Refresh data
on Sunday, February 10th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद बागेश्वर के विधानसभा क्षेत्र बागेश्वर के ग्राम मोहननगर से तुनेड़ा-बसेत मोटर मार्ग के किमी0 1 व 2 में डामरीकरण का कार्य।
on Thursday, February 28th 2019, 6:30:00 pm
0.09%
Financial Progress
1st Expenditure
of ₹ 9895 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 110.42Lacs )
on Wednesday, March 23rd 2022, 6:59:39 am
Technical Sanction
of ₹ 110.42 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE Latter no-490/1C
on Thursday, December 8th 2022, 2:55:18 am
PWD UttarakahndPhoto (ID 13632) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera badet m/r km 2 hm 4-6
Remark : Soling coat
on Thursday, December 8th 2022, 3:18:52 am
PWD UttarakahndPhoto (ID 13638) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera-baset m/r km2 2-4
Remark : Soling coat
on Thursday, December 8th 2022, 3:43:02 am
PWD UttarakahndPhoto (ID 13651) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera baset m/r km 1 hm 8-10
Remark : Soling coat
on Monday, December 12th 2022, 4:37:19 am
PWD UttarakahndPhoto (ID 13900) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera baset m/r
Remark : Km1 2-4
on Wednesday, December 14th 2022, 2:22:55 am
PWD UttarakahndPhoto (ID 14034) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera baset m/r
Remark : Soling coat test
on Friday, December 30th 2022, 4:35:12 am
PWD UttarakahndPhoto (ID 15021) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Inter coat width
on Friday, December 30th 2022, 4:37:42 am
PWD UttarakahndPhoto (ID 15022) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Km1
Remark : Inter coat thickness
on Monday, January 2nd 2023, 5:16:27 am
PWD UttarakahndPhoto (ID 15076) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera baset
Remark : Km1
on Monday, January 2nd 2023, 5:18:05 am
PWD UttarakahndPhoto (ID 15077) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera baset
Remark : Km1
on Tuesday, January 3rd 2023, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, January 4th 2023, 12:09:45 am
PWD UttarakahndPhoto (ID 15128) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera-baset m/r
Remark : Tunera-baset m/r
on Thursday, March 16th 2023, 5:51:05 am
PWD UttarakahndPhoto (ID 25192) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera
Remark : K m1
on Thursday, March 16th 2023, 5:53:24 am
PWD UttarakahndPhoto (ID 25193) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Tunera
Remark : Km1
on Monday, March 27th 2023, 6:30:00 pm
21.84%
Financial Progress
2nd Expenditure
of ₹ 2401300 (24.01 Lacs ) done.
Cummulative ₹ 24.11Lacs ( against 110.42Lacs )
on Sunday, April 16th 2023, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, May 28th 2023, 6:30:00 pm
32.42%
Financial Progress
3rd Expenditure
of ₹ 1168690 (11.69 Lacs ) done.
Cummulative ₹ 35.80Lacs ( against 110.42Lacs )
on Friday, June 2nd 2023, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, June 23rd 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 4th time
on Tuesday, June 27th 2023, 6:30:00 pm
46.84%
Financial Progress
4th Expenditure
of ₹ 1592065 (15.92 Lacs ) done.
Cummulative ₹ 51.72Lacs ( against 110.42Lacs )
on Sunday, August 27th 2023, 6:30:00 pm
83.78%
Financial Progress
5th Expenditure
of ₹ 4079524 (40.80 Lacs ) done.
Cummulative ₹ 92.51Lacs ( against 110.42Lacs )
on Sunday, September 24th 2023, 6:30:00 pm
84.24%
Financial Progress
6th Expenditure
of ₹ 50759 (0.51 Lacs ) done.
Cummulative ₹ 93.02Lacs ( against 110.42Lacs )
on Thursday, December 21st 2023, 6:30:00 pm
88.78%
Financial Progress
7th Expenditure
of ₹ 500974 (5.01 Lacs ) done.
Cummulative ₹ 98.03Lacs ( against 110.42Lacs )
on Monday, January 22nd 2024, 6:30:00 pm
89.35%
Financial Progress
8th Expenditure
of ₹ 62400 (0.62 Lacs ) done.
Cummulative ₹ 98.66Lacs ( against 110.42Lacs )
on Tuesday, February 27th 2024, 6:30:00 pm
96.10%
Financial Progress
9th Expenditure
of ₹ 745950 (7.46 Lacs ) done.
Cummulative ₹ 106.12Lacs ( against 110.42Lacs )
on Sunday, March 24th 2024, 6:30:00 pm
97.88%
Financial Progress
10th Expenditure
of ₹ 196612 (1.97 Lacs ) done.
Cummulative ₹ 108.08Lacs ( against 110.42Lacs )
on Tuesday, April 9th 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 5th time