on Sunday, July 4th 2021, 6:30:00 pm
Work Sanctioned
कमेड़ी से पापे मोटर मार्ग में पार्ट-।। एवं सेतु के एप्रेाच का कार्य।
on Thursday, December 9th 2021, 8:15:38 am
Technical Sanction
of ₹ 60 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE latter no 2989/1C
on Monday, April 11th 2022, 5:31:57 am
PWD UttarakahndPhoto (ID 5259) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 1 ch 0.10
Remark : 5W864
on Monday, April 11th 2022, 5:37:33 am
PWD UttarakahndPhoto (ID 5260) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 1
Remark : R/w construction for bridge approach and profile correction
on Saturday, April 23rd 2022, 4:41:14 am
PWD UttarakahndPhoto (ID 5380) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Kamedi
Remark : Kamdi Pape bridge approach wall
on Saturday, April 23rd 2022, 4:42:58 am
PWD UttarakahndPhoto (ID 8871) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Kamedi
Remark : Bridge approach wall
on Saturday, April 23rd 2022, 5:47:41 am
PWD UttarakahndPhoto (ID 8872) from Site Received
Uploader : Deepika Devi, Additional Assistant Engineer Civil ,CD Nainital
Landmark : Kamedi Pape m/r
Remark : Kamedi Pape m/r HP bend
on Saturday, April 23rd 2022, 5:51:01 am
PWD UttarakahndPhoto (ID 5425) from Site Received
Uploader : Nawal Kishor Dwivedi, Assistant Engineer Civil ,Almora Zone
Landmark : Km 4 HM 0-2
Remark : Defect cutting in HP bend
on Thursday, September 29th 2022, 6:30:00 pm
52.63%
Financial Progress
1st Expenditure
of ₹ 3157642 (31.58 Lacs ) done.
Cummulative ₹ 31.58Lacs ( against 60Lacs )
on Thursday, December 22nd 2022, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, December 27th 2022, 6:30:00 pm
53.63%
Financial Progress
2nd Expenditure
of ₹ 60220 (0.60 Lacs ) done.
Cummulative ₹ 32.18Lacs ( against 60Lacs )
on Friday, March 31st 2023, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, July 27th 2023, 6:30:00 pm
63.35%
Financial Progress
3rd Expenditure
of ₹ 583005 (5.83 Lacs ) done.
Cummulative ₹ 38.01Lacs ( against 60Lacs )