on Monday, January 6th 2020, 6:30:00 pm
Work Sanctioned
राष्ट्रीय राजमार्ग 119 (नया नाम 534) के कि०मी० 28.00 से कि०मी० 34.00 तक एवं कि०मी० 44.00 से कि०मी० 58.00 तक में सुदृढीकरण तथा कि०मी० 23 .00 से कि०मी० 78.00 तक में सुरक्षात्मक कार्य।
on Tuesday, January 7th 2020, 7:14:30 am
Technical Sanction
of ₹ 1689.43 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. F.No. RO/UK/12014/111/Annual Plan /2019-20
on Monday, December 28th 2020, 6:30:00 pm
10.76%
Financial Progress
1st Expenditure
of ₹ 18173178 (181.73 Lacs ) done.
Cummulative ₹ 181.73Lacs ( against 1689.43Lacs )
on Friday, March 26th 2021, 6:30:00 pm
18.75%
Financial Progress
2nd Expenditure
of ₹ 13509944 (135.10 Lacs ) done.
Cummulative ₹ 316.83Lacs ( against 1689.43Lacs )
on Sunday, May 23rd 2021, 6:30:00 pm
171.61%
Financial Progress
3rd Expenditure
of ₹ 258232318 (2582.32 Lacs ) done.
Cummulative ₹ 2899.15Lacs ( against 1689.43Lacs )
on Sunday, May 23rd 2021, 6:30:00 pm
34.03%
Financial Progress
4th Expenditure
of ₹ -232430003 (-2324.30 Lacs ) done.
Cummulative ₹ 574.85Lacs ( against 1689.43Lacs )
on Thursday, June 17th 2021, 6:30:00 pm
34.05%
Financial Progress
5th Expenditure
of ₹ 42480 (0.42 Lacs ) done.
Cummulative ₹ 575.28Lacs ( against 1689.43Lacs )
on Thursday, June 17th 2021, 6:30:00 pm
34.08%
Financial Progress
6th Expenditure
of ₹ 46610 (0.47 Lacs ) done.
Cummulative ₹ 575.75Lacs ( against 1689.43Lacs )
on Thursday, June 17th 2021, 6:30:00 pm
34.11%
Financial Progress
7th Expenditure
of ₹ 46610 (0.47 Lacs ) done.
Cummulative ₹ 576.21Lacs ( against 1689.43Lacs )
on Monday, July 26th 2021, 6:30:00 pm
47%
Physical Progress
Physical Progress Reported at 1st time
on Monday, August 16th 2021, 7:06:49 am
PWD UttarakahndPhoto (ID 753) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C.H -31.860
Remark : R/wall in wire crate. Work satisfactory.
on Monday, August 16th 2021, 8:02:29 am
PWD UttarakahndPhoto (ID 781) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C.H- 51.250
Remark : DBM work in progress. Work satisfactory
on Monday, August 16th 2021, 6:30:00 pm
56%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, September 22nd 2021, 6:08:14 am
PWD UttarakahndPhoto (ID 1535) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C. H - 30.210
Remark : Bituminous concrete(B.C) work in progress. Work is satisfactory.
on Wednesday, September 22nd 2021, 6:19:16 am
PWD UttarakahndPhoto (ID 1539) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C. H 32.650
Remark : R/w is complete. Work is satisfactory
on Friday, October 15th 2021, 5:10:29 am
PWD UttarakahndPhoto (ID 2615) from Site Received
Uploader : Ashish Sani, Junior Engineer Civil ,NH Div Dhumakot
Landmark : C. H 50.150
Remark : D. B. M work in progress.
on Sunday, October 31st 2021, 6:30:00 pm
45.80%
Financial Progress
8th Expenditure
of ₹ 19760361 (197.60 Lacs ) done.
Cummulative ₹ 773.81Lacs ( against 1689.43Lacs )
on Monday, November 22nd 2021, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, December 15th 2021, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, December 16th 2021, 6:30:00 pm
57.41%
Financial Progress
9th Expenditure
of ₹ 19602154 (196.02 Lacs ) done.
Cummulative ₹ 969.84Lacs ( against 1689.43Lacs )
on Tuesday, January 4th 2022, 6:30:00 pm
83%
Physical Progress
Physical Progress Reported at 5th time
on Thursday, May 12th 2022, 6:30:00 pm
65.49%
Financial Progress
10th Expenditure
of ₹ 13649558 (136.50 Lacs ) done.
Cummulative ₹ 1106.33Lacs ( against 1689.43Lacs )
on Tuesday, May 24th 2022, 6:30:00 pm
66.62%
Financial Progress
11th Expenditure
of ₹ 1916569 (19.17 Lacs ) done.
Cummulative ₹ 1125.50Lacs ( against 1689.43Lacs )
on Saturday, January 7th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 6th time