12 years ago

on Wednesday, December 4th 2013, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0- 537/2012 के अन्तर्गत जनपद देहरादून के विधान सभा क्षेत्र चकराता में डियूडीलानी से ढलीन सकरोल तक मोटर मार्ग का निर्माण।

4 years ago

on Wednesday, September 29th 2021, 10:26:38 am
<span class="4">Picture Id:1859</span>
PWD Uttarakahnd
Photo (ID 1859) from Site Received
Uploader : Radhika Sharma, Assistant Engineer Civil ,TD Sahiya
Landmark : 3/2-3
Remark : Scupper slab casting

4 years ago

on Wednesday, September 29th 2021, 10:57:49 am
<span class="4">Picture Id:1860</span>
PWD Uttarakahnd
Photo (ID 1860) from Site Received
Uploader : Radhika Sharma, Assistant Engineer Civil ,TD Sahiya
Landmark : 3/2-3
Remark : Slab casting

4 years ago

on Tuesday, March 29th 2022, 6:30:00 pm
0.00%
Financial Progress

1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 62.72Lacs )

3 years ago

on Sunday, May 29th 2022, 6:30:00 pm
0.00%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 62.72Lacs )

3 years ago

on Sunday, May 29th 2022, 6:30:00 pm
85.03%
Financial Progress

3rd Expenditure
of ₹ 5333000 (53.33 Lacs ) done.
Cummulative ₹ 53.33Lacs ( against 62.72Lacs )

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
85.09%
Financial Progress

4th Expenditure
of ₹ 4000 (0.04 Lacs ) done.
Cummulative ₹ 53.37Lacs ( against 62.72Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
86.05%
Financial Progress

5th Expenditure
of ₹ 60000 (0.60 Lacs ) done.
Cummulative ₹ 53.97Lacs ( against 62.72Lacs )

3 years ago

on Wednesday, March 29th 2023, 6:30:00 pm
86.07%
Financial Progress

6th Expenditure
of ₹ 1000 (0.01 Lacs ) done.
Cummulative ₹ 53.98Lacs ( against 62.72Lacs )

3 years ago

on Wednesday, March 29th 2023, 6:30:00 pm
86.07%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 53.98Lacs ( against 62.72Lacs )

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
86.19%
Financial Progress

8th Expenditure
of ₹ 7545 (0.08 Lacs ) done.
Cummulative ₹ 54.06Lacs ( against 62.72Lacs )

2 years ago

on Friday, December 29th 2023, 6:30:00 pm
86.27%
Financial Progress

9th Expenditure
of ₹ 5418 (0.05 Lacs ) done.
Cummulative ₹ 54.11Lacs ( against 62.72Lacs )

2 years ago

on Friday, March 29th 2024, 6:30:00 pm
88.34%
Financial Progress

10th Expenditure
of ₹ 129649 (1.30 Lacs ) done.
Cummulative ₹ 55.41Lacs ( against 62.72Lacs )

a year ago

on Thursday, July 18th 2024, 6:30:00 pm
85%

Physical Progress
Physical Progress Reported at 1st time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors