6 years ago

on Monday, March 30th 2020, 6:30:00 pm
Work Sanctioned
वार्षिक योजना 2019-20 के अन्तर्गत, राष्ट्रीय राजमार्ग 121 (नया नाम 309) के कि०मी० 110.00 से कि०मी० 262.00 तक में 6 मी० स्पान पुलिया एवं सुरक्षात्मक कार्य।

6 years ago

on Tuesday, March 31st 2020, 7:11:22 am

Technical Sanction
of ₹ 480.56 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. F. No. -RO/UK/12014/130/Annual Plan /2019-20

5 years ago

on Monday, November 9th 2020, 6:30:00 pm
12.47%
Financial Progress

1st Expenditure
of ₹ 5993719 (59.94 Lacs ) done.
Cummulative ₹ 59.94Lacs ( against 480.56Lacs )

5 years ago

on Tuesday, February 23rd 2021, 6:30:00 pm
32.50%
Financial Progress

2nd Expenditure
of ₹ 9625272 (96.25 Lacs ) done.
Cummulative ₹ 156.19Lacs ( against 480.56Lacs )

4 years ago

on Monday, June 28th 2021, 6:30:00 pm
47.23%
Financial Progress

3rd Expenditure
of ₹ 7075801 (70.76 Lacs ) done.
Cummulative ₹ 226.95Lacs ( against 480.56Lacs )

4 years ago

on Friday, July 23rd 2021, 7:55:50 am
<span class="4">Picture Id:403</span>
PWD Uttarakahnd
Photo (ID 403) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 220.375
Remark : Culvert work is completed and approch road work in progress

4 years ago

on Friday, July 23rd 2021, 8:01:43 am
<span class="4">Picture Id:404</span>
PWD Uttarakahnd
Photo (ID 404) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Culvert upto bed level complete and slab work in progress

4 years ago

on Friday, July 23rd 2021, 8:09:58 am
<span class="4">Picture Id:405</span>
PWD Uttarakahnd
Photo (ID 405) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 217+450
Remark : Culvert upto bed level complete and approch road wall in progress

4 years ago

on Friday, July 23rd 2021, 8:13:57 am
<span class="4">Picture Id:406</span>
PWD Uttarakahnd
Photo (ID 406) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+900
Remark : Culvert upto bed block level complete and slab work in progress

4 years ago

on Friday, July 23rd 2021, 8:17:34 am
<span class="4">Picture Id:407</span>
PWD Uttarakahnd
Photo (ID 407) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+250
Remark : Slab reinforcement work in progress

4 years ago

on Friday, July 23rd 2021, 8:31:33 am
<span class="4">Picture Id:408</span>
PWD Uttarakahnd
Photo (ID 408) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 210+900
Remark : Culvert work complete and approch road work in progress

4 years ago

on Friday, July 23rd 2021, 8:34:38 am
<span class="4">Picture Id:409</span>
PWD Uttarakahnd
Photo (ID 409) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 210+400
Remark : Culvert up to slab level complete and slab work in progress

4 years ago

on Monday, July 26th 2021, 6:30:00 pm
54%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Sunday, August 15th 2021, 11:52:35 am
<span class="4">Picture Id:682</span>
PWD Uttarakahnd
Photo (ID 682) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+250
Remark : Slab reinforcement work in complete

4 years ago

on Sunday, August 15th 2021, 12:04:05 pm
<span class="4">Picture Id:683</span>
PWD Uttarakahnd
Photo (ID 683) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Slab reinforcement work in complete .

4 years ago

on Sunday, August 15th 2021, 12:25:38 pm
<span class="4">Picture Id:690</span>
PWD Uttarakahnd
Photo (ID 690) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 210+200
Remark : Culvert up to bed block level complete

4 years ago

on Monday, August 16th 2021, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Tuesday, September 21st 2021, 7:20:51 am
<span class="4">Picture Id:1465</span>
PWD Uttarakahnd
Photo (ID 1465) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Slab work completed and approach road work in progress

4 years ago

on Tuesday, September 21st 2021, 7:24:58 am
<span class="4">Picture Id:1466</span>
PWD Uttarakahnd
Photo (ID 1466) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Culvert work is completed approach road work in progress

4 years ago

on Tuesday, September 21st 2021, 7:34:40 am
<span class="4">Picture Id:1467</span>
PWD Uttarakahnd
Photo (ID 1467) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+250
Remark : Slab culvert work completed and approach road work in progress

4 years ago

on Sunday, October 3rd 2021, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 3rd time

4 years ago

on Monday, October 4th 2021, 8:12:33 am
<span class="4">Picture Id:1990</span>
PWD Uttarakahnd
Photo (ID 1990) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 217+450
Remark : Reinforced work completed

4 years ago

on Monday, October 4th 2021, 8:30:36 am
<span class="4">Picture Id:1992</span>
PWD Uttarakahnd
Photo (ID 1992) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Culvert open for traffic

4 years ago

on Wednesday, October 27th 2021, 6:30:00 pm
61.29%
Financial Progress

4th Expenditure
of ₹ 6757680 (67.58 Lacs ) done.
Cummulative ₹ 294.52Lacs ( against 480.56Lacs )

4 years ago

on Monday, November 22nd 2021, 6:30:00 pm
73%

Physical Progress
Physical Progress Reported at 4th time

4 years ago

on Wednesday, December 15th 2021, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 5th time

4 years ago

on Tuesday, January 4th 2022, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 6th time

4 years ago

on Friday, April 1st 2022, 6:30:00 pm
85%

Physical Progress
Physical Progress Reported at 7th time

3 years ago

on Saturday, January 7th 2023, 6:30:00 pm
92%

Physical Progress
Physical Progress Reported at 8th time

2 years ago

on Tuesday, April 2nd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 9th time