4 years ago

on Thursday, January 6th 2022, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद बागेश्वर के विधानसभा क्षेत्र-बागेश्वर के अन्तर्गत विवेकानन्द विद्या मंदिर इण्टर कालेज मण्डलसेरा से शम्भू जोशी के मकान के पास सरयू नदी की ओर सम्पर्क मोर्ग का निर्माण।

3 years ago

on Sunday, June 26th 2022, 6:58:08 am

Technical Sanction
of ₹ 40.42 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE Latter no-996/1C

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
0.29%
Financial Progress

1st Expenditure
of ₹ 11697 (0.12 Lacs ) done.
Cummulative ₹ 0.12Lacs ( against 40.42Lacs )

3 years ago

on Tuesday, December 27th 2022, 6:30:00 pm
27.70%
Financial Progress

2nd Expenditure
of ₹ 1108091 (11.08 Lacs ) done.
Cummulative ₹ 11.20Lacs ( against 40.42Lacs )

3 years ago

on Tuesday, January 3rd 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Sunday, May 28th 2023, 6:30:00 pm
30.95%
Financial Progress

3rd Expenditure
of ₹ 131180 (1.31 Lacs ) done.
Cummulative ₹ 12.51Lacs ( against 40.42Lacs )

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
77.17%
Financial Progress

4th Expenditure
of ₹ 1868280 (18.68 Lacs ) done.
Cummulative ₹ 31.19Lacs ( against 40.42Lacs )

2 years ago

on Sunday, September 24th 2023, 6:30:00 pm
84.40%
Financial Progress

5th Expenditure
of ₹ 292000 (2.92 Lacs ) done.
Cummulative ₹ 34.11Lacs ( against 40.42Lacs )

10 months ago

on Saturday, October 26th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 2nd time

10 months ago

on Monday, October 28th 2024, 6:30:00 pm
85.75%
Financial Progress

6th Expenditure
of ₹ 54779 (0.55 Lacs ) done.
Cummulative ₹ 34.66Lacs ( against 40.42Lacs )

10 months ago

on Monday, October 28th 2024, 6:30:00 pm
87.20%
Financial Progress

7th Expenditure
of ₹ 58500 (0.58 Lacs ) done.
Cummulative ₹ 35.25Lacs ( against 40.42Lacs )

6 months ago

on Monday, March 17th 2025, 6:30:00 pm
87.45%
Financial Progress

8th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 35.35Lacs ( against 40.42Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
90.70%
Financial Progress

9th Expenditure
of ₹ 131620 (1.32 Lacs ) done.
Cummulative ₹ 36.66Lacs ( against 40.42Lacs )

2 months ago

on Sunday, July 6th 2025, 6:30:00 pm
92.13%
Financial Progress

10th Expenditure
of ₹ 57589 (0.58 Lacs ) done.
Cummulative ₹ 37.24Lacs ( against 40.42Lacs )