4 years ago

on Sunday, July 4th 2021, 6:30:00 pm
Work Sanctioned
कमेड़ी से पापे मोटर मार्ग में पार्ट-।। एवं सेतु के एप्रेाच का कार्य।

4 years ago

on Thursday, December 9th 2021, 8:15:38 am

Technical Sanction
of ₹ 60 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE latter no 2989/1C

3 years ago

on Monday, April 11th 2022, 5:31:57 am
<span class="4">Picture Id:5259</span>
PWD Uttarakahnd
Photo (ID 5259) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 1 ch 0.10
Remark : 5W864

3 years ago

on Monday, April 11th 2022, 5:37:33 am
<span class="4">Picture Id:5260</span>
PWD Uttarakahnd
Photo (ID 5260) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 1
Remark : R/w construction for bridge approach and profile correction

3 years ago

on Saturday, April 23rd 2022, 4:41:14 am
<span class="4">Picture Id:5380</span>
PWD Uttarakahnd
Photo (ID 5380) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Kamedi
Remark : Kamdi Pape bridge approach wall

3 years ago

on Saturday, April 23rd 2022, 4:42:58 am
<span class="4">Picture Id:8871</span>
PWD Uttarakahnd
Photo (ID 8871) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Kamedi
Remark : Bridge approach wall

3 years ago

on Saturday, April 23rd 2022, 5:47:41 am
<span class="4">Picture Id:8872</span>
PWD Uttarakahnd
Photo (ID 8872) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Kamedi Pape m/r
Remark : Kamedi Pape m/r HP bend

3 years ago

on Saturday, April 23rd 2022, 5:51:01 am
<span class="4">Picture Id:5425</span>
PWD Uttarakahnd
Photo (ID 5425) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 4 HM 0-2
Remark : Defect cutting in HP bend

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
52.63%
Financial Progress

1st Expenditure
of ₹ 3157642 (31.58 Lacs ) done.
Cummulative ₹ 31.58Lacs ( against 60Lacs )

3 years ago

on Thursday, December 22nd 2022, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Tuesday, December 27th 2022, 6:30:00 pm
53.63%
Financial Progress

2nd Expenditure
of ₹ 60220 (0.60 Lacs ) done.
Cummulative ₹ 32.18Lacs ( against 60Lacs )

3 years ago

on Friday, March 31st 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
63.35%
Financial Progress

3rd Expenditure
of ₹ 583005 (5.83 Lacs ) done.
Cummulative ₹ 38.01Lacs ( against 60Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable