Work Sanctioned
राज्य आपदा न्यूनीकरण निधि मद वर्ष 2024-25 के अन्तर्गत जनपद बागेश्वर के विकास खण्ड गरूड़ में पाण्डेखरक-जिजोली-देवनाई मोटर मार्ग के किमी0 1 है0मी0 8-10 में भूस्खलन के कारण आवासीय मकान की सुरक्षा हेतु सुरक्षात्मक कार्य।
on Saturday, September 28th 2024, 9:37:05 am
Technical Sanction
of ₹ 14.53 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE letter No-2681/1C
on Monday, March 17th 2025, 6:30:00 pm
87.20%
Financial Progress
1st Expenditure
of ₹ 1266945 (12.67 Lacs ) done.
Cummulative ₹ 12.67Lacs ( against 14.53Lacs )
on Monday, March 24th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, May 20th 2025, 6:30:00 pm
97.69%
Financial Progress
2nd Expenditure
of ₹ 152501 (1.53 Lacs ) done.
Cummulative ₹ 14.19Lacs ( against 14.53Lacs )