Refresh data
Refresh data

7 months ago

on Thursday, February 6th 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र मसूरी के मोतीलाल नेहरू मार्ग में डी.बी.एम./बी.सी. द्वारा मार्ग की सतह सुधार का कार्य।

6 months ago

on Monday, March 17th 2025, 6:30:00 pm
0.42%
Financial Progress

1st Expenditure
of ₹ 114224 (1.14 Lacs ) done.
Cummulative ₹ 1.14Lacs ( against 273.43Lacs )

6 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
0.44%
Financial Progress

2nd Expenditure
of ₹ 7000 (0.07 Lacs ) done.
Cummulative ₹ 1.21Lacs ( against 273.43Lacs )

6 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
29.65%
Financial Progress

4th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 81.08Lacs ( against 273.43Lacs )

6 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
29.54%
Financial Progress

3rd Expenditure
of ₹ 7955553 (79.56 Lacs ) done.
Cummulative ₹ 80.77Lacs ( against 273.43Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
29.88%
Financial Progress

5th Expenditure
of ₹ 62664 (0.63 Lacs ) done.
Cummulative ₹ 81.70Lacs ( against 273.43Lacs )

5 months ago

on Thursday, April 10th 2025, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 1st time

4 months ago

on Thursday, May 8th 2025, 6:30:00 pm
29.92%
Financial Progress

6th Expenditure
of ₹ 10030 (0.10 Lacs ) done.
Cummulative ₹ 81.80Lacs ( against 273.43Lacs )

4 months ago

on Wednesday, May 21st 2025, 6:30:00 pm
29.96%
Financial Progress

7th Expenditure
of ₹ 12390 (0.12 Lacs ) done.
Cummulative ₹ 81.93Lacs ( against 273.43Lacs )

4 months ago

on Friday, May 30th 2025, 6:30:00 pm
36.34%
Financial Progress

8th Expenditure
of ₹ 1744187 (17.44 Lacs ) done.
Cummulative ₹ 99.37Lacs ( against 273.43Lacs )

4 months ago

on Friday, May 30th 2025, 6:30:00 pm
47.49%
Financial Progress

9th Expenditure
of ₹ 3048597 (30.49 Lacs ) done.
Cummulative ₹ 129.86Lacs ( against 273.43Lacs )

4 months ago

on Monday, June 2nd 2025, 6:30:00 pm
48.59%
Financial Progress

11th Expenditure
of ₹ 51072 (0.51 Lacs ) done.
Cummulative ₹ 132.86Lacs ( against 273.43Lacs )

4 months ago

on Monday, June 2nd 2025, 6:30:00 pm
48.40%
Financial Progress

10th Expenditure
of ₹ 249652 (2.50 Lacs ) done.
Cummulative ₹ 132.35Lacs ( against 273.43Lacs )

3 months ago

on Thursday, June 5th 2025, 6:30:00 pm
48.85%
Financial Progress

13th Expenditure
of ₹ 36580 (0.37 Lacs ) done.
Cummulative ₹ 133.56Lacs ( against 273.43Lacs )

3 months ago

on Thursday, June 5th 2025, 6:30:00 pm
48.71%
Financial Progress

12th Expenditure
of ₹ 32922 (0.33 Lacs ) done.
Cummulative ₹ 133.19Lacs ( against 273.43Lacs )

3 months ago

on Tuesday, July 1st 2025, 6:30:00 pm
62.79%
Financial Progress

15th Expenditure
of ₹ 35400 (0.35 Lacs ) done.
Cummulative ₹ 171.67Lacs ( against 273.43Lacs )

3 months ago

on Tuesday, July 1st 2025, 6:30:00 pm
62.66%
Financial Progress

14th Expenditure
of ₹ 3776157 (37.76 Lacs ) done.
Cummulative ₹ 171.32Lacs ( against 273.43Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
62.97%
Financial Progress

16th Expenditure
of ₹ 49500 (0.49 Lacs ) done.
Cummulative ₹ 172.17Lacs ( against 273.43Lacs )

2 months ago

on Sunday, July 13th 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 2nd time

2 months ago

on Sunday, July 20th 2025, 6:30:00 pm
63.21%
Financial Progress

17th Expenditure
of ₹ 66000 (0.66 Lacs ) done.
Cummulative ₹ 172.83Lacs ( against 273.43Lacs )

a month ago

on Thursday, August 7th 2025, 6:30:00 pm
64.00%
Financial Progress

18th Expenditure
of ₹ 217438 (2.17 Lacs ) done.
Cummulative ₹ 175.00Lacs ( against 273.43Lacs )

a month ago

on Thursday, August 7th 2025, 6:30:00 pm
64.19%
Financial Progress

19th Expenditure
of ₹ 51923 (0.52 Lacs ) done.
Cummulative ₹ 175.52Lacs ( against 273.43Lacs )

a month ago

on Tuesday, August 12th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 3rd time

a month ago

on Tuesday, August 19th 2025, 6:30:00 pm
64.62%
Financial Progress

20th Expenditure
of ₹ 118000 (1.18 Lacs ) done.
Cummulative ₹ 176.70Lacs ( against 273.43Lacs )

25 days ago

on Sunday, August 24th 2025, 6:30:00 pm
64.74%
Financial Progress

21st Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 177.01Lacs ( against 273.43Lacs )
Loading...

AI layer

AI Road
AI Bridge
5000 km
3000 mi
Unavailable