7 months ago

on Sunday, February 23rd 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र चकराता में खारसी मोटर मार्ग के कि.मी.-25 से चैमा होते हुए नई खारसी मोटर मार्ग हरिजन बस्ती गेहरी में जोड़ने हेतु मोटर मार्ग का नवनिर्माण कार्य (द्वितीय चरण स्टेज-।,)।

6 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
0.12%
Financial Progress

1st Expenditure
of ₹ 20000 (0.20 Lacs ) done.
Cummulative ₹ 0.20Lacs ( against 165.44Lacs )

5 months ago

on Sunday, April 27th 2025, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

3 months ago

on Sunday, June 29th 2025, 6:30:00 pm
4.25%
Financial Progress

2nd Expenditure
of ₹ 683310 (6.83 Lacs ) done.
Cummulative ₹ 7.03Lacs ( against 165.44Lacs )

2 months ago

on Sunday, July 27th 2025, 6:30:00 pm
4.71%
Financial Progress

3rd Expenditure
of ₹ 76658 (0.77 Lacs ) done.
Cummulative ₹ 7.80Lacs ( against 165.44Lacs )