Refresh data
Refresh data

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र विकासनगर के अन्तर्गत विकासनगर में बादामावाला मार्ग, बैरागीवाला मार्ग, फतेहपुर मार्ग, जमनीपुर तत्पड़ मार्ग एवं केशरबाग वार्ड नं0-2 में इण्टरलाॅकिंग टाईल्स द्वारा पुनः निर्माण कार्य।

2 years ago

on Monday, April 10th 2023, 11:18:47 am

Technical Sanction
of ₹ 77.21 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1728/1C

2 years ago

on Friday, August 4th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Friday, August 11th 2023, 7:10:53 am
<span class="4">Picture Id:23582</span>
PWD Uttarakahnd
Photo (ID 23582) from Site Received
Uploader : Meenakshi, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0\0
Remark : Bawodi road

2 years ago

on Friday, August 11th 2023, 8:13:15 am
<span class="4">Picture Id:23590</span>
PWD Uttarakahnd
Photo (ID 23590) from Site Received
Uploader : Meenakshi, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0\0
Remark : Aadarsh Vihar khadan Singh ke ghar Tak

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
18.42%
Financial Progress

1st Expenditure
of ₹ 1528551 (15.29 Lacs ) done.
Cummulative ₹ 15.29Lacs ( against 83Lacs )

2 years ago

on Monday, November 6th 2023, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Friday, December 29th 2023, 6:30:00 pm
18.42%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 15.29Lacs ( against 83Lacs )

2 years ago

on Friday, December 29th 2023, 6:30:00 pm
35.95%
Financial Progress

3rd Expenditure
of ₹ 1455274 (14.55 Lacs ) done.
Cummulative ₹ 29.84Lacs ( against 83Lacs )

2 years ago

on Monday, January 8th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Tuesday, January 30th 2024, 6:30:00 pm
35.95%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 29.84Lacs ( against 83Lacs )

2 years ago

on Tuesday, January 30th 2024, 6:30:00 pm
60.08%
Financial Progress

5th Expenditure
of ₹ 2002957 (20.03 Lacs ) done.
Cummulative ₹ 49.87Lacs ( against 83Lacs )

2 years ago

on Wednesday, February 28th 2024, 6:30:00 pm
66.08%
Financial Progress

6th Expenditure
of ₹ 497689 (4.98 Lacs ) done.
Cummulative ₹ 54.84Lacs ( against 83Lacs )

2 years ago

on Thursday, March 14th 2024, 6:30:00 pm
66.08%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 54.84Lacs ( against 83Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
89.97%
Financial Progress

8th Expenditure
of ₹ 1982912 (19.83 Lacs ) done.
Cummulative ₹ 74.67Lacs ( against 83Lacs )

a year ago

on Saturday, June 29th 2024, 6:30:00 pm
95.95%
Financial Progress

9th Expenditure
of ₹ 496253 (4.96 Lacs ) done.
Cummulative ₹ 79.64Lacs ( against 83Lacs )

9 months ago

on Monday, December 30th 2024, 6:30:00 pm
98.95%
Financial Progress

10th Expenditure
of ₹ 248981 (2.49 Lacs ) done.
Cummulative ₹ 82.13Lacs ( against 83Lacs )

6 months ago

on Tuesday, March 25th 2025, 5:28:23 am
<span class="4">Picture Id:66496</span>
PWD Uttarakahnd
Photo (ID 66496) from Site Received
Uploader : Himanshu Nautiyal, Assistant Engineer Civil ,CD Dehradun
Landmark : 0.100
Remark : अधीक्षण अभियंता महोदय 8th वृत्त द्वारा निरीक्षण

6 months ago

on Tuesday, March 25th 2025, 5:54:02 am
<span class="4">Picture Id:66499</span>
PWD Uttarakahnd
Photo (ID 66499) from Site Received
Uploader : Himanshu Nautiyal, Assistant Engineer Civil ,CD Dehradun
Landmark : 0.025 janipur tappad
Remark : अधीक्षण अभियंता महोदय 8th वृत्त द्वारा निरीक्षण