Refresh data
Refresh data

3 years ago

on Sunday, October 3rd 2021, 6:30:00 pm
Work Sanctioned
केन्द्रीय सड़क अवसंरचना निधि के अन्तर्गत पौड़ी-देवप्रयाग-गजा-जाजल मोटर मार्ग के कि0मी0 1 से 49 में आर0एस0ए0 की संस्तुति के आधार पर सड़क सुरक्षा का कार्य। (राज्य मार्ग संख्या-31)

3 years ago

on Wednesday, December 15th 2021, 8:14:56 am

Technical Sanction
of ₹ 650 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6132/12(7)yata/CRIF-pauri/2021

3 years ago

on Tuesday, February 15th 2022, 1:17:48 am
<span class="4">Picture Id:4331</span>
PWD Uttarakahnd
Photo (ID 4331) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 38
Remark : Inspection by SE Sir..Cutting work in progress

3 years ago

on Sunday, February 20th 2022, 1:05:19 am
<span class="4">Picture Id:4423</span>
PWD Uttarakahnd
Photo (ID 4423) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 31
Remark : Cutting work in progress

3 years ago

on Sunday, February 20th 2022, 1:59:36 am
<span class="4">Picture Id:4429</span>
PWD Uttarakahnd
Photo (ID 4429) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 37
Remark : Cutting completed in section

3 years ago

on Sunday, February 20th 2022, 2:17:53 am
<span class="4">Picture Id:4431</span>
PWD Uttarakahnd
Photo (ID 4431) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 39
Remark : Debri removal in progress

3 years ago

on Sunday, February 20th 2022, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Tuesday, February 22nd 2022, 12:11:45 am
<span class="4">Picture Id:4468</span>
PWD Uttarakahnd
Photo (ID 4468) from Site Received
Uploader : Harish Gairola, Additional Assistant Engineer Civil ,CD Narendnagar
Landmark : Km-32(4-6)
Remark : Hill side cutting on curves SH-31

3 years ago

on Sunday, March 6th 2022, 9:38:48 pm
<span class="4">Picture Id:4735</span>
PWD Uttarakahnd
Photo (ID 4735) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 18
Remark : Hill side cutting in progress and removal of debris.

3 years ago

on Sunday, March 6th 2022, 9:49:47 pm
<span class="4">Picture Id:4736</span>
PWD Uttarakahnd
Photo (ID 4736) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 17
Remark : Hill side cutting in progress

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
42.32%
Financial Progress

1st Expenditure
of ₹ 27505733 (275.06 Lacs ) done.
Cummulative ₹ 275.06Lacs ( against 650Lacs )

3 years ago

on Thursday, April 7th 2022, 4:14:43 am
<span class="4">Picture Id:5209</span>
PWD Uttarakahnd
Photo (ID 5209) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 25
Remark : Installation of crash barrier in progress

3 years ago

on Monday, May 2nd 2022, 12:45:00 am
<span class="4">Picture Id:5484</span>
PWD Uttarakahnd
Photo (ID 5484) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 1
Remark : White line marking started from km1

3 years ago

on Friday, May 13th 2022, 1:47:52 am
<span class="4">Picture Id:5560</span>
PWD Uttarakahnd
Photo (ID 5560) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 3
Remark : Thermoplastic edge marking completed in km 3

3 years ago

on Sunday, May 22nd 2022, 8:11:56 am
<span class="4">Picture Id:5617</span>
PWD Uttarakahnd
Photo (ID 5617) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 19
Remark : Inspection on Pauri Devprayag SH 31 by Chief Engineer Sir and SE sir

3 years ago

on Thursday, June 30th 2022, 6:30:00 pm
51.54%
Financial Progress

2nd Expenditure
of ₹ 5997800 (59.98 Lacs ) done.
Cummulative ₹ 335.04Lacs ( against 650Lacs )

3 years ago

on Tuesday, August 30th 2022, 6:30:00 pm
67.88%
Financial Progress

3rd Expenditure
of ₹ 10616598 (106.17 Lacs ) done.
Cummulative ₹ 441.20Lacs ( against 650Lacs )

2 years ago

on Thursday, September 29th 2022, 6:30:00 pm
67.98%
Financial Progress

4th Expenditure
of ₹ 68813 (0.69 Lacs ) done.
Cummulative ₹ 441.89Lacs ( against 650Lacs )

2 years ago

on Sunday, October 30th 2022, 6:30:00 pm
75.62%
Financial Progress

5th Expenditure
of ₹ 4966131 (49.66 Lacs ) done.
Cummulative ₹ 491.55Lacs ( against 650Lacs )

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
75.71%
Financial Progress

6th Expenditure
of ₹ 57112 (0.57 Lacs ) done.
Cummulative ₹ 492.12Lacs ( against 650Lacs )

2 years ago

on Monday, February 27th 2023, 6:30:00 pm
82.55%
Financial Progress

7th Expenditure
of ₹ 4444920 (44.45 Lacs ) done.
Cummulative ₹ 536.57Lacs ( against 650Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
83.28%
Financial Progress

8th Expenditure
of ₹ 476526 (4.77 Lacs ) done.
Cummulative ₹ 541.34Lacs ( against 650Lacs )

2 years ago

on Thursday, April 6th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
83.34%
Financial Progress

9th Expenditure
of ₹ 36744 (0.37 Lacs ) done.
Cummulative ₹ 541.70Lacs ( against 650Lacs )

2 years ago

on Wednesday, July 26th 2023, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Wednesday, July 26th 2023, 6:30:00 pm
89.99%
Financial Progress

10th Expenditure
of ₹ 4325817 (43.26 Lacs ) done.
Cummulative ₹ 584.96Lacs ( against 650Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
90.00%
Financial Progress

11th Expenditure
of ₹ 2832 (0.03 Lacs ) done.
Cummulative ₹ 584.99Lacs ( against 650Lacs )

a year ago

on Friday, September 29th 2023, 6:30:00 pm
94.84%
Financial Progress

12th Expenditure
of ₹ 3146194 (31.46 Lacs ) done.
Cummulative ₹ 616.45Lacs ( against 650Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
99.47%
Financial Progress

13th Expenditure
of ₹ 3012779 (30.13 Lacs ) done.
Cummulative ₹ 646.58Lacs ( against 650Lacs )

a year ago

on Saturday, April 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable