Refresh data
on Monday, June 26th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 643/2021 के अन्तर्गत जनपद देहरादून के विधानसभा चकराता के अन्तर्गत मसूरी चकराता राष्ट्रीय राजमार्ग से गोई छनास मोटर मार्ग का नव निर्माण कार्य। (द्वितीय चरण स्टेज-।)
on Friday, August 4th 2023, 7:40:04 am
Technical Sanction
of ₹ 126.31 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. SE E-File No. 30778/2023 Dated 04.08.2023
on Wednesday, November 29th 2023, 6:30:00 pm
7.36%
Financial Progress
1st Expenditure
of ₹ 1000000 (10.00 Lacs ) done.
Cummulative ₹ 10.00Lacs ( against 135.78Lacs )
on Wednesday, December 6th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Friday, December 29th 2023, 6:30:00 pm
31.61%
Financial Progress
2nd Expenditure
of ₹ 3291820 (32.92 Lacs ) done.
Cummulative ₹ 42.92Lacs ( against 135.78Lacs )
on Wednesday, January 10th 2024, 5:27:25 am
PWD UttarakahndPhoto (ID 34613) from Site Received
Uploader : Dinesh Singh, Assistant Engineer Civil ,TD Sahiya
Landmark : 0.400
Remark : 0.400 hill side cutting
on Wednesday, January 10th 2024, 5:36:33 am
PWD UttarakahndPhoto (ID 34614) from Site Received
Uploader : Dinesh Singh, Assistant Engineer Civil ,TD Sahiya
Landmark : 0.375
Remark : Hill side cutting
on Thursday, February 8th 2024, 6:30:00 pm
40.79%
Financial Progress
3rd Expenditure
of ₹ 1247000 (12.47 Lacs ) done.
Cummulative ₹ 55.39Lacs ( against 135.78Lacs )
on Wednesday, February 28th 2024, 6:30:00 pm
41.16%
Financial Progress
4th Expenditure
of ₹ 49999 (0.50 Lacs ) done.
Cummulative ₹ 55.89Lacs ( against 135.78Lacs )
on Monday, March 4th 2024, 6:30:00 pm
60.23%
Financial Progress
5th Expenditure
of ₹ 2589000 (25.89 Lacs ) done.
Cummulative ₹ 81.78Lacs ( against 135.78Lacs )
on Tuesday, March 26th 2024, 6:30:00 pm
83.12%
Financial Progress
6th Expenditure
of ₹ 3108714 (31.09 Lacs ) done.
Cummulative ₹ 112.87Lacs ( against 135.78Lacs )
on Friday, April 5th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, May 30th 2024, 11:02:51 am
PWD UttarakahndPhoto (ID 40627) from Site Received
Uploader : Vikas Parmar, Additional Assistant Engineer Civil ,TD Sahiya
Landmark : 3/16
Remark : Third party inspection in Goi chinas motor Road.
on Monday, June 10th 2024, 6:30:00 pm
89.80%
Financial Progress
7th Expenditure
of ₹ 907043 (9.07 Lacs ) done.
Cummulative ₹ 121.94Lacs ( against 135.78Lacs )
on Sunday, June 23rd 2024, 6:30:00 pm
89.80%
Financial Progress
8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 121.94Lacs ( against 135.78Lacs )
on Tuesday, July 30th 2024, 6:30:00 pm
94.03%
Financial Progress
9th Expenditure
of ₹ 573211 (5.73 Lacs ) done.
Cummulative ₹ 127.67Lacs ( against 135.78Lacs )
on Tuesday, July 30th 2024, 6:30:00 pm
107.39%
Financial Progress
10th Expenditure
of ₹ 573211 (5.73 Lacs ) done.
Cummulative ₹ 145.81Lacs ( against 135.78Lacs )