Work Sanctioned
टी.एस.पी. के अन्तर्गत जनपद देहरादून के विधानसभा क्षेत्र चकराता के विकासखण्ड कालसी में कुसियों-कचटा-खाती मोटर मार्ग का पुनः निर्माण /सुधारीकरण का कार्य।

6 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
0.03%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 372.33Lacs )

5 months ago

on Sunday, April 27th 2025, 6:30:00 pm
10.96%
Financial Progress

2nd Expenditure
of ₹ 4072180 (40.72 Lacs ) done.
Cummulative ₹ 40.82Lacs ( against 372.33Lacs )

5 months ago

on Wednesday, April 30th 2025, 7:13:06 am
<span class="4">Picture Id:68902</span>
PWD Uttarakahnd
Photo (ID 68902) from Site Received
Uploader : Vikas Parmar, Additional Assistant Engineer Civil ,TD Sahiya
Landmark : 0/26-28
Remark : Widening and protection work in progress.

4 months ago

on Monday, May 19th 2025, 6:30:00 pm
26.15%
Financial Progress

3rd Expenditure
of ₹ 5652796 (56.53 Lacs ) done.
Cummulative ₹ 97.35Lacs ( against 372.33Lacs )

3 months ago

on Tuesday, June 24th 2025, 6:30:00 pm
30.51%
Financial Progress

4th Expenditure
of ₹ 1623549 (16.24 Lacs ) done.
Cummulative ₹ 113.59Lacs ( against 372.33Lacs )

3 months ago

on Tuesday, June 24th 2025, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 1st time

AI layer

AI Road
AI Bridge
50 m
100 ft
Unavailable