Work Sanctioned
बड़खोलू रौतेला काण्डा मोटर मार्ग के कि0मी0 6 से कुड़िगांव-हैडाखोली मोटर मार्ग का नवनिर्माण कार्य। (द्वितीय चरण स्टेज-। )

3 years ago

on Monday, August 29th 2022, 7:13:20 am
<span class="4">Picture Id:7558</span>
PWD Uttarakahnd
Photo (ID 7558) from Site Received
Uploader : Dinesh Chandra Nautiyal, Executive Engineer Civil ,TD Ghansali
Landmark : Pauri Bus stand parking slab Reinforcement
Remark : Slab Reinforcement

2 years ago

on Monday, January 30th 2023, 6:30:00 pm
0.54%
Financial Progress

1st Expenditure
of ₹ 58310 (0.58 Lacs ) done.
Cummulative ₹ 0.58Lacs ( against 107.09Lacs )

2 years ago

on Monday, February 27th 2023, 6:30:00 pm
22.06%
Financial Progress

2nd Expenditure
of ₹ 2304135 (23.04 Lacs ) done.
Cummulative ₹ 23.62Lacs ( against 107.09Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
48.89%
Financial Progress

3rd Expenditure
of ₹ 2873124 (28.73 Lacs ) done.
Cummulative ₹ 52.36Lacs ( against 107.09Lacs )

2 years ago

on Sunday, April 16th 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Wednesday, May 31st 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
57.10%
Financial Progress

4th Expenditure
of ₹ 879071 (8.79 Lacs ) done.
Cummulative ₹ 61.15Lacs ( against 107.09Lacs )

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
58.17%
Financial Progress

5th Expenditure
of ₹ 114951 (1.15 Lacs ) done.
Cummulative ₹ 62.30Lacs ( against 107.09Lacs )

a year ago

on Saturday, December 30th 2023, 6:30:00 pm
76.57%
Financial Progress

6th Expenditure
of ₹ 1970234 (19.70 Lacs ) done.
Cummulative ₹ 82.00Lacs ( against 107.09Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
87.16%
Financial Progress

7th Expenditure
of ₹ 1133914 (11.34 Lacs ) done.
Cummulative ₹ 93.34Lacs ( against 107.09Lacs )

a year ago

on Thursday, April 11th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

8 months ago

on Thursday, September 12th 2024, 6:30:00 pm
90.61%
Financial Progress

8th Expenditure
of ₹ 369890 (3.70 Lacs ) done.
Cummulative ₹ 97.04Lacs ( against 107.09Lacs )

8 months ago

on Monday, September 30th 2024, 6:30:00 pm
91.53%
Financial Progress

9th Expenditure
of ₹ 98827 (0.99 Lacs ) done.
Cummulative ₹ 98.02Lacs ( against 107.09Lacs )

5 months ago

on Thursday, December 19th 2024, 6:30:00 pm
91.67%
Financial Progress

11th Expenditure
of ₹ 7880 (0.08 Lacs ) done.
Cummulative ₹ 98.16Lacs ( against 107.09Lacs )

5 months ago

on Thursday, December 19th 2024, 6:30:00 pm
91.59%
Financial Progress

10th Expenditure
of ₹ 6150 (0.06 Lacs ) done.
Cummulative ₹ 98.09Lacs ( against 107.09Lacs )

2 months ago

on Monday, March 17th 2025, 6:30:00 pm
92.67%
Financial Progress

12th Expenditure
of ₹ 107380 (1.07 Lacs ) done.
Cummulative ₹ 99.24Lacs ( against 107.09Lacs )