13 years ago

on Thursday, October 4th 2012, 6:30:00 pm
Work Sanctioned
मलेथा ग्वाड़ टोला मार्ग का बडोला तक विस्तार

13 years ago

on Thursday, February 28th 2013, 6:30:00 pm
0.07%
Financial Progress

1st Expenditure
of ₹ 6400 (0.06 Lacs ) done.
Cummulative ₹ 0.06Lacs ( against 88.2Lacs )

12 years ago

on Monday, September 30th 2013, 6:30:00 pm
0.30%
Financial Progress

2nd Expenditure
of ₹ 20100 (0.20 Lacs ) done.
Cummulative ₹ 0.27Lacs ( against 88.2Lacs )

11 years ago

on Saturday, February 28th 2015, 6:30:00 pm
4.62%
Financial Progress

3rd Expenditure
of ₹ 381073 (3.81 Lacs ) done.
Cummulative ₹ 4.08Lacs ( against 88.2Lacs )

10 years ago

on Thursday, April 30th 2015, 6:30:00 pm
4.83%
Financial Progress

4th Expenditure
of ₹ 18168 (0.18 Lacs ) done.
Cummulative ₹ 4.26Lacs ( against 88.2Lacs )

10 years ago

on Saturday, October 31st 2015, 6:30:00 pm
4.94%
Financial Progress

5th Expenditure
of ₹ 10010 (0.10 Lacs ) done.
Cummulative ₹ 4.36Lacs ( against 88.2Lacs )

10 years ago

on Sunday, January 31st 2016, 6:30:00 pm
5.21%
Financial Progress

6th Expenditure
of ₹ 23750 (0.24 Lacs ) done.
Cummulative ₹ 4.60Lacs ( against 88.2Lacs )

10 years ago

on Monday, February 29th 2016, 6:30:00 pm
6.87%
Financial Progress

7th Expenditure
of ₹ 146429 (1.46 Lacs ) done.
Cummulative ₹ 6.06Lacs ( against 88.2Lacs )

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
8.18%
Financial Progress

8th Expenditure
of ₹ 115647 (1.16 Lacs ) done.
Cummulative ₹ 7.22Lacs ( against 88.2Lacs )

2 years ago

on Monday, June 12th 2023, 6:30:00 pm
8.50%
Financial Progress

9th Expenditure
of ₹ 27718 (0.28 Lacs ) done.
Cummulative ₹ 7.49Lacs ( against 88.2Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
22.02%
Financial Progress

10th Expenditure
of ₹ 1193033 (11.93 Lacs ) done.
Cummulative ₹ 19.42Lacs ( against 88.2Lacs )

2 years ago

on Tuesday, August 8th 2023, 6:30:00 pm
27.84%
Financial Progress

13th Expenditure
of ₹ 15104 (0.15 Lacs ) done.
Cummulative ₹ 24.55Lacs ( against 88.2Lacs )

2 years ago

on Tuesday, August 8th 2023, 6:30:00 pm
27.67%
Financial Progress

12th Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 24.40Lacs ( against 88.2Lacs )

2 years ago

on Tuesday, August 8th 2023, 6:30:00 pm
27.44%
Financial Progress

11th Expenditure
of ₹ 477627 (4.78 Lacs ) done.
Cummulative ₹ 24.20Lacs ( against 88.2Lacs )

2 years ago

on Sunday, August 27th 2023, 6:30:00 pm
30.66%
Financial Progress

14th Expenditure
of ₹ 249216 (2.49 Lacs ) done.
Cummulative ₹ 27.05Lacs ( against 88.2Lacs )

2 years ago

on Friday, October 20th 2023, 6:30:00 pm
31.70%
Financial Progress

15th Expenditure
of ₹ 91686 (0.92 Lacs ) done.
Cummulative ₹ 27.96Lacs ( against 88.2Lacs )

2 years ago

on Sunday, October 29th 2023, 6:30:00 pm
32.11%
Financial Progress

16th Expenditure
of ₹ 35600 (0.36 Lacs ) done.
Cummulative ₹ 28.32Lacs ( against 88.2Lacs )

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
36.70%
Financial Progress

17th Expenditure
of ₹ 405000 (4.05 Lacs ) done.
Cummulative ₹ 32.37Lacs ( against 88.2Lacs )

2 years ago

on Saturday, December 30th 2023, 6:30:00 pm
13.71%
Financial Progress

18th Expenditure
of ₹ -2028000 (-20.28 Lacs ) done.
Cummulative ₹ 12.09Lacs ( against 88.2Lacs )

2 years ago

on Wednesday, January 3rd 2024, 6:30:00 pm
21.08%
Financial Progress

19th Expenditure
of ₹ 650765 (6.51 Lacs ) done.
Cummulative ₹ 18.60Lacs ( against 88.2Lacs )

2 years ago

on Tuesday, March 19th 2024, 6:30:00 pm
24.54%
Financial Progress

20th Expenditure
of ₹ 304440 (3.04 Lacs ) done.
Cummulative ₹ 21.64Lacs ( against 88.2Lacs )

a year ago

on Sunday, June 2nd 2024, 6:30:00 pm
13.38%
Financial Progress

21st Expenditure
of ₹ -984223 (-9.84 Lacs ) done.
Cummulative ₹ 11.80Lacs ( against 88.2Lacs )

a year ago

on Wednesday, June 12th 2024, 6:30:00 pm
24.54%
Financial Progress

22nd Expenditure
of ₹ 984223 (9.84 Lacs ) done.
Cummulative ₹ 21.64Lacs ( against 88.2Lacs )

a year ago

on Sunday, July 28th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
24.54%
Financial Progress

24th Expenditure
of ₹ -444780 (-4.45 Lacs ) done.
Cummulative ₹ 21.64Lacs ( against 88.2Lacs )

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
29.58%
Financial Progress

23rd Expenditure
of ₹ 444780 (4.45 Lacs ) done.
Cummulative ₹ 26.09Lacs ( against 88.2Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
24.54%
Financial Progress

26th Expenditure
of ₹ -186796 (-1.87 Lacs ) done.
Cummulative ₹ 21.64Lacs ( against 88.2Lacs )

a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
26.65%
Financial Progress

25th Expenditure
of ₹ 186796 (1.87 Lacs ) done.
Cummulative ₹ 23.51Lacs ( against 88.2Lacs )

a year ago

on Wednesday, October 23rd 2024, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

9 months ago

on Monday, December 23rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

6 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 4th time

23 days ago

on Saturday, August 30th 2025, 6:30:00 pm
26.24%
Financial Progress

27th Expenditure
of ₹ 150126 (1.50 Lacs ) done.
Cummulative ₹ 23.14Lacs ( against 88.2Lacs )