Work Sanctioned
राज्य योजना वर्ष 2024-25 के अन्तर्गत जनपद हरिद्वार के पिरान कलियर के ग्राम मगरूमपुर के क्षतिग्रस्त सी0सी0 आन्तरिक मार्गों का सी0सी0 इण्टरलोकिंग टाईल्स द्वारा पुनः निर्माण कार्य।
on Wednesday, October 23rd 2024, 8:26:15 am
Technical Sanction
of ₹ 12.13 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 46/1C
on Tuesday, January 28th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Monday, February 3rd 2025, 6:30:00 pm
33.41%
Financial Progress
1st Expenditure
of ₹ 405251 (4.05 Lacs ) done.
Cummulative ₹ 4.05Lacs ( against 12.13Lacs )
on Wednesday, February 12th 2025, 6:30:00 pm
58.48%
Financial Progress
2nd Expenditure
of ₹ 304080 (3.04 Lacs ) done.
Cummulative ₹ 7.09Lacs ( against 12.13Lacs )
on Monday, March 3rd 2025, 6:30:00 pm
59.02%
Financial Progress
3rd Expenditure
of ₹ 6597 (0.07 Lacs ) done.
Cummulative ₹ 7.16Lacs ( against 12.13Lacs )
on Monday, March 3rd 2025, 6:30:00 pm
59.76%
Financial Progress
4th Expenditure
of ₹ 8988 (0.09 Lacs ) done.
Cummulative ₹ 7.25Lacs ( against 12.13Lacs )
on Monday, March 3rd 2025, 6:30:00 pm
61.63%
Financial Progress
5th Expenditure
of ₹ 22680 (0.23 Lacs ) done.
Cummulative ₹ 7.48Lacs ( against 12.13Lacs )
on Friday, May 2nd 2025, 6:30:00 pm
98.43%
Financial Progress
6th Expenditure
of ₹ 446354 (4.46 Lacs ) done.
Cummulative ₹ 11.94Lacs ( against 12.13Lacs )
on Wednesday, July 16th 2025, 6:30:00 pm
99.99%
Financial Progress
7th Expenditure
of ₹ 18880 (0.19 Lacs ) done.
Cummulative ₹ 12.13Lacs ( against 12.13Lacs )