Refresh data
on Tuesday, December 19th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद टिहरी गढ़वाल में जौनपुर वि0ख0 में लालपुल-भुत्सी मोटर मार्ग के कि0मी0 04 है0मी0 (8-10)में स्टील गर्डर मोटर सेतु का पहुंच मार्ग सहित निर्माण कार्य (12.00 मी0 आर0सी0सी0 क्षतिग्रस्त सेतु के स्थान पर) (प्रथम चरण) (RFQ एवं TOR के अनुसार)
on Tuesday, March 19th 2024, 6:30:00 pm
0.92%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 10.92Lacs )
on Sunday, March 31st 2024, 6:30:00 pm
1%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, September 3rd 2024, 6:30:00 pm
0.92%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 10.92Lacs )
on Thursday, September 12th 2024, 6:30:00 pm
32.97%
Financial Progress
3rd Expenditure
of ₹ 350000 (3.50 Lacs ) done.
Cummulative ₹ 3.60Lacs ( against 10.92Lacs )
on Friday, September 27th 2024, 7:12:21 am
PWD UttarakahndPhoto (ID 53474) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km 04
Remark : Km 04 bridge location
on Friday, September 27th 2024, 7:16:15 am
PWD UttarakahndPhoto (ID 53475) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km04
Remark : लाल पुल साइड abutment view
on Friday, September 27th 2024, 7:18:18 am
PWD UttarakahndPhoto (ID 53476) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km04
Remark : भुतसी साइड abutment view
on Friday, September 27th 2024, 7:20:47 am
PWD UttarakahndPhoto (ID 53477) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km04
Remark : Bridge location
on Friday, November 29th 2024, 6:30:00 pm
68.23%
Financial Progress
4th Expenditure
of ₹ 385100 (3.85 Lacs ) done.
Cummulative ₹ 7.45Lacs ( against 10.92Lacs )
on Wednesday, December 4th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time