Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र डोईवाला में भोगपुर से बागी नवाकोट डिम्मर मोटर मार्ग पर डामरीकरण का कार्य।
on Tuesday, August 1st 2023, 10:57:10 am
Technical Sanction
of ₹ 232.69 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. Vide S.E No-4966/237C-9/23
on Monday, December 4th 2023, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, January 6th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, January 11th 2024, 6:30:00 pm
13.37%
Financial Progress
1st Expenditure
of ₹ 3345037 (33.45 Lacs ) done.
Cummulative ₹ 33.45Lacs ( against 250.14Lacs )
on Sunday, January 28th 2024, 6:30:00 pm
13.41%
Financial Progress
2nd Expenditure
of ₹ 8996 (0.09 Lacs ) done.
Cummulative ₹ 33.54Lacs ( against 250.14Lacs )
on Monday, February 5th 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, February 20th 2024, 6:30:00 pm
13.41%
Financial Progress
3rd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 33.54Lacs ( against 250.14Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
42.49%
Financial Progress
4th Expenditure
of ₹ 7274530 (72.75 Lacs ) done.
Cummulative ₹ 106.29Lacs ( against 250.14Lacs )
on Monday, April 29th 2024, 6:30:00 pm
52%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, May 15th 2024, 6:30:00 pm
42.56%
Financial Progress
5th Expenditure
of ₹ 17582 (0.18 Lacs ) done.
Cummulative ₹ 106.46Lacs ( against 250.14Lacs )
on Wednesday, May 15th 2024, 6:30:00 pm
42.62%
Financial Progress
6th Expenditure
of ₹ 15930 (0.16 Lacs ) done.
Cummulative ₹ 106.62Lacs ( against 250.14Lacs )
on Thursday, May 30th 2024, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 5th time
on Friday, June 28th 2024, 6:30:00 pm
50.56%
Financial Progress
7th Expenditure
of ₹ 1984330 (19.84 Lacs ) done.
Cummulative ₹ 126.46Lacs ( against 250.14Lacs )
on Sunday, June 30th 2024, 6:53:54 am
PWD UttarakahndPhoto (ID 48978) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.625
Remark : PC work
on Sunday, June 30th 2024, 6:56:49 am
PWD UttarakahndPhoto (ID 48981) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.725
Remark : Banded Wall protection work
on Sunday, June 30th 2024, 6:59:44 am
PWD UttarakahndPhoto (ID 48984) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 0.725
Remark : PC work
on Sunday, June 30th 2024, 7:02:56 am
PWD UttarakahndPhoto (ID 48988) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 1.300
Remark : PC work
on Sunday, June 30th 2024, 7:08:32 am
PWD UttarakahndPhoto (ID 48991) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 1.725
Remark : PC work
on Sunday, June 30th 2024, 7:14:06 am
PWD UttarakahndPhoto (ID 48994) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 2.375
Remark : PC work
on Sunday, June 30th 2024, 7:17:53 am
PWD UttarakahndPhoto (ID 48997) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 2.625
Remark : PC work
on Sunday, June 30th 2024, 7:21:12 am
PWD UttarakahndPhoto (ID 48999) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 3.25
Remark : PC work
on Sunday, June 30th 2024, 7:24:08 am
PWD UttarakahndPhoto (ID 49007) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 3.225
Remark : PC work
on Sunday, June 30th 2024, 7:28:22 am
PWD UttarakahndPhoto (ID 49011) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 3.350
Remark : PC work
on Sunday, June 30th 2024, 7:30:54 am
PWD UttarakahndPhoto (ID 49012) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 3.575
Remark : PC work
on Sunday, June 30th 2024, 7:33:40 am
PWD UttarakahndPhoto (ID 49015) from Site Received
Uploader : Rahul Kumar , Junior Engineer Civil ,TD Rishikesh
Landmark : 3.725
Remark : PC work
on Tuesday, July 2nd 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 6th time
on Monday, July 22nd 2024, 6:30:00 pm
50.56%
Financial Progress
8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 126.46Lacs ( against 250.14Lacs )
on Thursday, July 25th 2024, 6:30:00 pm
62.57%
Financial Progress
9th Expenditure
of ₹ 3004393 (30.04 Lacs ) done.
Cummulative ₹ 156.51Lacs ( against 250.14Lacs )
on Sunday, September 22nd 2024, 6:30:00 pm
65.03%
Financial Progress
10th Expenditure
of ₹ 614675 (6.15 Lacs ) done.
Cummulative ₹ 162.65Lacs ( against 250.14Lacs )
on Monday, September 23rd 2024, 6:30:00 pm
78.31%
Financial Progress
11th Expenditure
of ₹ 3323982 (33.24 Lacs ) done.
Cummulative ₹ 195.89Lacs ( against 250.14Lacs )
on Friday, September 27th 2024, 6:30:00 pm
78.31%
Financial Progress
13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 195.89Lacs ( against 250.14Lacs )
on Friday, September 27th 2024, 6:30:00 pm
78.31%
Financial Progress
12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 195.89Lacs ( against 250.14Lacs )
on Friday, September 27th 2024, 6:30:00 pm
78.33%
Financial Progress
14th Expenditure
of ₹ 4390 (0.04 Lacs ) done.
Cummulative ₹ 195.94Lacs ( against 250.14Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
78.30%
Financial Progress
15th Expenditure
of ₹ -7637 (-0.08 Lacs ) done.
Cummulative ₹ 195.86Lacs ( against 250.14Lacs )
on Monday, October 14th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 7th time
on Friday, November 29th 2024, 6:30:00 pm
78.65%
Financial Progress
16th Expenditure
of ₹ 87520 (0.88 Lacs ) done.
Cummulative ₹ 196.74Lacs ( against 250.14Lacs )
on Tuesday, December 10th 2024, 6:30:00 pm
87.85%
Financial Progress
17th Expenditure
of ₹ 2302215 (23.02 Lacs ) done.
Cummulative ₹ 219.76Lacs ( against 250.14Lacs )
on Wednesday, December 25th 2024, 6:30:00 pm
87.85%
Financial Progress
18th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 219.76Lacs ( against 250.14Lacs )
on Wednesday, December 25th 2024, 6:30:00 pm
87.85%
Financial Progress
19th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 219.76Lacs ( against 250.14Lacs )
on Thursday, January 30th 2025, 6:30:00 pm
88.01%
Financial Progress
20th Expenditure
of ₹ 37700 (0.38 Lacs ) done.
Cummulative ₹ 220.14Lacs ( against 250.14Lacs )
on Tuesday, March 11th 2025, 6:30:00 pm
88.17%
Financial Progress
21st Expenditure
of ₹ 40000 (0.40 Lacs ) done.
Cummulative ₹ 220.54Lacs ( against 250.14Lacs )
on Sunday, March 16th 2025, 6:30:00 pm
88.35%
Financial Progress
24th Expenditure
of ₹ 14632 (0.15 Lacs ) done.
Cummulative ₹ 221.01Lacs ( against 250.14Lacs )
on Sunday, March 16th 2025, 6:30:00 pm
88.29%
Financial Progress
23rd Expenditure
of ₹ 14632 (0.15 Lacs ) done.
Cummulative ₹ 220.86Lacs ( against 250.14Lacs )
on Sunday, March 16th 2025, 6:30:00 pm
88.24%
Financial Progress
22nd Expenditure
of ₹ 17700 (0.18 Lacs ) done.
Cummulative ₹ 220.71Lacs ( against 250.14Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
88.75%
Financial Progress
25th Expenditure
of ₹ 98813 (0.99 Lacs ) done.
Cummulative ₹ 221.99Lacs ( against 250.14Lacs )
on Thursday, August 7th 2025, 6:30:00 pm
88.90%
Financial Progress
26th Expenditure
of ₹ 38682 (0.39 Lacs ) done.
Cummulative ₹ 222.38Lacs ( against 250.14Lacs )
on Thursday, August 21st 2025, 6:30:00 pm
89.17%
Financial Progress
27th Expenditure
of ₹ 68003 (0.68 Lacs ) done.
Cummulative ₹ 223.06Lacs ( against 250.14Lacs )
on Thursday, August 28th 2025, 6:30:00 pm
89.36%
Financial Progress
28th Expenditure
of ₹ 47157 (0.47 Lacs ) done.
Cummulative ₹ 223.53Lacs ( against 250.14Lacs )