Work Sanctioned
जनपद टिहरी गढ़वाल के विकास खण्ड़ कीर्तिनगर के अन्तर्गत जैधार बैण्ड से माछनी मोटर मार्ग का नवनिर्माण।
on Wednesday, March 30th 2022, 6:30:00 pm
25.35%
Financial Progress
1st Expenditure
of ₹ 343000 (3.43 Lacs ) done.
Cummulative ₹ 3.43Lacs ( against 13.53Lacs )
on Monday, June 19th 2023, 6:30:00 pm
59.25%
Financial Progress
2nd Expenditure
of ₹ 458625 (4.59 Lacs ) done.
Cummulative ₹ 8.02Lacs ( against 13.53Lacs )
on Thursday, June 29th 2023, 6:30:00 pm
65.07%
Financial Progress
3rd Expenditure
of ₹ 78758 (0.79 Lacs ) done.
Cummulative ₹ 8.80Lacs ( against 13.53Lacs )
on Sunday, July 9th 2023, 6:30:00 pm
101.68%
Financial Progress
4th Expenditure
of ₹ 495393 (4.95 Lacs ) done.
Cummulative ₹ 13.76Lacs ( against 13.53Lacs )
on Tuesday, January 30th 2024, 6:30:00 pm
31.17%
Financial Progress
5th Expenditure
of ₹ -954000 (-9.54 Lacs ) done.
Cummulative ₹ 4.22Lacs ( against 13.53Lacs )
on Wednesday, April 17th 2024, 6:30:00 pm
57.53%
Financial Progress
6th Expenditure
of ₹ 356585 (3.57 Lacs ) done.
Cummulative ₹ 7.78Lacs ( against 13.53Lacs )
on Wednesday, April 17th 2024, 6:30:00 pm
67.58%
Financial Progress
7th Expenditure
of ₹ 135956 (1.36 Lacs ) done.
Cummulative ₹ 9.14Lacs ( against 13.53Lacs )
on Monday, April 29th 2024, 6:30:00 pm
31.17%
Financial Progress
8th Expenditure
of ₹ -492541 (-4.93 Lacs ) done.
Cummulative ₹ 4.22Lacs ( against 13.53Lacs )
on Sunday, July 14th 2024, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, October 23rd 2024, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, March 26th 2025, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, May 13th 2025, 6:30:00 pm
61.25%
Financial Progress
9th Expenditure
of ₹ 406965 (4.07 Lacs ) done.
Cummulative ₹ 8.29Lacs ( against 13.53Lacs )