Refresh data
on Sunday, May 25th 2014, 6:30:00 pm
Work Sanctioned
जनपद टिहरी गढवाल के विधानसभा क्षेत्र धनोल्टी में मसोन-काण्डी-द्वारगढ पर जयद्वार से सुरांशु तक मोटर मार्ग का नवनिर्माण।
on Saturday, January 31st 2015, 6:30:00 pm
0.27%
Financial Progress
1st Expenditure
of ₹ 10290 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 38.65Lacs )
on Sunday, May 31st 2015, 6:30:00 pm
3.57%
Financial Progress
2nd Expenditure
of ₹ 127864 (1.28 Lacs ) done.
Cummulative ₹ 1.38Lacs ( against 38.65Lacs )
on Tuesday, December 13th 2016, 6:30:00 pm
Technical Sanction
of ₹ 38.65 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE-1922/1C
on Sunday, February 5th 2023, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, January 15th 2025, 8:07:22 am
PWD UttarakahndPhoto (ID 62767) from Site Received
Uploader : Maneesh Chauhan, Additional Assistant Engineer Civil ,TD Thatyur
Landmark : ग्रामवासियो के साथ बैठक
Remark : ग्रामवासियो के साथ बैठक
on Sunday, March 9th 2025, 8:54:03 am
PWD UttarakahndPhoto (ID 65612) from Site Received
Uploader : Maneesh Chauhan, Additional Assistant Engineer Civil ,TD Thatyur
Landmark : At surasu village
Remark : Survey work for aligment
on Friday, April 25th 2025, 6:22:49 am
PWD UttarakahndPhoto (ID 68150) from Site Received
Uploader : Madan Mohan Joshi, Assistant Engineer Civil ,TD Thatyur
Landmark : 0.00
Remark : Starting point of Alignment