5 years ago

on Tuesday, December 15th 2020, 6:30:00 pm
Work Sanctioned
जनपद बागेश्वर के विधानसभा क्षेत्र बागेश्वर के विकास खण्ड गरूड़ के अन्तर्गत गागरीगोल-तिलसारी मोटर मार्ग के किमी0 2 से चनोली-रामपुर-कोठो मोटर मार्ग में डामरीकरण का कार्य। (द्वितीय चरण)

5 years ago

on Thursday, January 21st 2021, 6:30:00 pm

Technical Sanction
of ₹ 75.48 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE latter no 146/1C

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
0.13%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 75.48Lacs )

4 years ago

on Thursday, December 16th 2021, 11:40:03 am
<span class="4">Picture Id:3793</span>
PWD Uttarakahnd
Photo (ID 3793) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : 0.6 Km Near Rampur Village
Remark : G3 Work

4 years ago

on Thursday, December 16th 2021, 11:44:55 am
<span class="4">Picture Id:3794</span>
PWD Uttarakahnd
Photo (ID 3794) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : 0.5 Km
Remark : G3 Work

4 years ago

on Sunday, December 19th 2021, 6:15:04 am
<span class="4">Picture Id:3815</span>
PWD Uttarakahnd
Photo (ID 3815) from Site Received
Uploader : Anuj, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : Chainage 0.125 r/wall
Remark : R/wall R.R dry

4 years ago

on Monday, December 20th 2021, 7:58:59 am
<span class="4">Picture Id:3821</span>
PWD Uttarakahnd
Photo (ID 3821) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : 0.250 First HP Bend
Remark : C/o of R/wall at first HP Bend

4 years ago

on Monday, December 20th 2021, 8:03:45 am
<span class="4">Picture Id:3822</span>
PWD Uttarakahnd
Photo (ID 3822) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : 0.250
Remark : . C/o R/wall

4 years ago

on Wednesday, December 29th 2021, 10:15:47 am
<span class="4">Picture Id:3960</span>
PWD Uttarakahnd
Photo (ID 3960) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 1 ch 0.25
Remark : C/o of Retaining wall

4 years ago

on Tuesday, January 4th 2022, 6:48:26 am
<span class="4">Picture Id:3997</span>
PWD Uttarakahnd
Photo (ID 3997) from Site Received
Uploader : Anuj, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0.125
Remark : R/wall in RR dry

4 years ago

on Tuesday, January 18th 2022, 6:11:09 am
<span class="4">Picture Id:4134</span>
PWD Uttarakahnd
Photo (ID 4134) from Site Received
Uploader : Anuj, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0.700
Remark : Construction of 1m rcc scupper in rampur kotho m/r

4 years ago

on Tuesday, January 18th 2022, 6:13:39 am
<span class="4">Picture Id:4135</span>
PWD Uttarakahnd
Photo (ID 4135) from Site Received
Uploader : Anuj, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0.675
Remark : R.R dry r/wall

4 years ago

on Wednesday, January 19th 2022, 8:40:38 am
<span class="4">Picture Id:4161</span>
PWD Uttarakahnd
Photo (ID 4161) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : 0.6 km
Remark : R/w

4 years ago

on Friday, February 11th 2022, 11:40:57 am
<span class="4">Picture Id:4328</span>
PWD Uttarakahnd
Photo (ID 4328) from Site Received
Uploader : Anuj, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0.100
Remark : B/wall in rampur kotho m/r

4 years ago

on Sunday, February 20th 2022, 7:35:08 am
<span class="4">Picture Id:4430</span>
PWD Uttarakahnd
Photo (ID 4430) from Site Received
Uploader : Anuj, Additional Assistant Engineer Civil ,TD Chakrata
Landmark : 0.100
Remark : Improvement and reconstruction work in rampur kotho m/r

3 years ago

on Monday, June 27th 2022, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
26.25%
Financial Progress

2nd Expenditure
of ₹ 1971200 (19.71 Lacs ) done.
Cummulative ₹ 19.81Lacs ( against 75.48Lacs )

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
62.67%
Financial Progress

3rd Expenditure
of ₹ 2749266 (27.49 Lacs ) done.
Cummulative ₹ 47.30Lacs ( against 75.48Lacs )

3 years ago

on Sunday, April 16th 2023, 6:30:00 pm
24%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Friday, June 2nd 2023, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Tuesday, June 27th 2023, 6:30:00 pm
80.97%
Financial Progress

4th Expenditure
of ₹ 1381075 (13.81 Lacs ) done.
Cummulative ₹ 61.12Lacs ( against 75.48Lacs )

2 years ago

on Monday, January 22nd 2024, 6:30:00 pm
81.01%
Financial Progress

5th Expenditure
of ₹ 3304 (0.03 Lacs ) done.
Cummulative ₹ 61.15Lacs ( against 75.48Lacs )