Refresh data
Refresh data

5 years ago

on Monday, January 18th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र डोईवाला में घुत्तु गन्धकपानी तक मोटर मार्ग का निर्माण कार्य। (द्वारा-प्लेड-लडवाकोट-घुत्तु गन्धकपानी)

4 years ago

on Tuesday, August 3rd 2021, 8:26:19 am

Technical Sanction
of ₹ 970.9 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2825/09(384) Yata-Ster-I (Zone Off.)/2021

4 years ago

on Thursday, March 24th 2022, 6:30:00 pm
18.97%
Financial Progress

1st Expenditure
of ₹ 19761342 (197.61 Lacs ) done.
Cummulative ₹ 197.61Lacs ( against 1041.67Lacs )

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
22.56%
Financial Progress

3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 234.99Lacs ( against 1041.67Lacs )

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
22.56%
Financial Progress

2nd Expenditure
of ₹ 3737406 (37.37 Lacs ) done.
Cummulative ₹ 234.99Lacs ( against 1041.67Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
22.59%
Financial Progress

4th Expenditure
of ₹ 29475 (0.29 Lacs ) done.
Cummulative ₹ 235.28Lacs ( against 1041.67Lacs )

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
27.09%
Financial Progress

6th Expenditure
of ₹ 4621391 (46.21 Lacs ) done.
Cummulative ₹ 282.19Lacs ( against 1041.67Lacs )

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
22.65%
Financial Progress

5th Expenditure
of ₹ 68991 (0.69 Lacs ) done.
Cummulative ₹ 235.97Lacs ( against 1041.67Lacs )

3 years ago

on Tuesday, August 2nd 2022, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
27.25%
Financial Progress

8th Expenditure
of ₹ 159180 (1.59 Lacs ) done.
Cummulative ₹ 283.89Lacs ( against 1041.67Lacs )

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
27.10%
Financial Progress

7th Expenditure
of ₹ 11200 (0.11 Lacs ) done.
Cummulative ₹ 282.30Lacs ( against 1041.67Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
29.28%
Financial Progress

10th Expenditure
of ₹ 2105918 (21.06 Lacs ) done.
Cummulative ₹ 304.95Lacs ( against 1041.67Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
27.25%
Financial Progress

9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 283.89Lacs ( against 1041.67Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
29.29%
Financial Progress

11th Expenditure
of ₹ 14998 (0.15 Lacs ) done.
Cummulative ₹ 305.10Lacs ( against 1041.67Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
29.49%
Financial Progress

12th Expenditure
of ₹ 206603 (2.07 Lacs ) done.
Cummulative ₹ 307.17Lacs ( against 1041.67Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
29.51%
Financial Progress

13th Expenditure
of ₹ 19647 (0.20 Lacs ) done.
Cummulative ₹ 307.36Lacs ( against 1041.67Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
30.54%
Financial Progress

14th Expenditure
of ₹ 1071878 (10.72 Lacs ) done.
Cummulative ₹ 318.08Lacs ( against 1041.67Lacs )

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
30.56%
Financial Progress

15th Expenditure
of ₹ 28422 (0.28 Lacs ) done.
Cummulative ₹ 318.36Lacs ( against 1041.67Lacs )

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
30.84%
Financial Progress

16th Expenditure
of ₹ 289856 (2.90 Lacs ) done.
Cummulative ₹ 321.26Lacs ( against 1041.67Lacs )

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
41.82%
Financial Progress

17th Expenditure
of ₹ 11434082 (114.34 Lacs ) done.
Cummulative ₹ 435.60Lacs ( against 1041.67Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
41.84%
Financial Progress

18th Expenditure
of ₹ 26980 (0.27 Lacs ) done.
Cummulative ₹ 435.87Lacs ( against 1041.67Lacs )

3 years ago

on Thursday, March 30th 2023, 6:30:00 pm
49.83%
Financial Progress

20th Expenditure
of ₹ 1259059 (12.59 Lacs ) done.
Cummulative ₹ 519.06Lacs ( against 1041.67Lacs )

3 years ago

on Thursday, March 30th 2023, 6:30:00 pm
48.62%
Financial Progress

19th Expenditure
of ₹ 7059930 (70.60 Lacs ) done.
Cummulative ₹ 506.47Lacs ( against 1041.67Lacs )

3 years ago

on Saturday, April 8th 2023, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Friday, June 16th 2023, 6:30:00 pm
50.79%
Financial Progress

21st Expenditure
of ₹ 997209 (9.97 Lacs ) done.
Cummulative ₹ 529.04Lacs ( against 1041.67Lacs )

2 years ago

on Monday, June 19th 2023, 6:30:00 pm
50.81%
Financial Progress

22nd Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 529.31Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, June 20th 2023, 6:30:00 pm
53.55%
Financial Progress

23rd Expenditure
of ₹ 2854979 (28.55 Lacs ) done.
Cummulative ₹ 557.86Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
55.24%
Financial Progress

24th Expenditure
of ₹ 1759718 (17.60 Lacs ) done.
Cummulative ₹ 575.46Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
55.43%
Financial Progress

25th Expenditure
of ₹ 197121 (1.97 Lacs ) done.
Cummulative ₹ 577.43Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
56.82%
Financial Progress

26th Expenditure
of ₹ 1447026 (14.47 Lacs ) done.
Cummulative ₹ 591.90Lacs ( against 1041.67Lacs )

2 years ago

on Sunday, July 30th 2023, 6:30:00 pm
56.82%
Financial Progress

27th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 591.90Lacs ( against 1041.67Lacs )

2 years ago

on Sunday, August 6th 2023, 6:30:00 pm
56.83%
Financial Progress

28th Expenditure
of ₹ 11800 (0.12 Lacs ) done.
Cummulative ₹ 592.02Lacs ( against 1041.67Lacs )

2 years ago

on Monday, August 21st 2023, 6:30:00 pm
57.07%
Financial Progress

29th Expenditure
of ₹ 248468 (2.48 Lacs ) done.
Cummulative ₹ 594.51Lacs ( against 1041.67Lacs )

2 years ago

on Monday, August 21st 2023, 6:30:00 pm
57.09%
Financial Progress

30th Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 594.71Lacs ( against 1041.67Lacs )

2 years ago

on Sunday, August 27th 2023, 6:30:00 pm
57.23%
Financial Progress

31st Expenditure
of ₹ 139359 (1.39 Lacs ) done.
Cummulative ₹ 596.10Lacs ( against 1041.67Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
57.23%
Financial Progress

32nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 596.10Lacs ( against 1041.67Lacs )

2 years ago

on Monday, September 11th 2023, 6:30:00 pm
53%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Monday, September 25th 2023, 6:30:00 pm
57.46%
Financial Progress

33rd Expenditure
of ₹ 246961 (2.47 Lacs ) done.
Cummulative ₹ 598.57Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
61.73%
Financial Progress

35th Expenditure
of ₹ 54900 (0.55 Lacs ) done.
Cummulative ₹ 643.04Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
61.75%
Financial Progress

36th Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 643.24Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
61.77%
Financial Progress

37th Expenditure
of ₹ 14647 (0.15 Lacs ) done.
Cummulative ₹ 643.39Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
61.82%
Financial Progress

38th Expenditure
of ₹ 59879 (0.60 Lacs ) done.
Cummulative ₹ 643.99Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
61.68%
Financial Progress

34th Expenditure
of ₹ 4391901 (43.92 Lacs ) done.
Cummulative ₹ 642.49Lacs ( against 1041.67Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
61.82%
Financial Progress

39th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 643.99Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
62.06%
Financial Progress

40th Expenditure
of ₹ 242518 (2.43 Lacs ) done.
Cummulative ₹ 646.41Lacs ( against 1041.67Lacs )

2 years ago

on Wednesday, November 15th 2023, 6:30:00 pm
66.29%
Financial Progress

41st Expenditure
of ₹ 4408492 (44.08 Lacs ) done.
Cummulative ₹ 690.50Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, November 16th 2023, 6:30:00 pm
66.31%
Financial Progress

42nd Expenditure
of ₹ 26444 (0.26 Lacs ) done.
Cummulative ₹ 690.76Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, November 16th 2023, 6:30:00 pm
66.33%
Financial Progress

43rd Expenditure
of ₹ 17563 (0.18 Lacs ) done.
Cummulative ₹ 690.94Lacs ( against 1041.67Lacs )

2 years ago

on Thursday, November 16th 2023, 6:30:00 pm
66.35%
Financial Progress

44th Expenditure
of ₹ 25958 (0.26 Lacs ) done.
Cummulative ₹ 691.20Lacs ( against 1041.67Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
66.35%
Financial Progress

45th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 691.20Lacs ( against 1041.67Lacs )

2 years ago

on Wednesday, December 13th 2023, 6:30:00 pm
66.48%
Financial Progress

46th Expenditure
of ₹ 125958 (1.26 Lacs ) done.
Cummulative ₹ 692.46Lacs ( against 1041.67Lacs )

2 years ago

on Sunday, December 17th 2023, 6:30:00 pm
66.48%
Financial Progress

47th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 692.46Lacs ( against 1041.67Lacs )

2 years ago

on Friday, February 16th 2024, 6:30:00 pm
66.48%
Financial Progress

48th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 692.46Lacs ( against 1041.67Lacs )

2 years ago

on Monday, February 19th 2024, 6:30:00 pm
71.29%
Financial Progress

49th Expenditure
of ₹ 5017382 (50.17 Lacs ) done.
Cummulative ₹ 742.63Lacs ( against 1041.67Lacs )

2 years ago

on Friday, March 15th 2024, 6:30:00 pm
74.77%
Financial Progress

50th Expenditure
of ₹ 3618068 (36.18 Lacs ) done.
Cummulative ₹ 778.81Lacs ( against 1041.67Lacs )

2 years ago

on Sunday, March 17th 2024, 6:30:00 pm
74.79%
Financial Progress

51st Expenditure
of ₹ 24414 (0.24 Lacs ) done.
Cummulative ₹ 779.06Lacs ( against 1041.67Lacs )

2 years ago

on Tuesday, March 19th 2024, 6:30:00 pm
75.01%
Financial Progress

52nd Expenditure
of ₹ 234802 (2.35 Lacs ) done.
Cummulative ₹ 781.40Lacs ( against 1041.67Lacs )

2 years ago

on Saturday, March 30th 2024, 6:30:00 pm
76.69%
Financial Progress

53rd Expenditure
of ₹ 1743574 (17.44 Lacs ) done.
Cummulative ₹ 798.84Lacs ( against 1041.67Lacs )

a year ago

on Monday, April 29th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Thursday, May 30th 2024, 6:30:00 pm
83%

Physical Progress
Physical Progress Reported at 6th time

a year ago

on Wednesday, June 5th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 7th time

a year ago

on Tuesday, July 2nd 2024, 6:30:00 pm
88%

Physical Progress
Physical Progress Reported at 8th time

a year ago

on Sunday, July 14th 2024, 6:30:00 pm
79.98%
Financial Progress

54th Expenditure
of ₹ 3430200 (34.30 Lacs ) done.
Cummulative ₹ 833.14Lacs ( against 1041.67Lacs )

a year ago

on Friday, August 16th 2024, 7:24:54 am
<span class="4">Picture Id:51966</span>
PWD Uttarakahnd
Photo (ID 51966) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Chainage 13/18 to 13/28
Remark : Road washed out due to heavy rain

a year ago

on Friday, August 16th 2024, 7:33:54 am
<span class="4">Picture Id:51967</span>
PWD Uttarakahnd
Photo (ID 51967) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Chainage, 13/20 to 13 /32
Remark : Road length about 375 mt washed out due Tu heavy rain from chainage 13/18 to, 13/30

a year ago

on Friday, August 16th 2024, 7:53:17 am
<span class="4">Picture Id:51971</span>
PWD Uttarakahnd
Photo (ID 51971) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Chainage 13/18 to 13/30
Remark : Road portion from chainage 13/18 to 13/30 washed due to heavy rain in area

a year ago

on Saturday, August 24th 2024, 8:02:40 am
<span class="4">Picture Id:52165</span>
PWD Uttarakahnd
Photo (ID 52165) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Km4 ghutu gandhak pani road
Remark : Road damage due to slip

a year ago

on Saturday, August 24th 2024, 8:24:55 am
<span class="4">Picture Id:52166</span>
PWD Uttarakahnd
Photo (ID 52166) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Km 5 ghutu gandhak pani road
Remark : Road length washed out in heavy rain

a year ago

on Saturday, August 24th 2024, 8:39:35 am
<span class="4">Picture Id:52168</span>
PWD Uttarakahnd
Photo (ID 52168) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Km 8 ghutu gandhak pani road
Remark : Road portion length, 35 mtr damaged

a year ago

on Saturday, August 24th 2024, 9:08:33 am
<span class="4">Picture Id:52172</span>
PWD Uttarakahnd
Photo (ID 52172) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Km12 ghutu gandhak pani road
Remark : Slip and land slide damaged road

a year ago

on Monday, September 2nd 2024, 8:12:57 am
<span class="4">Picture Id:52362</span>
PWD Uttarakahnd
Photo (ID 52362) from Site Received
Uploader : Makan Singh, Additional Assistant Engineer Civil ,TD Rishikesh
Landmark : Chainage, 6.450
Remark : Road portion washed out due to heavy rain

a year ago

on Monday, September 2nd 2024, 9:16:10 am
<span class="4">Picture Id:52363</span>
PWD Uttarakahnd
Photo (ID 52363) from Site Received
Uploader : Sandeep Semwal, Assistant Engineer Civil ,TD Rishikesh
Landmark : Km 13.450
Remark : Road portion wash out

a year ago

on Monday, September 2nd 2024, 9:21:31 am
<span class="4">Picture Id:52364</span>
PWD Uttarakahnd
Photo (ID 52364) from Site Received
Uploader : Sandeep Semwal, Assistant Engineer Civil ,TD Rishikesh
Landmark : Km 13.50
Remark : Road portion wash out

a year ago

on Monday, September 2nd 2024, 9:27:24 am
<span class="4">Picture Id:53133</span>
PWD Uttarakahnd
Photo (ID 53133) from Site Received
Uploader : Sandeep Semwal, Assistant Engineer Civil ,TD Rishikesh
Landmark : Km 13.50
Remark : Road portion wash out

10 months ago

on Friday, December 6th 2024, 6:45:10 am
<span class="4">Picture Id:60568</span>
PWD Uttarakahnd
Photo (ID 60568) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : Km 1
Remark : Complete

10 months ago

on Friday, December 6th 2024, 7:56:06 am
<span class="4">Picture Id:60569</span>
PWD Uttarakahnd
Photo (ID 60569) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : Km 14
Remark : Hp bend at 13/28

10 months ago

on Friday, December 6th 2024, 8:09:33 am
<span class="4">Picture Id:60571</span>
PWD Uttarakahnd
Photo (ID 60571) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : 13/35
Remark : Slide portion created due to cutting

10 months ago

on Friday, December 6th 2024, 8:18:57 am
<span class="4">Picture Id:60572</span>
PWD Uttarakahnd
Photo (ID 60572) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : 14/2
Remark : Cutting in progress

10 months ago

on Friday, December 6th 2024, 8:22:49 am
<span class="4">Picture Id:60573</span>
PWD Uttarakahnd
Photo (ID 60573) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : 12/38
Remark : Cutting and filling in progress

10 months ago

on Friday, December 6th 2024, 8:33:45 am
<span class="4">Picture Id:60574</span>
PWD Uttarakahnd
Photo (ID 60574) from Site Received
Uploader : Mukesh Singh Parmar, Chief Engineer Level-II ,NH Zone
Landmark : Ch 13/26
Remark : Hill side cutting in progress

9 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
79.98%
Financial Progress

55th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 833.14Lacs ( against 1041.67Lacs )

9 months ago

on Thursday, January 2nd 2025, 6:30:00 pm
84.59%
Financial Progress

56th Expenditure
of ₹ 4796860 (47.97 Lacs ) done.
Cummulative ₹ 881.11Lacs ( against 1041.67Lacs )

7 months ago

on Monday, February 24th 2025, 6:30:00 pm
84.70%
Financial Progress

57th Expenditure
of ₹ 118767 (1.19 Lacs ) done.
Cummulative ₹ 882.30Lacs ( against 1041.67Lacs )

7 months ago

on Wednesday, March 5th 2025, 6:30:00 pm
93%

Physical Progress
Physical Progress Reported at 9th time

7 months ago

on Monday, March 10th 2025, 6:30:00 pm
89.16%
Financial Progress

58th Expenditure
of ₹ 4645209 (46.45 Lacs ) done.
Cummulative ₹ 928.75Lacs ( against 1041.67Lacs )

6 months ago

on Thursday, March 27th 2025, 6:30:00 pm
90.41%
Financial Progress

59th Expenditure
of ₹ 1297785 (12.98 Lacs ) done.
Cummulative ₹ 941.73Lacs ( against 1041.67Lacs )

6 months ago

on Tuesday, April 1st 2025, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 10th time

5 months ago

on Sunday, May 4th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 11th time

3 months ago

on Monday, June 30th 2025, 6:30:00 pm
94.16%
Financial Progress

60th Expenditure
of ₹ 3906820 (39.07 Lacs ) done.
Cummulative ₹ 980.80Lacs ( against 1041.67Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable