3 years ago

on Monday, March 28th 2022, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2022-23 में राज्य योजना के अन्तर्गत (मिसिंग लिंक) जनपद टिहरी गढ़वाल के विधान सभा क्षेत्र देवप्रयाग के विकास खण्ड़ देवप्रयाग में हिण्ड़ोलाखाल पलेठी मुल्यागांव मोटर मार्ग के चैनेज 6.350 से 10.850 में क्राॅस ड्रैनेज के अन्तर्गत 1 मीटर स्पान आर0सी0सी0 स्कपर का निर्माण कार्य। (विस्तृत आगणन)

2 years ago

on Friday, March 31st 2023, 12:26:42 pm

Technical Sanction
of ₹ 56.03 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 511/1C Dt. 31.03.2023

2 years ago

on Thursday, September 28th 2023, 6:30:00 pm
7.35%
Financial Progress

1st Expenditure
of ₹ 411782 (4.12 Lacs ) done.
Cummulative ₹ 4.12Lacs ( against 56.03Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
18.71%
Financial Progress

2nd Expenditure
of ₹ 636476 (6.36 Lacs ) done.
Cummulative ₹ 10.48Lacs ( against 56.03Lacs )

2 years ago

on Wednesday, October 4th 2023, 6:30:00 pm
21%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
29.88%
Financial Progress

3rd Expenditure
of ₹ 625838 (6.26 Lacs ) done.
Cummulative ₹ 16.74Lacs ( against 56.03Lacs )

2 years ago

on Sunday, November 26th 2023, 6:30:00 pm
63.99%
Financial Progress

5th Expenditure
of ₹ 930863 (9.31 Lacs ) done.
Cummulative ₹ 35.85Lacs ( against 56.03Lacs )

2 years ago

on Sunday, November 26th 2023, 6:30:00 pm
47.38%
Financial Progress

4th Expenditure
of ₹ 980387 (9.80 Lacs ) done.
Cummulative ₹ 26.54Lacs ( against 56.03Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
62.76%
Financial Progress

6th Expenditure
of ₹ -69000 (-0.69 Lacs ) done.
Cummulative ₹ 35.16Lacs ( against 56.03Lacs )

2 years ago

on Friday, December 1st 2023, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Wednesday, January 3rd 2024, 6:30:00 pm
73.37%
Financial Progress

7th Expenditure
of ₹ 594557 (5.95 Lacs ) done.
Cummulative ₹ 41.11Lacs ( against 56.03Lacs )

2 years ago

on Wednesday, January 3rd 2024, 6:30:00 pm
87.56%
Financial Progress

8th Expenditure
of ₹ 794956 (7.95 Lacs ) done.
Cummulative ₹ 49.06Lacs ( against 56.03Lacs )

2 years ago

on Sunday, January 28th 2024, 6:30:00 pm
96.14%
Financial Progress

9th Expenditure
of ₹ 480605 (4.81 Lacs ) done.
Cummulative ₹ 53.86Lacs ( against 56.03Lacs )

2 years ago

on Wednesday, February 21st 2024, 6:30:00 pm
96.43%
Financial Progress

10th Expenditure
of ₹ 16600 (0.17 Lacs ) done.
Cummulative ₹ 54.03Lacs ( against 56.03Lacs )

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
97.68%
Financial Progress

11th Expenditure
of ₹ 69710 (0.70 Lacs ) done.
Cummulative ₹ 54.73Lacs ( against 56.03Lacs )

a year ago

on Sunday, May 26th 2024, 6:30:00 pm
98.99%
Financial Progress

12th Expenditure
of ₹ 73425 (0.73 Lacs ) done.
Cummulative ₹ 55.46Lacs ( against 56.03Lacs )

a year ago

on Sunday, October 13th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time