8 years ago

on Tuesday, February 6th 2018, 6:30:00 pm
Work Sanctioned
जनपद टिहरी गढवाल के विधानसभा क्षेत्र धनौल्टी के अन्तर्गत मुनोग मोटर मार्ग का पुनःनिर्माण एवं डामरीकरण का कार्य ।द्वितीय चरण

8 years ago

on Wednesday, March 14th 2018, 6:30:00 pm

Technical Sanction
of ₹ 66.04 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE-445/1C

7 years ago

on Monday, April 30th 2018, 6:30:00 pm
0.12%
Financial Progress

1st Expenditure
of ₹ 7831 (0.08 Lacs ) done.
Cummulative ₹ 0.08Lacs ( against 66.04Lacs )

7 years ago

on Thursday, May 31st 2018, 6:30:00 pm
0.35%
Financial Progress

2nd Expenditure
of ₹ 15470 (0.15 Lacs ) done.
Cummulative ₹ 0.23Lacs ( against 66.04Lacs )

7 years ago

on Saturday, June 30th 2018, 6:30:00 pm
0.61%
Financial Progress

3rd Expenditure
of ₹ 16800 (0.17 Lacs ) done.
Cummulative ₹ 0.40Lacs ( against 66.04Lacs )

7 years ago

on Wednesday, October 31st 2018, 6:30:00 pm
1.06%
Financial Progress

4th Expenditure
of ₹ 29773 (0.30 Lacs ) done.
Cummulative ₹ 0.70Lacs ( against 66.04Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
1.99%
Financial Progress

5th Expenditure
of ₹ 61312 (0.61 Lacs ) done.
Cummulative ₹ 1.31Lacs ( against 66.04Lacs )

6 years ago

on Thursday, October 31st 2019, 6:30:00 pm
2.22%
Financial Progress

6th Expenditure
of ₹ 15150 (0.15 Lacs ) done.
Cummulative ₹ 1.46Lacs ( against 66.04Lacs )

6 years ago

on Friday, January 31st 2020, 6:30:00 pm
10.66%
Financial Progress

7th Expenditure
of ₹ 557940 (5.58 Lacs ) done.
Cummulative ₹ 7.04Lacs ( against 66.04Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
23.86%
Financial Progress

8th Expenditure
of ₹ 871564 (8.72 Lacs ) done.
Cummulative ₹ 15.76Lacs ( against 66.04Lacs )

5 years ago

on Sunday, January 31st 2021, 6:30:00 pm
24.41%
Financial Progress

9th Expenditure
of ₹ 36350 (0.36 Lacs ) done.
Cummulative ₹ 16.12Lacs ( against 66.04Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
30.44%
Financial Progress

10th Expenditure
of ₹ 398316 (3.98 Lacs ) done.
Cummulative ₹ 20.11Lacs ( against 66.04Lacs )

4 years ago

on Tuesday, June 29th 2021, 6:30:00 pm
30.77%
Financial Progress

11th Expenditure
of ₹ 21806 (0.22 Lacs ) done.
Cummulative ₹ 20.32Lacs ( against 66.04Lacs )

4 years ago

on Thursday, December 30th 2021, 6:30:00 pm
33.96%
Financial Progress

12th Expenditure
of ₹ 210149 (2.10 Lacs ) done.
Cummulative ₹ 22.42Lacs ( against 66.04Lacs )

4 years ago

on Sunday, February 27th 2022, 6:30:00 pm
36.05%
Financial Progress

13th Expenditure
of ₹ 137986 (1.38 Lacs ) done.
Cummulative ₹ 23.80Lacs ( against 66.04Lacs )

3 years ago

on Sunday, February 5th 2023, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
36.78%
Financial Progress

14th Expenditure
of ₹ 48642 (0.49 Lacs ) done.
Cummulative ₹ 24.29Lacs ( against 66.04Lacs )

2 years ago

on Thursday, March 21st 2024, 6:30:00 pm
38.14%
Financial Progress

15th Expenditure
of ₹ 89952 (0.90 Lacs ) done.
Cummulative ₹ 25.19Lacs ( against 66.04Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Friday, July 19th 2024, 6:30:00 pm
54.09%
Financial Progress

16th Expenditure
of ₹ 1052800 (10.53 Lacs ) done.
Cummulative ₹ 35.72Lacs ( against 66.04Lacs )

9 months ago

on Thursday, December 19th 2024, 6:30:00 pm
54.09%
Financial Progress

17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 35.72Lacs ( against 66.04Lacs )

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
54.37%
Financial Progress

18th Expenditure
of ₹ 18531 (0.19 Lacs ) done.
Cummulative ₹ 35.90Lacs ( against 66.04Lacs )

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
54.62%
Financial Progress

19th Expenditure
of ₹ 16917 (0.17 Lacs ) done.
Cummulative ₹ 36.07Lacs ( against 66.04Lacs )

8 months ago

on Thursday, January 23rd 2025, 6:30:00 pm
54.83%
Financial Progress

20th Expenditure
of ₹ 13460 (0.13 Lacs ) done.
Cummulative ₹ 36.21Lacs ( against 66.04Lacs )

7 months ago

on Monday, February 17th 2025, 6:30:00 pm
58.22%
Financial Progress

21st Expenditure
of ₹ 224200 (2.24 Lacs ) done.
Cummulative ₹ 38.45Lacs ( against 66.04Lacs )

7 months ago

on Thursday, February 27th 2025, 6:30:00 pm
58.22%
Financial Progress

22nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 38.45Lacs ( against 66.04Lacs )

6 months ago

on Sunday, April 6th 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 3rd time

4 months ago

on Monday, May 26th 2025, 6:30:00 pm
59.16%
Financial Progress

23rd Expenditure
of ₹ 62208 (0.62 Lacs ) done.
Cummulative ₹ 39.07Lacs ( against 66.04Lacs )

4 months ago

on Tuesday, May 27th 2025, 6:30:00 pm
71.91%
Financial Progress

24th Expenditure
of ₹ 841796 (8.42 Lacs ) done.
Cummulative ₹ 47.49Lacs ( against 66.04Lacs )

4 months ago

on Thursday, May 29th 2025, 6:30:00 pm
88.53%
Financial Progress

25th Expenditure
of ₹ 1097600 (10.98 Lacs ) done.
Cummulative ₹ 58.47Lacs ( against 66.04Lacs )

2 months ago

on Tuesday, July 22nd 2025, 6:30:00 pm
90.50%
Financial Progress

26th Expenditure
of ₹ 129994 (1.30 Lacs ) done.
Cummulative ₹ 59.77Lacs ( against 66.04Lacs )

2 months ago

on Monday, July 28th 2025, 6:30:00 pm
97.43%
Financial Progress

27th Expenditure
of ₹ 457848 (4.58 Lacs ) done.
Cummulative ₹ 64.34Lacs ( against 66.04Lacs )

a month ago

on Tuesday, August 19th 2025, 6:30:00 pm
97.80%
Financial Progress

28th Expenditure
of ₹ 24000 (0.24 Lacs ) done.
Cummulative ₹ 64.58Lacs ( against 66.04Lacs )