@
Refresh data
Refresh data

7 years ago

on Sunday, February 17th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना वर्ष 2018-19 के अन्तर्गत भगवानपुर से रूहालकी दयालपुर होते हुए इकबालपुर मार्ग का चैड़ीकरण एवं सुद्ृढ़ीकरण का कार्य।

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.00%
Financial Progress

1st Expenditure
of ₹ 1500 (0.01 Lacs ) done.
Cummulative ₹ 0.01Lacs ( against 339.98Lacs )

6 years ago

on Wednesday, June 12th 2019, 6:30:00 pm

Technical Sanction
of ₹ 318.48 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2037/217(Hari)Yata-Level-1 (Zone office)/2019

5 years ago

on Friday, July 31st 2020, 6:30:00 pm
7.04%
Financial Progress

2nd Expenditure
of ₹ 2393000 (23.93 Lacs ) done.
Cummulative ₹ 23.95Lacs ( against 339.98Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
22.34%
Financial Progress

3rd Expenditure
of ₹ 5201000 (52.01 Lacs ) done.
Cummulative ₹ 75.95Lacs ( against 339.98Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
41.85%
Financial Progress

4th Expenditure
of ₹ 6634000 (66.34 Lacs ) done.
Cummulative ₹ 142.29Lacs ( against 339.98Lacs )

4 years ago

on Tuesday, July 6th 2021, 6:30:00 pm
46%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Friday, July 30th 2021, 6:30:00 pm
66.18%
Financial Progress

5th Expenditure
of ₹ 8271000 (82.71 Lacs ) done.
Cummulative ₹ 225.00Lacs ( against 339.98Lacs )

4 years ago

on Tuesday, August 3rd 2021, 6:30:00 pm
98%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Monday, August 30th 2021, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
78.96%
Financial Progress

6th Expenditure
of ₹ 4343000 (43.43 Lacs ) done.
Cummulative ₹ 268.44Lacs ( against 339.98Lacs )

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
79.07%
Financial Progress

7th Expenditure
of ₹ 39000 (0.39 Lacs ) done.
Cummulative ₹ 268.82Lacs ( against 339.98Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
79.36%
Financial Progress

8th Expenditure
of ₹ 97000 (0.97 Lacs ) done.
Cummulative ₹ 269.80Lacs ( against 339.98Lacs )

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
81.27%
Financial Progress

9th Expenditure
of ₹ 649000 (6.49 Lacs ) done.
Cummulative ₹ 276.29Lacs ( against 339.98Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
87.11%
Financial Progress

10th Expenditure
of ₹ 1986000 (19.86 Lacs ) done.
Cummulative ₹ 296.14Lacs ( against 339.98Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
92.59%
Financial Progress

11th Expenditure
of ₹ 1864000 (18.64 Lacs ) done.
Cummulative ₹ 314.79Lacs ( against 339.98Lacs )

a year ago

on Sunday, June 23rd 2024, 6:30:00 pm
93.57%
Financial Progress

12th Expenditure
of ₹ 334880 (3.35 Lacs ) done.
Cummulative ₹ 318.13Lacs ( against 339.98Lacs )

a year ago

on Monday, July 1st 2024, 11:03:06 am
<span class="4">Picture Id:49788</span>
PWD Uttarakahnd
Photo (ID 49788) from Site Received
Uploader : Narayan Singh, Additional Assistant Engineer Civil ,CD Chamba
Landmark : Km 1(0.650)
Remark : Work completed

a year ago

on Tuesday, October 15th 2024, 6:30:00 pm
94.16%
Financial Progress

13th Expenditure
of ₹ 200600 (2.01 Lacs ) done.
Cummulative ₹ 320.14Lacs ( against 339.98Lacs )

AI layer

AI Road
AI Bridge
50 m
100 ft
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors