Work Sanctioned
राज्य योजना वर्ष 2023-24 के अन्तर्गत ग्राम शेरपुर खेलमऊ में श्री अजय के खेत से श्री बादल के खेत तक खडण्जा निर्माण कार्य।
on Monday, October 30th 2023, 10:01:01 am
Technical Sanction
of ₹ 27.5 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2190(5)/1C
on Friday, February 16th 2024, 6:30:00 pm
0.35%
Financial Progress
1st Expenditure
of ₹ 9636 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 27.5Lacs )
on Tuesday, February 27th 2024, 6:30:00 pm
39.08%
Financial Progress
2nd Expenditure
of ₹ 1064950 (10.65 Lacs ) done.
Cummulative ₹ 10.75Lacs ( against 27.5Lacs )
on Friday, March 1st 2024, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, March 27th 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, April 24th 2024, 6:30:00 pm
76%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, May 23rd 2024, 6:30:00 pm
40.09%
Financial Progress
3rd Expenditure
of ₹ 27933 (0.28 Lacs ) done.
Cummulative ₹ 11.03Lacs ( against 27.5Lacs )
on Monday, May 27th 2024, 5:31:52 am
PWD UttarakahndPhoto (ID 40153) from Site Received
Uploader : Rahul Arya, Assistant Engineer Civil ,CD Roorkee
Landmark : Ajay ke khet se
Remark : Kharanja work
on Monday, May 27th 2024, 5:38:35 am
PWD UttarakahndPhoto (ID 40154) from Site Received
Uploader : Rahul Arya, Assistant Engineer Civil ,CD Roorkee
Landmark : Ajay ke khet
Remark : Khanja
on Monday, May 27th 2024, 5:42:56 am
PWD UttarakahndPhoto (ID 40155) from Site Received
Uploader : Rahul Arya, Assistant Engineer Civil ,CD Roorkee
Landmark : Ajay ke khet se badal ke khet tak
Remark : Khanja
on Wednesday, June 26th 2024, 6:30:00 pm
86%
Physical Progress
Physical Progress Reported at 4th time
on Sunday, July 14th 2024, 6:30:00 pm
40.99%
Financial Progress
4th Expenditure
of ₹ 24780 (0.25 Lacs ) done.
Cummulative ₹ 11.27Lacs ( against 27.5Lacs )
on Monday, July 29th 2024, 6:30:00 pm
91%
Physical Progress
Physical Progress Reported at 5th time
on Friday, August 30th 2024, 6:30:00 pm
69.29%
Financial Progress
5th Expenditure
of ₹ 778053 (7.78 Lacs ) done.
Cummulative ₹ 19.05Lacs ( against 27.5Lacs )
on Wednesday, October 23rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Monday, March 3rd 2025, 6:30:00 pm
74.87%
Financial Progress
6th Expenditure
of ₹ 153513 (1.54 Lacs ) done.
Cummulative ₹ 20.59Lacs ( against 27.5Lacs )
on Thursday, May 8th 2025, 6:30:00 pm
92.65%
Financial Progress
7th Expenditure
of ₹ 489124 (4.89 Lacs ) done.
Cummulative ₹ 25.48Lacs ( against 27.5Lacs )
on Sunday, May 25th 2025, 6:30:00 pm
94.36%
Financial Progress
9th Expenditure
of ₹ 23506 (0.24 Lacs ) done.
Cummulative ₹ 25.95Lacs ( against 27.5Lacs )
on Sunday, May 25th 2025, 6:30:00 pm
93.51%
Financial Progress
8th Expenditure
of ₹ 23506 (0.24 Lacs ) done.
Cummulative ₹ 25.71Lacs ( against 27.5Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
95.63%
Financial Progress
14th Expenditure
of ₹ 6802 (0.07 Lacs ) done.
Cummulative ₹ 26.30Lacs ( against 27.5Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
95.38%
Financial Progress
13th Expenditure
of ₹ 14211 (0.14 Lacs ) done.
Cummulative ₹ 26.23Lacs ( against 27.5Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
94.86%
Financial Progress
12th Expenditure
of ₹ 5678 (0.06 Lacs ) done.
Cummulative ₹ 26.09Lacs ( against 27.5Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
94.66%
Financial Progress
11th Expenditure
of ₹ 2369 (0.02 Lacs ) done.
Cummulative ₹ 26.03Lacs ( against 27.5Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
94.57%
Financial Progress
10th Expenditure
of ₹ 5668 (0.06 Lacs ) done.
Cummulative ₹ 26.01Lacs ( against 27.5Lacs )