@
Refresh data
Refresh data

4 years ago

on Wednesday, January 5th 2022, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद अल्मोड़ा के विधान सभा क्षेत्र द्वाराहाट के अन्तर्गत गनोली-बावन मोटर मार्ग का सुधारीकरण एवं डामरीकरण का कार्य (द्वितीय चरण

3 years ago

on Saturday, January 21st 2023, 6:42:30 am

Technical Sanction
of ₹ 241.61 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 37/101yata-a/2022

3 years ago

on Thursday, March 30th 2023, 6:30:00 pm
0.06%
Financial Progress

1st Expenditure
of ₹ 16226 (0.16 Lacs ) done.
Cummulative ₹ 0.16Lacs ( against 258.75Lacs )

2 years ago

on Monday, September 11th 2023, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
15.64%
Financial Progress

2nd Expenditure
of ₹ 4031758 (40.32 Lacs ) done.
Cummulative ₹ 40.48Lacs ( against 258.75Lacs )

2 years ago

on Wednesday, October 4th 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
15.98%
Financial Progress

3rd Expenditure
of ₹ 87352 (0.87 Lacs ) done.
Cummulative ₹ 41.35Lacs ( against 258.75Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
33.59%
Financial Progress

4th Expenditure
of ₹ 4555935 (45.56 Lacs ) done.
Cummulative ₹ 86.91Lacs ( against 258.75Lacs )

2 years ago

on Sunday, December 3rd 2023, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Thursday, January 11th 2024, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Sunday, January 14th 2024, 6:30:00 pm
42.42%
Financial Progress

5th Expenditure
of ₹ 2285736 (22.86 Lacs ) done.
Cummulative ₹ 109.77Lacs ( against 258.75Lacs )

2 years ago

on Wednesday, January 17th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 5th time

2 years ago

on Friday, February 16th 2024, 6:30:00 pm
50.76%
Financial Progress

6th Expenditure
of ₹ 2156098 (21.56 Lacs ) done.
Cummulative ₹ 131.33Lacs ( against 258.75Lacs )

2 years ago

on Tuesday, March 5th 2024, 6:30:00 pm
54.21%
Financial Progress

7th Expenditure
of ₹ 894831 (8.95 Lacs ) done.
Cummulative ₹ 140.28Lacs ( against 258.75Lacs )

a year ago

on Saturday, June 29th 2024, 6:30:00 pm
61.06%
Financial Progress

8th Expenditure
of ₹ 1770727 (17.71 Lacs ) done.
Cummulative ₹ 157.99Lacs ( against 258.75Lacs )

a year ago

on Saturday, July 13th 2024, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 6th time

a year ago

on Tuesday, July 30th 2024, 6:30:00 pm
61.46%
Financial Progress

9th Expenditure
of ₹ 104909 (1.05 Lacs ) done.
Cummulative ₹ 159.04Lacs ( against 258.75Lacs )

a year ago

on Tuesday, September 10th 2024, 6:30:00 pm
64.65%
Financial Progress

10th Expenditure
of ₹ 823881 (8.24 Lacs ) done.
Cummulative ₹ 167.27Lacs ( against 258.75Lacs )

a year ago

on Thursday, October 17th 2024, 9:07:21 am
<span class="4">Picture Id:57206</span>
PWD Uttarakahnd
Photo (ID 57206) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : At km 3.50
Remark : OGPC work is being done at km 3.500km

a year ago

on Thursday, October 17th 2024, 9:10:01 am
<span class="4">Picture Id:57207</span>
PWD Uttarakahnd
Photo (ID 57207) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : At ch 3.600km
Remark : OGPC work is being done at km 3.600km

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
72.80%
Financial Progress

11th Expenditure
of ₹ 2109213 (21.09 Lacs ) done.
Cummulative ₹ 188.37Lacs ( against 258.75Lacs )

a year ago

on Monday, October 28th 2024, 10:14:00 am
<span class="4">Picture Id:58360</span>
PWD Uttarakahnd
Photo (ID 58360) from Site Received
Uploader : Kuldeep Singh , Junior Engineer Civil ,CD Ranikhet
Landmark : Ch. 2.76 Km.
Remark : PC work at Km 2.76

a year ago

on Monday, October 28th 2024, 11:01:14 am
<span class="4">Picture Id:58372</span>
PWD Uttarakahnd
Photo (ID 58372) from Site Received
Uploader : Kuldeep Singh , Junior Engineer Civil ,CD Ranikhet
Landmark : Ch. 2.700 km
Remark : Seal Coat work at ch 2.700 Km.

a year ago

on Tuesday, November 5th 2024, 8:27:18 am
<span class="4">Picture Id:58492</span>
PWD Uttarakahnd
Photo (ID 58492) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : At km 2.500
Remark : PC work in progress at km 2.500

a year ago

on Saturday, November 16th 2024, 7:10:43 am
<span class="4">Picture Id:59028</span>
PWD Uttarakahnd
Photo (ID 59028) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : At km 2.425
Remark : OGPC work

a year ago

on Wednesday, November 20th 2024, 8:29:32 am
<span class="4">Picture Id:59755</span>
PWD Uttarakahnd
Photo (ID 59755) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : 1st km
Remark : OGPC work of Ganoli to Baban MR

a year ago

on Wednesday, November 20th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 7th time

10 months ago

on Thursday, November 28th 2024, 6:32:42 am
<span class="4">Picture Id:59758</span>
PWD Uttarakahnd
Photo (ID 59758) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : At km 4.00 end Point
Remark : End point of the MR

10 months ago

on Tuesday, December 3rd 2024, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 8th time

10 months ago

on Thursday, December 12th 2024, 9:13:39 am
<span class="4">Picture Id:61060</span>
PWD Uttarakahnd
Photo (ID 61060) from Site Received
Uploader : Tula Ram, Assistant Engineer Civil ,CD Ranikhet
Landmark : At
Remark : Carriage way at km 3.800

10 months ago

on Friday, December 20th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 9th time

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
86.69%
Financial Progress

12th Expenditure
of ₹ 3594931 (35.95 Lacs ) done.
Cummulative ₹ 224.32Lacs ( against 258.75Lacs )

8 months ago

on Thursday, January 30th 2025, 6:30:00 pm
86.79%
Financial Progress

13th Expenditure
of ₹ 24800 (0.25 Lacs ) done.
Cummulative ₹ 224.56Lacs ( against 258.75Lacs )

7 months ago

on Thursday, February 27th 2025, 6:30:00 pm
91.19%
Financial Progress

14th Expenditure
of ₹ 1138109 (11.38 Lacs ) done.
Cummulative ₹ 235.95Lacs ( against 258.75Lacs )

6 months ago

on Sunday, March 30th 2025, 6:30:00 pm
91.71%
Financial Progress

15th Expenditure
of ₹ 134709 (1.35 Lacs ) done.
Cummulative ₹ 237.29Lacs ( against 258.75Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors