on Tuesday, March 5th 2019, 6:30:00 pm
Work Sanctioned
सरायबसेढ़ी मोटर मार्ग का सुदृढ़ीकरण एवं चैड़ीकरण का कार्य (कि0मी0 1 से 21 तक)।
on Wednesday, December 9th 2020, 7:40:56 am
Technical Sanction
of ₹ 3332.41 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 3613/02Ra0Ma0-UK/2021
on Tuesday, March 30th 2021, 6:30:00 pm
6.00%
Financial Progress
1st Expenditure
of ₹ 20000000 (200.00 Lacs ) done.
Cummulative ₹ 200.00Lacs ( against 3332.41Lacs )
on Friday, July 2nd 2021, 6:30:00 pm
6.00%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 200.00Lacs ( against 3332.41Lacs )
on Friday, July 2nd 2021, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, July 29th 2021, 6:30:00 pm
42%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, August 12th 2021, 6:30:00 pm
24.18%
Financial Progress
3rd Expenditure
of ₹ 60570453 (605.70 Lacs ) done.
Cummulative ₹ 805.70Lacs ( against 3332.41Lacs )
on Monday, August 16th 2021, 6:13:48 am
PWD UttarakahndPhoto (ID 738) from Site Received
Uploader : Devendra Pal Singh Negi, Executive Engineer Civil ,Engineer-in-Chief Office
Landmark : Km 15.00
Remark : DBM work for km 15.00.
on Monday, August 16th 2021, 6:16:36 am
PWD UttarakahndPhoto (ID 739) from Site Received
Uploader : Devendra Pal Singh Negi, Executive Engineer Civil ,Engineer-in-Chief Office
Landmark : 14.540
Remark : DBM near aithal railway station.
on Wednesday, September 22nd 2021, 4:51:34 am
PWD UttarakahndPhoto (ID 1534) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 3.325
Remark : Reinforcement of raft For 60mtr span box culvert. Quality found ok
on Wednesday, September 22nd 2021, 6:11:13 am
PWD UttarakahndPhoto (ID 1537) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 3.325
Remark : Bridge of 60.00meter span box culvert, raft reinforcement
on Thursday, September 23rd 2021, 4:45:59 am
PWD UttarakahndPhoto (ID 1648) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 3.325 box culvert
Remark : 60 meter box culvert raft concrete
on Tuesday, September 28th 2021, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, September 30th 2021, 6:27:26 am
PWD UttarakahndPhoto (ID 1868) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 3.325
Remark : 60 meter box culvert sarai basari
on Sunday, October 3rd 2021, 6:30:00 pm
24.20%
Financial Progress
4th Expenditure
of ₹ 76895 (0.77 Lacs ) done.
Cummulative ₹ 806.47Lacs ( against 3332.41Lacs )
on Monday, October 4th 2021, 6:38:37 am
PWD UttarakahndPhoto (ID 1973) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 3.230
Remark : Curing work for raft of 60mtr span box culvert work.
on Monday, October 4th 2021, 6:52:36 am
PWD UttarakahndPhoto (ID 1978) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 13.00
Remark : Diversion work start for 20 mtr span box culvert.
on Monday, October 4th 2021, 7:16:02 am
PWD UttarakahndPhoto (ID 1981) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 13.00
Remark : Diversion work start for 20mtr span box culvert work.
on Monday, October 4th 2021, 7:23:18 am
PWD UttarakahndPhoto (ID 1984) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 14.110
Remark : Reinforcement work in progress for 2 mtr span box culvert.
on Thursday, October 7th 2021, 8:09:37 am
PWD UttarakahndPhoto (ID 2186) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 15.750
Remark : Maintaining Camber and super elevation (Profile correction) for DBM work.
on Thursday, October 7th 2021, 10:42:52 am
PWD UttarakahndPhoto (ID 2206) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 14.550
Remark : Ready WMM surface for DBM work
on Thursday, October 7th 2021, 10:57:02 am
PWD UttarakahndPhoto (ID 2208) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 15.520
Remark : Checking Camber in WMM surface.
on Thursday, October 7th 2021, 11:04:16 am
PWD UttarakahndPhoto (ID 2209) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 15.470
Remark : Checking Camber on WMM work found 3%.
on Sunday, October 10th 2021, 4:13:35 am
PWD UttarakahndPhoto (ID 2390) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 14.240
Remark : Raft casting for 2mtr culvert
on Sunday, October 10th 2021, 4:50:12 am
PWD UttarakahndPhoto (ID 2391) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 15.200
Remark : DBM work.
on Monday, October 11th 2021, 4:48:59 am
PWD UttarakahndPhoto (ID 2392) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 15.700
Remark : DBM work
on Friday, October 22nd 2021, 5:01:22 am
PWD UttarakahndPhoto (ID 2740) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 17.00
Remark : BC work start.
on Thursday, October 28th 2021, 5:47:23 am
PWD UttarakahndPhoto (ID 2898) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 19.700
Remark : WMM work .
on Thursday, October 28th 2021, 8:47:15 am
PWD UttarakahndPhoto (ID 2912) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 18.300
Remark : BC work in progress
on Thursday, October 28th 2021, 9:17:13 am
PWD UttarakahndPhoto (ID 2913) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 18.400
Remark : BC work in progress
on Sunday, October 31st 2021, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 4th time
on Monday, November 1st 2021, 6:30:00 pm
38.82%
Financial Progress
5th Expenditure
of ₹ 48718225 (487.18 Lacs ) done.
Cummulative ₹ 1293.66Lacs ( against 3332.41Lacs )
on Friday, November 12th 2021, 5:25:37 am
PWD UttarakahndPhoto (ID 3407) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 4.600
Remark : BC work over DBM.
on Friday, November 12th 2021, 5:37:08 am
PWD UttarakahndPhoto (ID 3408) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 3.400
Remark : Shuttering work in progress for 60mtr span RCC culvert.
on Friday, November 12th 2021, 7:51:28 am
PWD UttarakahndPhoto (ID 3410) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 13.00
Remark : Diversion work complete for 20 mtr span box culvert.
on Wednesday, November 17th 2021, 3:29:01 am
PWD UttarakahndPhoto (ID 3477) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 13.00
Remark : Dismantling start for 20mtr Span box culvert.
on Friday, November 19th 2021, 11:56:41 am
PWD UttarakahndPhoto (ID 3521) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 13.00
Remark : Taking levels for 20 mtr Span box culvert.
on Tuesday, November 23rd 2021, 8:07:07 am
PWD UttarakahndPhoto (ID 3559) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 3.320
Remark : Curing work
on Tuesday, November 23rd 2021, 8:12:27 am
PWD UttarakahndPhoto (ID 3560) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 3.340
Remark : Curing work.
on Tuesday, November 23rd 2021, 9:04:23 am
PWD UttarakahndPhoto (ID 3561) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 13.00
Remark : Excavation for key...
on Friday, January 14th 2022, 6:30:00 pm
50.12%
Financial Progress
6th Expenditure
of ₹ 37640483 (376.40 Lacs ) done.
Cummulative ₹ 1670.06Lacs ( against 3332.41Lacs )
on Wednesday, January 19th 2022, 5:19:12 am
PWD UttarakahndPhoto (ID 4149) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 3.320
Remark : Curing of slab of 60mtr Span Box culvert.
on Wednesday, January 19th 2022, 5:31:03 am
PWD UttarakahndPhoto (ID 4150) from Site Received
Uploader : Anurag Dev, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 3+320
Remark : Preparing for casting of remaining 20 mtr part of 60 mtr Span box culvert.
on Sunday, January 23rd 2022, 6:30:00 pm
50.13%
Financial Progress
7th Expenditure
of ₹ 48100 (0.48 Lacs ) done.
Cummulative ₹ 1670.54Lacs ( against 3332.41Lacs )
on Monday, February 21st 2022, 6:30:00 pm
50.17%
Financial Progress
8th Expenditure
of ₹ 132946 (1.33 Lacs ) done.
Cummulative ₹ 1671.87Lacs ( against 3332.41Lacs )
on Tuesday, March 22nd 2022, 6:30:00 pm
54.87%
Financial Progress
9th Expenditure
of ₹ 15650517 (156.51 Lacs ) done.
Cummulative ₹ 1828.38Lacs ( against 3332.41Lacs )
on Wednesday, March 23rd 2022, 6:30:00 pm
58.43%
Financial Progress
10th Expenditure
of ₹ 11887240 (118.87 Lacs ) done.
Cummulative ₹ 1947.25Lacs ( against 3332.41Lacs )
on Wednesday, March 23rd 2022, 6:30:00 pm
58.47%
Financial Progress
11th Expenditure
of ₹ 120242 (1.20 Lacs ) done.
Cummulative ₹ 1948.45Lacs ( against 3332.41Lacs )
on Wednesday, March 23rd 2022, 6:30:00 pm
58.52%
Financial Progress
12th Expenditure
of ₹ 154899 (1.55 Lacs ) done.
Cummulative ₹ 1950.00Lacs ( against 3332.41Lacs )
on Friday, April 1st 2022, 6:30:00 pm
92%
Physical Progress
Physical Progress Reported at 5th time
on Saturday, April 2nd 2022, 9:13:41 am
PWD UttarakahndPhoto (ID 5145) from Site Received
Uploader : Ashok Kumar, Assistant Engineer Civil ,CD Pabo
Landmark : 15.150 Near Aithel
Remark : Thermoplastic Paint on the Road in chainage 15.150.
on Thursday, May 26th 2022, 6:30:00 pm
63.29%
Financial Progress
13th Expenditure
of ₹ 15918410 (159.18 Lacs ) done.
Cummulative ₹ 2109.18Lacs ( against 3332.41Lacs )
on Tuesday, June 7th 2022, 6:30:00 pm
63.32%
Financial Progress
14th Expenditure
of ₹ 102000 (1.02 Lacs ) done.
Cummulative ₹ 2110.20Lacs ( against 3332.41Lacs )
on Tuesday, June 14th 2022, 6:30:00 pm
63.35%
Financial Progress
15th Expenditure
of ₹ 97798 (0.98 Lacs ) done.
Cummulative ₹ 2111.18Lacs ( against 3332.41Lacs )
on Sunday, July 24th 2022, 6:30:00 pm
63.36%
Financial Progress
16th Expenditure
of ₹ 17622 (0.18 Lacs ) done.
Cummulative ₹ 2111.36Lacs ( against 3332.41Lacs )
on Monday, July 25th 2022, 6:30:00 pm
63.36%
Financial Progress
17th Expenditure
of ₹ 16546 (0.17 Lacs ) done.
Cummulative ₹ 2111.52Lacs ( against 3332.41Lacs )
on Tuesday, July 26th 2022, 6:30:00 pm
63.39%
Financial Progress
18th Expenditure
of ₹ 102000 (1.02 Lacs ) done.
Cummulative ₹ 2112.54Lacs ( against 3332.41Lacs )
on Tuesday, July 26th 2022, 6:30:00 pm
63.42%
Financial Progress
19th Expenditure
of ₹ 81232 (0.81 Lacs ) done.
Cummulative ₹ 2113.36Lacs ( against 3332.41Lacs )
on Thursday, December 1st 2022, 6:30:00 pm
63.44%
Financial Progress
20th Expenditure
of ₹ 58688 (0.59 Lacs ) done.
Cummulative ₹ 2113.94Lacs ( against 3332.41Lacs )
on Sunday, December 4th 2022, 6:30:00 pm
63.47%
Financial Progress
21st Expenditure
of ₹ 97704 (0.98 Lacs ) done.
Cummulative ₹ 2114.92Lacs ( against 3332.41Lacs )
on Sunday, January 29th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time
on Sunday, February 5th 2023, 6:30:00 pm
72.02%
Financial Progress
22nd Expenditure
of ₹ 28500000 (285.00 Lacs ) done.
Cummulative ₹ 2399.92Lacs ( against 3332.41Lacs )
on Tuesday, March 21st 2023, 6:30:00 pm
73.26%
Financial Progress
23rd Expenditure
of ₹ 4132000 (41.32 Lacs ) done.
Cummulative ₹ 2441.24Lacs ( against 3332.41Lacs )
on Wednesday, August 23rd 2023, 6:30:00 pm
75.33%
Financial Progress
24th Expenditure
of ₹ 6909461 (69.09 Lacs ) done.
Cummulative ₹ 2510.33Lacs ( against 3332.41Lacs )
on Monday, November 6th 2023, 6:30:00 pm
75.37%
Financial Progress
25th Expenditure
of ₹ 119501 (1.20 Lacs ) done.
Cummulative ₹ 2511.53Lacs ( against 3332.41Lacs )
on Monday, November 6th 2023, 6:30:00 pm
75.39%
Financial Progress
26th Expenditure
of ₹ 92860 (0.93 Lacs ) done.
Cummulative ₹ 2512.46Lacs ( against 3332.41Lacs )
on Monday, November 6th 2023, 6:30:00 pm
75.41%
Financial Progress
27th Expenditure
of ₹ 54806 (0.55 Lacs ) done.
Cummulative ₹ 2513.01Lacs ( against 3332.41Lacs )
on Wednesday, June 26th 2024, 6:30:00 pm
75.43%
Financial Progress
28th Expenditure
of ₹ 62000 (0.62 Lacs ) done.
Cummulative ₹ 2513.63Lacs ( against 3332.41Lacs )
on Wednesday, June 26th 2024, 6:30:00 pm
75.47%
Financial Progress
29th Expenditure
of ₹ 123977 (1.24 Lacs ) done.
Cummulative ₹ 2514.87Lacs ( against 3332.41Lacs )
on Wednesday, June 26th 2024, 6:30:00 pm
75.97%
Financial Progress
30th Expenditure
of ₹ 1668658 (16.69 Lacs ) done.
Cummulative ₹ 2531.55Lacs ( against 3332.41Lacs )
on Wednesday, June 26th 2024, 6:30:00 pm
76.46%
Financial Progress
31st Expenditure
of ₹ 1631717 (16.32 Lacs ) done.
Cummulative ₹ 2547.87Lacs ( against 3332.41Lacs )
on Wednesday, June 26th 2024, 6:30:00 pm
76.81%
Financial Progress
32nd Expenditure
of ₹ 1185027 (11.85 Lacs ) done.
Cummulative ₹ 2559.72Lacs ( against 3332.41Lacs )
on Wednesday, June 26th 2024, 6:30:00 pm
76.83%
Financial Progress
33rd Expenditure
of ₹ 73200 (0.73 Lacs ) done.
Cummulative ₹ 2560.45Lacs ( against 3332.41Lacs )
on Friday, August 2nd 2024, 6:30:00 pm
77.26%
Financial Progress
34th Expenditure
of ₹ 1427206 (14.27 Lacs ) done.
Cummulative ₹ 2574.72Lacs ( against 3332.41Lacs )
on Friday, August 2nd 2024, 6:30:00 pm
77.69%
Financial Progress
35th Expenditure
of ₹ 1427206 (14.27 Lacs ) done.
Cummulative ₹ 2589.00Lacs ( against 3332.41Lacs )
on Friday, August 23rd 2024, 6:30:00 pm
77.70%
Financial Progress
36th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 2589.31Lacs ( against 3332.41Lacs )
on Thursday, August 29th 2024, 6:30:00 pm
77.71%
Financial Progress
37th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 2589.62Lacs ( against 3332.41Lacs )
on Thursday, October 10th 2024, 6:30:00 pm
77.75%
Financial Progress
38th Expenditure
of ₹ 118271 (1.18 Lacs ) done.
Cummulative ₹ 2590.80Lacs ( against 3332.41Lacs )
on Thursday, October 10th 2024, 6:30:00 pm
77.78%
Financial Progress
39th Expenditure
of ₹ 118271 (1.18 Lacs ) done.
Cummulative ₹ 2591.98Lacs ( against 3332.41Lacs )
on Tuesday, October 22nd 2024, 6:30:00 pm
77.85%
Financial Progress
40th Expenditure
of ₹ 223393 (2.23 Lacs ) done.
Cummulative ₹ 2594.22Lacs ( against 3332.41Lacs )
on Thursday, October 24th 2024, 6:30:00 pm
77.88%
Financial Progress
41st Expenditure
of ₹ 118271 (1.18 Lacs ) done.
Cummulative ₹ 2595.40Lacs ( against 3332.41Lacs )
on Sunday, October 27th 2024, 6:30:00 pm
77.95%
Financial Progress
42nd Expenditure
of ₹ 223393 (2.23 Lacs ) done.
Cummulative ₹ 2597.63Lacs ( against 3332.41Lacs )
on Monday, January 13th 2025, 6:30:00 pm
77.97%
Financial Progress
43rd Expenditure
of ₹ 76895 (0.77 Lacs ) done.
Cummulative ₹ 2598.40Lacs ( against 3332.41Lacs )
on Monday, January 13th 2025, 6:30:00 pm
78.00%
Financial Progress
44th Expenditure
of ₹ 102916 (1.03 Lacs ) done.
Cummulative ₹ 2599.43Lacs ( against 3332.41Lacs )
on Tuesday, January 14th 2025, 6:30:00 pm
78.02%
Financial Progress
45th Expenditure
of ₹ 48321 (0.48 Lacs ) done.
Cummulative ₹ 2599.91Lacs ( against 3332.41Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
78.03%
Financial Progress
46th Expenditure
of ₹ 35553 (0.36 Lacs ) done.
Cummulative ₹ 2600.27Lacs ( against 3332.41Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
78.03%
Financial Progress
47th Expenditure
of ₹ 14230 (0.14 Lacs ) done.
Cummulative ₹ 2600.41Lacs ( against 3332.41Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
78.04%
Financial Progress
48th Expenditure
of ₹ 16332 (0.16 Lacs ) done.
Cummulative ₹ 2600.57Lacs ( against 3332.41Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
78.06%
Financial Progress
49th Expenditure
of ₹ 55335 (0.55 Lacs ) done.
Cummulative ₹ 2601.13Lacs ( against 3332.41Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
78.10%
Financial Progress
50th Expenditure
of ₹ 159222 (1.59 Lacs ) done.
Cummulative ₹ 2602.72Lacs ( against 3332.41Lacs )
on Tuesday, January 21st 2025, 6:30:00 pm
78.15%
Financial Progress
51st Expenditure
of ₹ 162585 (1.63 Lacs ) done.
Cummulative ₹ 2604.35Lacs ( against 3332.41Lacs )
on Sunday, January 26th 2025, 6:30:00 pm
78.16%
Financial Progress
52nd Expenditure
of ₹ 10083 (0.10 Lacs ) done.
Cummulative ₹ 2604.45Lacs ( against 3332.41Lacs )
on Tuesday, February 11th 2025, 6:30:00 pm
78.17%
Financial Progress
53rd Expenditure
of ₹ 44357 (0.44 Lacs ) done.
Cummulative ₹ 2604.89Lacs ( against 3332.41Lacs )
on Tuesday, February 11th 2025, 6:30:00 pm
78.18%
Financial Progress
54th Expenditure
of ₹ 27376 (0.27 Lacs ) done.
Cummulative ₹ 2605.16Lacs ( against 3332.41Lacs )
on Sunday, February 23rd 2025, 6:30:00 pm
78.20%
Financial Progress
55th Expenditure
of ₹ 81382 (0.81 Lacs ) done.
Cummulative ₹ 2605.98Lacs ( against 3332.41Lacs )
on Sunday, February 23rd 2025, 6:30:00 pm
78.21%
Financial Progress
56th Expenditure
of ₹ 25207 (0.25 Lacs ) done.
Cummulative ₹ 2606.23Lacs ( against 3332.41Lacs )
on Sunday, February 23rd 2025, 6:30:00 pm
78.21%
Financial Progress
57th Expenditure
of ₹ 7762 (0.08 Lacs ) done.
Cummulative ₹ 2606.31Lacs ( against 3332.41Lacs )
on Sunday, February 23rd 2025, 6:30:00 pm
78.24%
Financial Progress
58th Expenditure
of ₹ 92000 (0.92 Lacs ) done.
Cummulative ₹ 2607.23Lacs ( against 3332.41Lacs )
on Friday, February 28th 2025, 6:30:00 pm
78.25%
Financial Progress
59th Expenditure
of ₹ 25941 (0.26 Lacs ) done.
Cummulative ₹ 2607.49Lacs ( against 3332.41Lacs )
on Friday, February 28th 2025, 6:30:00 pm
78.25%
Financial Progress
60th Expenditure
of ₹ 6741 (0.07 Lacs ) done.
Cummulative ₹ 2607.55Lacs ( against 3332.41Lacs )
on Thursday, March 27th 2025, 6:30:00 pm
78.59%
Financial Progress
61st Expenditure
of ₹ 1131000 (11.31 Lacs ) done.
Cummulative ₹ 2618.86Lacs ( against 3332.41Lacs )
on Thursday, May 29th 2025, 6:30:00 pm
79.49%
Financial Progress
62nd Expenditure
of ₹ 3020947 (30.21 Lacs ) done.
Cummulative ₹ 2649.07Lacs ( against 3332.41Lacs )
on Monday, June 9th 2025, 6:30:00 pm
79.50%
Financial Progress
63rd Expenditure
of ₹ 3906 (0.04 Lacs ) done.
Cummulative ₹ 2649.11Lacs ( against 3332.41Lacs )
on Friday, August 1st 2025, 6:30:00 pm
79.55%
Financial Progress
64th Expenditure
of ₹ 172398 (1.72 Lacs ) done.
Cummulative ₹ 2650.84Lacs ( against 3332.41Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
79.55%
Financial Progress
65th Expenditure
of ₹ 17019 (0.17 Lacs ) done.
Cummulative ₹ 2651.01Lacs ( against 3332.41Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
80.17%
Financial Progress
66th Expenditure
of ₹ 2053048 (20.53 Lacs ) done.
Cummulative ₹ 2671.54Lacs ( against 3332.41Lacs )
on Sunday, September 14th 2025, 6:30:00 pm
80.17%
Financial Progress
67th Expenditure
of ₹ 18054 (0.18 Lacs ) done.
Cummulative ₹ 2671.72Lacs ( against 3332.41Lacs )
on Thursday, September 25th 2025, 6:30:00 pm
80.19%
Financial Progress
68th Expenditure
of ₹ 62000 (0.62 Lacs ) done.
Cummulative ₹ 2672.34Lacs ( against 3332.41Lacs )
on Wednesday, October 15th 2025, 6:30:00 pm
80.70%
Financial Progress
69th Expenditure
of ₹ 1695432 (16.95 Lacs ) done.
Cummulative ₹ 2689.29Lacs ( against 3332.41Lacs )