Work Sanctioned
ग्राम पंचायत छिद्दरवाला व चकजोगीवाला में सडक निर्माण कार्य।
on Tuesday, August 13th 2024, 10:27:27 am
Technical Sanction
of ₹ 4 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. E.E. No. 2177/6 C (T.S.)
on Thursday, January 30th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, March 30th 2025, 6:30:00 pm
50.00%
Financial Progress
1st Expenditure
of ₹ 200000 (2.00 Lacs ) done.
Cummulative ₹ 2.00Lacs ( against 4Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
96.97%
Financial Progress
2nd Expenditure
of ₹ 187865 (1.88 Lacs ) done.
Cummulative ₹ 3.88Lacs ( against 4Lacs )