Work Sanctioned
राष्ट्रीय राजमार्ग 119 (नया नाम 534) के कि०मी० 28.00 से कि०मी० 34.00 तक एवं कि०मी० 44.00 से कि०मी० 58.00 तक में सुदृढीकरण तथा कि०मी० 23 .00 से कि०मी० 78.00 तक में सुरक्षात्मक कार्य।

6 years ago

on Tuesday, January 7th 2020, 7:14:30 am

Technical Sanction
of ₹ 1689.43 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. F.No. RO/UK/12014/111/Annual Plan /2019-20

5 years ago

on Monday, December 28th 2020, 6:30:00 pm
10.76%
Financial Progress

1st Expenditure
of ₹ 18173178 (181.73 Lacs ) done.
Cummulative ₹ 181.73Lacs ( against 1689.43Lacs )

5 years ago

on Friday, March 26th 2021, 6:30:00 pm
18.75%
Financial Progress

2nd Expenditure
of ₹ 13509944 (135.10 Lacs ) done.
Cummulative ₹ 316.83Lacs ( against 1689.43Lacs )

4 years ago

on Sunday, May 23rd 2021, 6:30:00 pm
171.61%
Financial Progress

3rd Expenditure
of ₹ 258232318 (2582.32 Lacs ) done.
Cummulative ₹ 2899.15Lacs ( against 1689.43Lacs )

4 years ago

on Sunday, May 23rd 2021, 6:30:00 pm
34.03%
Financial Progress

4th Expenditure
of ₹ -232430003 (-2324.30 Lacs ) done.
Cummulative ₹ 574.85Lacs ( against 1689.43Lacs )

4 years ago

on Thursday, June 17th 2021, 6:30:00 pm
34.05%
Financial Progress

5th Expenditure
of ₹ 42480 (0.42 Lacs ) done.
Cummulative ₹ 575.28Lacs ( against 1689.43Lacs )

4 years ago

on Thursday, June 17th 2021, 6:30:00 pm
34.08%
Financial Progress

6th Expenditure
of ₹ 46610 (0.47 Lacs ) done.
Cummulative ₹ 575.75Lacs ( against 1689.43Lacs )

4 years ago

on Thursday, June 17th 2021, 6:30:00 pm
34.11%
Financial Progress

7th Expenditure
of ₹ 46610 (0.47 Lacs ) done.
Cummulative ₹ 576.21Lacs ( against 1689.43Lacs )

4 years ago

on Monday, July 26th 2021, 6:30:00 pm
47%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Monday, August 16th 2021, 7:06:49 am
<span class="4">Picture Id:753</span>
PWD Uttarakahnd
Photo (ID 753) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C.H -31.860
Remark : R/wall in wire crate. Work satisfactory.

4 years ago

on Monday, August 16th 2021, 8:02:29 am
<span class="4">Picture Id:781</span>
PWD Uttarakahnd
Photo (ID 781) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C.H- 51.250
Remark : DBM work in progress. Work satisfactory

4 years ago

on Monday, August 16th 2021, 6:30:00 pm
56%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Wednesday, September 22nd 2021, 6:08:14 am
<span class="4">Picture Id:1535</span>
PWD Uttarakahnd
Photo (ID 1535) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C. H - 30.210
Remark : Bituminous concrete(B.C) work in progress. Work is satisfactory.

4 years ago

on Wednesday, September 22nd 2021, 6:19:16 am
<span class="4">Picture Id:1539</span>
PWD Uttarakahnd
Photo (ID 1539) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C. H 32.650
Remark : R/w is complete. Work is satisfactory

4 years ago

on Friday, October 15th 2021, 5:10:29 am
<span class="4">Picture Id:2615</span>
PWD Uttarakahnd
Photo (ID 2615) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C. H 50.150
Remark : D. B. M work in progress.

4 years ago

on Sunday, October 31st 2021, 6:30:00 pm
45.80%
Financial Progress

8th Expenditure
of ₹ 19760361 (197.60 Lacs ) done.
Cummulative ₹ 773.81Lacs ( against 1689.43Lacs )

4 years ago

on Monday, November 22nd 2021, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 3rd time

4 years ago

on Wednesday, December 15th 2021, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 4th time

4 years ago

on Thursday, December 16th 2021, 6:30:00 pm
57.41%
Financial Progress

9th Expenditure
of ₹ 19602154 (196.02 Lacs ) done.
Cummulative ₹ 969.84Lacs ( against 1689.43Lacs )

4 years ago

on Tuesday, January 4th 2022, 6:30:00 pm
83%

Physical Progress
Physical Progress Reported at 5th time

3 years ago

on Thursday, May 12th 2022, 6:30:00 pm
65.49%
Financial Progress

10th Expenditure
of ₹ 13649558 (136.50 Lacs ) done.
Cummulative ₹ 1106.33Lacs ( against 1689.43Lacs )

3 years ago

on Tuesday, May 24th 2022, 6:30:00 pm
66.62%
Financial Progress

11th Expenditure
of ₹ 1916569 (19.17 Lacs ) done.
Cummulative ₹ 1125.50Lacs ( against 1689.43Lacs )

3 years ago

on Saturday, January 7th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable