Work Sanctioned
राज्य योजना 2024-25 के अन्तर्गत जनपद हरिद्वार के वि0स0 क्षेत्र बी.एच.ई.एल. रानीपुर में ग्राम हेत्तमपुर के आन्तरिक मार्गों का इण्टरलाॅकिंग टाईल्स द्वारा नाली सहित निर्माण कार्य।

a year ago

on Wednesday, November 27th 2024, 8:46:05 am

Technical Sanction
of ₹ 87.99 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE Approved Register Sl.no.46

a year ago

on Friday, December 27th 2024, 6:30:00 pm
2%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Monday, December 30th 2024, 6:30:00 pm
22.80%
Financial Progress

1st Expenditure
of ₹ 2006000 (20.06 Lacs ) done.
Cummulative ₹ 20.06Lacs ( against 87.99Lacs )

9 months ago

on Thursday, February 27th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

8 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
22.91%
Financial Progress

2nd Expenditure
of ₹ 9763 (0.10 Lacs ) done.
Cummulative ₹ 20.16Lacs ( against 87.99Lacs )

8 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
25.59%
Financial Progress

3rd Expenditure
of ₹ 236000 (2.36 Lacs ) done.
Cummulative ₹ 22.52Lacs ( against 87.99Lacs )

8 months ago

on Friday, March 14th 2025, 6:30:00 pm
90.53%
Financial Progress

4th Expenditure
of ₹ 5714273 (57.14 Lacs ) done.
Cummulative ₹ 79.66Lacs ( against 87.99Lacs )

8 months ago

on Sunday, March 16th 2025, 6:30:00 pm
91.07%
Financial Progress

5th Expenditure
of ₹ 47200 (0.47 Lacs ) done.
Cummulative ₹ 80.13Lacs ( against 87.99Lacs )