on Wednesday, November 4th 2020, 6:30:00 pm
Work Sanctioned
जनपद देहरादून के विधानसभा क्षेत्र धर्मपुर में शान्ति विहार फेज-2, शक्ति विहार फेज-2 केदारपुरम (मोथरोवाला) तथा बंजारावाला क्षेत्र के अवशेष आन्तरिक मार्ग, नाली, पुलियों एवं सुरक्षा दीवारों का निर्माण कार्य।

5 years ago

on Friday, February 26th 2021, 6:30:00 pm

Technical Sanction
of ₹ 76.03 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. S.E.'s Letter No. 977/334(x)C 9/21

4 years ago

on Monday, August 30th 2021, 6:30:00 pm
3.04%
Financial Progress

1st Expenditure
of ₹ 499558 (5.00 Lacs ) done.
Cummulative ₹ 5.00Lacs ( against 164.32Lacs )

4 years ago

on Wednesday, November 10th 2021, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Monday, November 29th 2021, 6:30:00 pm
3.24%
Financial Progress

2nd Expenditure
of ₹ 32550 (0.33 Lacs ) done.
Cummulative ₹ 5.32Lacs ( against 164.32Lacs )

4 years ago

on Monday, March 14th 2022, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
16.00%
Financial Progress

3rd Expenditure
of ₹ 2097648 (20.98 Lacs ) done.
Cummulative ₹ 26.30Lacs ( against 164.32Lacs )

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
16.07%
Financial Progress

4th Expenditure
of ₹ 11100 (0.11 Lacs ) done.
Cummulative ₹ 26.41Lacs ( against 164.32Lacs )

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
16.24%
Financial Progress

5th Expenditure
of ₹ 28314 (0.28 Lacs ) done.
Cummulative ₹ 26.69Lacs ( against 164.32Lacs )

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
42.36%
Financial Progress

6th Expenditure
of ₹ 4291478 (42.91 Lacs ) done.
Cummulative ₹ 69.61Lacs ( against 164.32Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
42.49%
Financial Progress

7th Expenditure
of ₹ 20777 (0.21 Lacs ) done.
Cummulative ₹ 69.81Lacs ( against 164.32Lacs )

2 years ago

on Tuesday, April 4th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Sunday, July 30th 2023, 6:30:00 pm
42.62%
Financial Progress

8th Expenditure
of ₹ 22200 (0.22 Lacs ) done.
Cummulative ₹ 70.04Lacs ( against 164.32Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
42.94%
Financial Progress

9th Expenditure
of ₹ 51984 (0.52 Lacs ) done.
Cummulative ₹ 70.56Lacs ( against 164.32Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
43.01%
Financial Progress

10th Expenditure
of ₹ 11100 (0.11 Lacs ) done.
Cummulative ₹ 70.67Lacs ( against 164.32Lacs )

2 years ago

on Friday, December 29th 2023, 6:30:00 pm
43.40%
Financial Progress

11th Expenditure
of ₹ 64699 (0.65 Lacs ) done.
Cummulative ₹ 71.31Lacs ( against 164.32Lacs )

2 years ago

on Wednesday, February 28th 2024, 6:30:00 pm
43.65%
Financial Progress

12th Expenditure
of ₹ 40692 (0.41 Lacs ) done.
Cummulative ₹ 71.72Lacs ( against 164.32Lacs )

5 months ago

on Monday, April 7th 2025, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 4th time
Loading...