Refresh data
on Monday, February 27th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत चकराता-लाखामण्डल मोटर मार्ग राज्य मार्ग सं0-18, के कि.मी. 24 चै0सं0 23.050 पर (समोग पुल)में पूर्व में निर्मित क्लास ‘बी‘ लोडिंग सेतु के स्थान पर क्लास ‘ए‘ लोडिंग (डेढ़ लेन )सेतु का निर्माण कार्य (स्पान 12मी0)(प्रथम चरण)।
on Thursday, March 30th 2023, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 3.6Lacs )
on Wednesday, August 30th 2023, 6:30:00 pm
8.41%
Financial Progress
2nd Expenditure
of ₹ 30270 (0.30 Lacs ) done.
Cummulative ₹ 0.30Lacs ( against 3.6Lacs )
on Friday, September 29th 2023, 6:30:00 pm
12.61%
Financial Progress
3rd Expenditure
of ₹ 15135 (0.15 Lacs ) done.
Cummulative ₹ 0.45Lacs ( against 3.6Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
53.47%
Financial Progress
4th Expenditure
of ₹ 147083 (1.47 Lacs ) done.
Cummulative ₹ 1.92Lacs ( against 3.6Lacs )
on Tuesday, April 30th 2024, 6:30:00 pm
53%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, July 18th 2024, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, December 25th 2024, 6:30:00 pm
61.49%
Financial Progress
5th Expenditure
of ₹ 28873 (0.29 Lacs ) done.
Cummulative ₹ 2.21Lacs ( against 3.6Lacs )
on Thursday, February 27th 2025, 6:30:00 pm
63.21%
Financial Progress
6th Expenditure
of ₹ 6203 (0.06 Lacs ) done.
Cummulative ₹ 2.28Lacs ( against 3.6Lacs )