4 years ago

on Tuesday, August 3rd 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र-रायपुर के नगर निगम क्षेत्रान्तर्गत वार्ड संख्या-55 (शाह नगर) के आन्तरिक क्षतिग्रस्त मार्गो पर एस0डी0बी0सी0/इण्टलाॅकिग टाईल्स द्वारा मार्ग निर्माण का कार्य।

4 years ago

on Monday, August 9th 2021, 9:16:57 am

Technical Sanction
of ₹ 85.16 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1946/1C

3 years ago

on Thursday, March 24th 2022, 6:30:00 pm
61.82%
Financial Progress

1st Expenditure
of ₹ 5265000 (52.65 Lacs ) done.
Cummulative ₹ 52.65Lacs ( against 85.16Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
68.69%
Financial Progress

2nd Expenditure
of ₹ 585000 (5.85 Lacs ) done.
Cummulative ₹ 58.50Lacs ( against 85.16Lacs )

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
10.61%
Financial Progress

3rd Expenditure
of ₹ -4946123 (-49.46 Lacs ) done.
Cummulative ₹ 9.04Lacs ( against 85.16Lacs )

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
61.31%
Financial Progress

4th Expenditure
of ₹ 4316963 (43.17 Lacs ) done.
Cummulative ₹ 52.21Lacs ( against 85.16Lacs )

3 years ago

on Sunday, December 25th 2022, 6:30:00 pm
98%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Tuesday, May 30th 2023, 6:30:00 pm
68.81%
Financial Progress

5th Expenditure
of ₹ 638620 (6.39 Lacs ) done.
Cummulative ₹ 58.59Lacs ( against 85.16Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
69.13%
Financial Progress

6th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 58.87Lacs ( against 85.16Lacs )

2 years ago

on Wednesday, January 17th 2024, 6:30:00 pm
69.46%
Financial Progress

7th Expenditure
of ₹ 27900 (0.28 Lacs ) done.
Cummulative ₹ 59.15Lacs ( against 85.16Lacs )

2 years ago

on Wednesday, January 17th 2024, 6:30:00 pm
69.70%
Financial Progress

8th Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 59.36Lacs ( against 85.16Lacs )

2 years ago

on Wednesday, January 17th 2024, 6:30:00 pm
70.05%
Financial Progress

9th Expenditure
of ₹ 29984 (0.30 Lacs ) done.
Cummulative ₹ 59.66Lacs ( against 85.16Lacs )

a year ago

on Saturday, April 27th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Sunday, June 30th 2024, 6:30:00 pm
70.46%
Financial Progress

10th Expenditure
of ₹ 35204 (0.35 Lacs ) done.
Cummulative ₹ 60.01Lacs ( against 85.16Lacs )

a year ago

on Thursday, July 11th 2024, 6:30:00 pm
70.71%
Financial Progress

11th Expenditure
of ₹ 21122 (0.21 Lacs ) done.
Cummulative ₹ 60.22Lacs ( against 85.16Lacs )

6 months ago

on Thursday, March 20th 2025, 6:30:00 pm
71.63%
Financial Progress

12th Expenditure
of ₹ 77880 (0.78 Lacs ) done.
Cummulative ₹ 61.00Lacs ( against 85.16Lacs )

6 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
71.98%
Financial Progress

13th Expenditure
of ₹ 30090 (0.30 Lacs ) done.
Cummulative ₹ 61.30Lacs ( against 85.16Lacs )

6 months ago

on Monday, March 24th 2025, 6:30:00 pm
72.46%
Financial Progress

14th Expenditure
of ₹ 41091 (0.41 Lacs ) done.
Cummulative ₹ 61.71Lacs ( against 85.16Lacs )

6 months ago

on Sunday, March 30th 2025, 6:30:00 pm
77.37%
Financial Progress

15th Expenditure
of ₹ 418067 (4.18 Lacs ) done.
Cummulative ₹ 65.89Lacs ( against 85.16Lacs )