on Tuesday, December 19th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद टिहरी गढ़वाल में जौनपुर वि0ख0 में लालपुल-भुत्सी मोटर मार्ग के कि0मी0 04 है0मी0 (8-10)में स्टील गर्डर मोटर सेतु का पहुंच मार्ग सहित निर्माण कार्य (12.00 मी0 आर0सी0सी0 क्षतिग्रस्त सेतु के स्थान पर) (प्रथम चरण) (RFQ एवं TOR के अनुसार)

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
0.92%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 10.92Lacs )

a year ago

on Sunday, March 31st 2024, 6:30:00 pm
1%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Tuesday, September 3rd 2024, 6:30:00 pm
0.92%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 10.92Lacs )

a year ago

on Thursday, September 12th 2024, 6:30:00 pm
32.97%
Financial Progress

3rd Expenditure
of ₹ 350000 (3.50 Lacs ) done.
Cummulative ₹ 3.60Lacs ( against 10.92Lacs )

a year ago

on Friday, September 27th 2024, 7:12:21 am
<span class="4">Picture Id:53474</span>
PWD Uttarakahnd
Photo (ID 53474) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km 04
Remark : Km 04 bridge location

a year ago

on Friday, September 27th 2024, 7:16:15 am
<span class="4">Picture Id:53475</span>
PWD Uttarakahnd
Photo (ID 53475) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km04
Remark : लाल पुल साइड abutment view

a year ago

on Friday, September 27th 2024, 7:18:18 am
<span class="4">Picture Id:53476</span>
PWD Uttarakahnd
Photo (ID 53476) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km04
Remark : भुतसी साइड abutment view

a year ago

on Friday, September 27th 2024, 7:20:47 am
<span class="4">Picture Id:53477</span>
PWD Uttarakahnd
Photo (ID 53477) from Site Received
Uploader : Lokesh Kumar Saraswat, Executive Engineer Civil ,CD Baijro
Landmark : Km04
Remark : Bridge location

10 months ago

on Friday, November 29th 2024, 6:30:00 pm
68.23%
Financial Progress

4th Expenditure
of ₹ 385100 (3.85 Lacs ) done.
Cummulative ₹ 7.45Lacs ( against 10.92Lacs )

9 months ago

on Wednesday, December 4th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors