Raj Singh, Assistant Engineer Civil ,CD Chamba
Landmark : Ch.0.750
Remark : Slab casting of RCC culvert
on Friday, February 14th 2025, 10:51:38 am
PWD UttarakahndPhoto (ID 64444) from Site Received
Uploader : Desh Raj Singh, Assistant Engineer Civil ,CD Chamba
Landmark : Ch. 1.000
Remark : Slab casting of RCC culvert
on Friday, February 14th 2025, 12:15:35 pm
PWD UttarakahndPhoto (ID 64448) from Site Received
Uploader : Desh Raj Singh, Assistant Engineer Civil ,CD Chamba
Landmark : Ch. 1.050
Remark : Slab casting of RCC culvert
on Thursday, February 20th 2025, 6:30:00 pm
28.68%
Financial Progress
4th Expenditure
of ₹ 1914406 (19.14 Lacs ) done.
Cummulative ₹ 46.53Lacs ( against 162.22Lacs )
on Monday, March 3rd 2025, 6:30:00 pm
40.69%
Financial Progress
5th Expenditure
of ₹ 1947000 (19.47 Lacs ) done.
Cummulative ₹ 66.00Lacs ( against 162.22Lacs )
on Tuesday, March 4th 2025, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, March 5th 2025, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, March 10th 2025, 6:30:00 pm
42.89%
Financial Progress
6th Expenditure
of ₹ 357232 (3.57 Lacs ) done.
Cummulative ₹ 69.57Lacs ( against 162.22Lacs )
on Sunday, March 16th 2025, 6:30:00 pm
44.42%
Financial Progress
7th Expenditure
of ₹ 249157 (2.49 Lacs ) done.
Cummulative ₹ 72.06Lacs ( against 162.22Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
44.49%
Financial Progress
8th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 72.16Lacs ( against 162.22Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
60.67%
Financial Progress
9th Expenditure
of ₹ 2625109 (26.25 Lacs ) done.
Cummulative ₹ 98.42Lacs ( against 162.22Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
60.70%
Financial Progress
10th Expenditure
of ₹ 5785 (0.06 Lacs ) done.
Cummulative ₹ 98.47Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
60.76%
Financial Progress
11th Expenditure
of ₹ 8489 (0.08 Lacs ) done.
Cummulative ₹ 98.56Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.28%
Financial Progress
12th Expenditure
of ₹ 247328 (2.47 Lacs ) done.
Cummulative ₹ 101.03Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.33%
Financial Progress
13th Expenditure
of ₹ 7865 (0.08 Lacs ) done.
Cummulative ₹ 101.11Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.35%
Financial Progress
14th Expenditure
of ₹ 3881 (0.04 Lacs ) done.
Cummulative ₹ 101.15Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.40%
Financial Progress
15th Expenditure
of ₹ 8121 (0.08 Lacs ) done.
Cummulative ₹ 101.23Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.47%
Financial Progress
16th Expenditure
of ₹ 10285 (0.10 Lacs ) done.
Cummulative ₹ 101.33Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.52%
Financial Progress
17th Expenditure
of ₹ 8498 (0.08 Lacs ) done.
Cummulative ₹ 101.42Lacs ( against 162.22Lacs )
on Monday, March 24th 2025, 6:30:00 pm
62.56%
Financial Progress
18th Expenditure
of ₹ 5948 (0.06 Lacs ) done.
Cummulative ₹ 101.48Lacs ( against 162.22Lacs )
on Wednesday, March 26th 2025, 6:30:00 pm
62.57%
Financial Progress
19th Expenditure
of ₹ 2585 (0.03 Lacs ) done.
Cummulative ₹ 101.50Lacs ( against 162.22Lacs )
on Tuesday, April 1st 2025, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, April 23rd 2025, 11:41:47 am
PWD UttarakahndPhoto (ID 67955) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Km 1.875
Remark : PC work in progress
on Friday, April 25th 2025, 5:13:34 am
PWD UttarakahndPhoto (ID 68130) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 1.250
Remark : PC work in progress
on Sunday, April 27th 2025, 7:48:19 am
PWD UttarakahndPhoto (ID 68435) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 0.775
Remark : PC work in progress
on Sunday, April 27th 2025, 9:13:15 am
PWD UttarakahndPhoto (ID 68445) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Ch-0.850
Remark : PC work in progress
on Thursday, May 1st 2025, 10:14:51 am
PWD UttarakahndPhoto (ID 69126) from Site Received
Uploader : Ghanshyam Singh, Assistant Engineer Civil ,CD Chamba
Landmark : 0.625km
Remark : Inspection with EE Sir
on Thursday, May 1st 2025, 11:08:39 am
PWD UttarakahndPhoto (ID 69142) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 0.700
Remark : PC work in progress
on Friday, May 2nd 2025, 2:47:32 am
PWD UttarakahndPhoto (ID 69180) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : 0.725
Remark : PC and Seal coat in progress
on Tuesday, May 20th 2025, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 5th time
on Friday, May 30th 2025, 6:30:00 pm
90.87%
Financial Progress
20th Expenditure
of ₹ 4590938 (45.91 Lacs ) done.
Cummulative ₹ 147.41Lacs ( against 162.22Lacs )
on Monday, June 9th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Tuesday, June 10th 2025, 11:22:17 am
PWD UttarakahndPhoto (ID 74207) from Site Received
Uploader : Ajendra Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Ch-1.850
Remark : Sinage work
on Sunday, June 15th 2025, 6:30:00 pm
90.92%
Financial Progress
21st Expenditure
of ₹ 7080 (0.07 Lacs ) done.
Cummulative ₹ 147.48Lacs ( against 162.22Lacs )
on Sunday, June 15th 2025, 6:30:00 pm
90.95%
Financial Progress
22nd Expenditure
of ₹ 5900 (0.06 Lacs ) done.
Cummulative ₹ 147.54Lacs ( against 162.22Lacs )
on Sunday, June 15th 2025, 6:30:00 pm
91.13%
Financial Progress
23rd Expenditure
of ₹ 28320 (0.28 Lacs ) done.
Cummulative ₹ 147.83Lacs ( against 162.22Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
91.22%
Financial Progress
24th Expenditure
of ₹ 15930 (0.16 Lacs ) done.
Cummulative ₹ 147.98Lacs ( against 162.22Lacs )
on Friday, July 4th 2025, 6:30:00 pm
94.75%
Financial Progress
25th Expenditure
of ₹ 572253 (5.72 Lacs ) done.
Cummulative ₹ 153.71Lacs ( against 162.22Lacs )
on Sunday, August 17th 2025, 6:30:00 pm
97.03%
Financial Progress
26th Expenditure
of ₹ 369836 (3.70 Lacs ) done.
Cummulative ₹ 157.41Lacs ( against 162.22Lacs )