Work Sanctioned
वार्षिक योजना 2019-20 के अन्तर्गत, राष्ट्रीय राजमार्ग 121 (नया नाम 309) के कि०मी० 110.00 से कि०मी० 262.00 तक में 6 मी० स्पान पुलिया एवं सुरक्षात्मक कार्य।
on Tuesday, March 31st 2020, 7:11:22 am
Technical Sanction
of ₹ 480.56 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. F. No. -RO/UK/12014/130/Annual Plan /2019-20
on Monday, November 9th 2020, 6:30:00 pm
12.47%
Financial Progress
1st Expenditure
of ₹ 5993719 (59.94 Lacs ) done.
Cummulative ₹ 59.94Lacs ( against 480.56Lacs )
on Tuesday, February 23rd 2021, 6:30:00 pm
32.50%
Financial Progress
2nd Expenditure
of ₹ 9625272 (96.25 Lacs ) done.
Cummulative ₹ 156.19Lacs ( against 480.56Lacs )
on Monday, June 28th 2021, 6:30:00 pm
47.23%
Financial Progress
3rd Expenditure
of ₹ 7075801 (70.76 Lacs ) done.
Cummulative ₹ 226.95Lacs ( against 480.56Lacs )
on Friday, July 23rd 2021, 7:55:50 am
PWD UttarakahndPhoto (ID 403) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 220.375
Remark : Culvert work is completed and approch road work in progress
on Friday, July 23rd 2021, 8:01:43 am
PWD UttarakahndPhoto (ID 404) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Culvert upto bed level complete and slab work in progress
on Friday, July 23rd 2021, 8:09:58 am
PWD UttarakahndPhoto (ID 405) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 217+450
Remark : Culvert upto bed level complete and approch road wall in progress
on Friday, July 23rd 2021, 8:13:57 am
PWD UttarakahndPhoto (ID 406) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+900
Remark : Culvert upto bed block level complete and slab work in progress
on Friday, July 23rd 2021, 8:17:34 am
PWD UttarakahndPhoto (ID 407) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+250
Remark : Slab reinforcement work in progress
on Friday, July 23rd 2021, 8:31:33 am
PWD UttarakahndPhoto (ID 408) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 210+900
Remark : Culvert work complete and approch road work in progress
on Friday, July 23rd 2021, 8:34:38 am
PWD UttarakahndPhoto (ID 409) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 210+400
Remark : Culvert up to slab level complete and slab work in progress
on Monday, July 26th 2021, 6:30:00 pm
54%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, August 15th 2021, 11:52:35 am
PWD UttarakahndPhoto (ID 682) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+250
Remark : Slab reinforcement work in complete
on Sunday, August 15th 2021, 12:04:05 pm
PWD UttarakahndPhoto (ID 683) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Slab reinforcement work in complete .
on Sunday, August 15th 2021, 12:25:38 pm
PWD UttarakahndPhoto (ID 690) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 210+200
Remark : Culvert up to bed block level complete
on Monday, August 16th 2021, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, September 21st 2021, 7:20:51 am
PWD UttarakahndPhoto (ID 1465) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Slab work completed and approach road work in progress
on Tuesday, September 21st 2021, 7:24:58 am
PWD UttarakahndPhoto (ID 1466) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Culvert work is completed approach road work in progress
on Tuesday, September 21st 2021, 7:34:40 am
PWD UttarakahndPhoto (ID 1467) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 216+250
Remark : Slab culvert work completed and approach road work in progress
on Sunday, October 3rd 2021, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, October 4th 2021, 8:12:33 am
PWD UttarakahndPhoto (ID 1990) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 217+450
Remark : Reinforced work completed
on Monday, October 4th 2021, 8:30:36 am
PWD UttarakahndPhoto (ID 1992) from Site Received
Uploader : Anurag Singh Bisht, Junior Engineer Civil ,NH Div Dhumakot
Landmark : 219+050
Remark : Culvert open for traffic
on Wednesday, October 27th 2021, 6:30:00 pm
61.29%
Financial Progress
4th Expenditure
of ₹ 6757680 (67.58 Lacs ) done.
Cummulative ₹ 294.52Lacs ( against 480.56Lacs )
on Monday, November 22nd 2021, 6:30:00 pm
73%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, December 15th 2021, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 5th time
on Tuesday, January 4th 2022, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 6th time
on Friday, April 1st 2022, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 7th time
on Saturday, January 7th 2023, 6:30:00 pm
92%
Physical Progress
Physical Progress Reported at 8th time
on Tuesday, April 2nd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 9th time