on Sunday, January 26th 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना वर्ष 2024-25 के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र रूड़की में पुरानी तहसील की आंतरिक सड़कों का बी0एम0, एस0डी0बी0सी0 द्वारा सड़क निर्माण कार्य।
on Thursday, February 6th 2025, 7:35:10 am
Technical Sanction
of ₹ 80.96 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 66/1C
on Sunday, May 25th 2025, 6:30:00 pm
55.39%
Financial Progress
1st Expenditure
of ₹ 4484000 (44.84 Lacs ) done.
Cummulative ₹ 44.84Lacs ( against 80.96Lacs )
on Friday, May 30th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 19th 2025, 6:30:00 pm
59.02%
Financial Progress
2nd Expenditure
of ₹ 294008 (2.94 Lacs ) done.
Cummulative ₹ 47.78Lacs ( against 80.96Lacs )
on Thursday, June 19th 2025, 6:30:00 pm
61.72%
Financial Progress
3rd Expenditure
of ₹ 218740 (2.19 Lacs ) done.
Cummulative ₹ 49.97Lacs ( against 80.96Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
62.73%
Financial Progress
4th Expenditure
of ₹ 81644 (0.82 Lacs ) done.
Cummulative ₹ 50.78Lacs ( against 80.96Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
68.82%
Financial Progress
5th Expenditure
of ₹ 493518 (4.94 Lacs ) done.
Cummulative ₹ 55.72Lacs ( against 80.96Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
74.30%
Financial Progress
6th Expenditure
of ₹ 443120 (4.43 Lacs ) done.
Cummulative ₹ 60.15Lacs ( against 80.96Lacs )
on Sunday, August 10th 2025, 6:30:00 pm
94.29%
Financial Progress
7th Expenditure
of ₹ 1618327 (16.18 Lacs ) done.
Cummulative ₹ 76.33Lacs ( against 80.96Lacs )