Work Sanctioned
महाकालेश्वर-बसभीड़ा मोटर मार्ग का निर्माण।

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
3.66%
Financial Progress

1st Expenditure
of ₹ 651323 (6.51 Lacs ) done.
Cummulative ₹ 6.51Lacs ( against 178Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
4.24%
Financial Progress

2nd Expenditure
of ₹ 104098 (1.04 Lacs ) done.
Cummulative ₹ 7.55Lacs ( against 178Lacs )

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
4.42%
Financial Progress

3rd Expenditure
of ₹ 31470 (0.31 Lacs ) done.
Cummulative ₹ 7.87Lacs ( against 178Lacs )

2 years ago

on Saturday, March 30th 2024, 6:30:00 pm
5.30%
Financial Progress

4th Expenditure
of ₹ 157119 (1.57 Lacs ) done.
Cummulative ₹ 9.44Lacs ( against 178Lacs )