4 years ago

on Monday, December 13th 2021, 6:30:00 pm
Work Sanctioned
पौड़ी-टंगरोली मोटर मार्ग के ग्राम बंगरगांव से ग्राम पाली तक मोटर मार्ग का नवनिर्माण कार्य एवं 24 मी0 स्पान स्टील गर्डर पुल का निर्माण कार्य। (द्वितीय चरण स्टेज-।)

4 years ago

on Thursday, December 16th 2021, 8:10:17 am

Technical Sanction
of ₹ 36.61 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS no- 32

4 years ago

on Sunday, February 27th 2022, 6:30:00 pm
0.18%
Financial Progress

1st Expenditure
of ₹ 6490 (0.06 Lacs ) done.
Cummulative ₹ 0.06Lacs ( against 36.61Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
10.13%
Financial Progress

2nd Expenditure
of ₹ 364476 (3.64 Lacs ) done.
Cummulative ₹ 3.71Lacs ( against 36.61Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
37.12%
Financial Progress

3rd Expenditure
of ₹ 988152 (9.88 Lacs ) done.
Cummulative ₹ 13.59Lacs ( against 36.61Lacs )

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
41.80%
Financial Progress

4th Expenditure
of ₹ 171091 (1.71 Lacs ) done.
Cummulative ₹ 15.30Lacs ( against 36.61Lacs )

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
45.33%
Financial Progress

5th Expenditure
of ₹ 129172 (1.29 Lacs ) done.
Cummulative ₹ 16.59Lacs ( against 36.61Lacs )

2 years ago

on Sunday, April 16th 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
64.32%
Financial Progress

6th Expenditure
of ₹ 695212 (6.95 Lacs ) done.
Cummulative ₹ 23.55Lacs ( against 36.61Lacs )

a year ago

on Thursday, April 11th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
64.32%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 23.55Lacs ( against 36.61Lacs )

a year ago

on Sunday, May 26th 2024, 6:30:00 pm
86.54%
Financial Progress

8th Expenditure
of ₹ 813597 (8.14 Lacs ) done.
Cummulative ₹ 31.68Lacs ( against 36.61Lacs )

3 months ago

on Sunday, June 29th 2025, 6:30:00 pm
89.21%
Financial Progress

9th Expenditure
of ₹ 97615 (0.98 Lacs ) done.
Cummulative ₹ 32.66Lacs ( against 36.61Lacs )

2 months ago

on Sunday, July 27th 2025, 6:30:00 pm
93.41%
Financial Progress

10th Expenditure
of ₹ 154015 (1.54 Lacs ) done.
Cummulative ₹ 34.20Lacs ( against 36.61Lacs )