2 years ago

on Thursday, July 20th 2023, 6:30:00 pm
Work Sanctioned
टिहरी-हिण्डोलाखाल-देवप्रयाग-व्यासघाट-बिलखेत (एस0एच0-49) ल0 31.50 कि0मी0 । अदवानी-नाहसैण-सुरपुर-बहेडाखाल-खाण्डा मोटर मार्ग ल0 36.50 कि0मी0 । (अन्य जिला मार्ग)

2 years ago

on Friday, October 20th 2023, 11:31:09 am

Technical Sanction
of ₹ 570.28 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6929/12(203)yata (pd pauri)-pauri/2023

2 years ago

on Tuesday, December 26th 2023, 5:43:13 am
<span class="4">Picture Id:33579</span>
PWD Uttarakahnd
Photo (ID 33579) from Site Received
Uploader : Mahendra Singh Dawan, Additional Assistant Engineer Civil ,PD Pauri
Landmark : टिहरी हिंडोलाखाल देवप्रयाग व्यासघाट बिलखेत SH-49 पर रोड सुरक्षात्मक कार्य प्रगति पर किलोमीटर 61 से 91
Remark : टिहरी हिंडोलाखाल व्यासघाट बिलखेत SH-49 पर रोड सुरक्षात्मक कार्य प्रगति पर

2 years ago

on Friday, December 29th 2023, 11:35:18 am
<span class="4">Picture Id:33897</span>
PWD Uttarakahnd
Photo (ID 33897) from Site Received
Uploader : Martunjay Sharma, Assistant Engineer Civil ,PD Pauri
Landmark : 60.350
Remark : Work in progress

2 years ago

on Monday, January 1st 2024, 5:16:47 am
<span class="4">Picture Id:34132</span>
PWD Uttarakahnd
Photo (ID 34132) from Site Received
Uploader : Martunjay Sharma, Assistant Engineer Civil ,PD Pauri
Landmark : 60.625
Remark : Work is continuous

2 years ago

on Monday, January 1st 2024, 5:19:30 am
<span class="4">Picture Id:34133</span>
PWD Uttarakahnd
Photo (ID 34133) from Site Received
Uploader : Martunjay Sharma, Assistant Engineer Civil ,PD Pauri
Landmark : 60.825
Remark : Work is contious

2 years ago

on Monday, January 1st 2024, 5:23:18 am
<span class="4">Picture Id:34134</span>
PWD Uttarakahnd
Photo (ID 34134) from Site Received
Uploader : Martunjay Sharma, Assistant Engineer Civil ,PD Pauri
Landmark : 61.10
Remark : Work is continous

2 years ago

on Monday, January 1st 2024, 5:30:35 am
<span class="4">Picture Id:34136</span>
PWD Uttarakahnd
Photo (ID 34136) from Site Received
Uploader : Martunjay Sharma, Assistant Engineer Civil ,PD Pauri
Landmark : 61.150
Remark : Most danger place

2 years ago

on Tuesday, January 9th 2024, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, January 11th 2024, 6:30:00 pm
19.58%
Financial Progress

1st Expenditure
of ₹ 11167520 (111.68 Lacs ) done.
Cummulative ₹ 111.68Lacs ( against 570.28Lacs )

2 years ago

on Tuesday, February 6th 2024, 5:21:15 am
<span class="4">Picture Id:35605</span>
PWD Uttarakahnd
Photo (ID 35605) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 8
Remark : Work in progress under road safety on adwani nahsen baherakhal m/r

2 years ago

on Tuesday, February 6th 2024, 5:43:25 am
<span class="4">Picture Id:35610</span>
PWD Uttarakahnd
Photo (ID 35610) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 10
Remark : Installation of crash barrier on adwani nahsen motor road

2 years ago

on Thursday, February 8th 2024, 6:30:00 pm
41.15%
Financial Progress

2nd Expenditure
of ₹ 12299140 (122.99 Lacs ) done.
Cummulative ₹ 234.67Lacs ( against 570.28Lacs )

2 years ago

on Wednesday, February 21st 2024, 6:30:00 pm
41.27%
Financial Progress

4th Expenditure
of ₹ 33837 (0.34 Lacs ) done.
Cummulative ₹ 235.34Lacs ( against 570.28Lacs )

2 years ago

on Wednesday, February 21st 2024, 6:30:00 pm
41.38%
Financial Progress

5th Expenditure
of ₹ 66680 (0.67 Lacs ) done.
Cummulative ₹ 236.01Lacs ( against 570.28Lacs )

2 years ago

on Wednesday, February 21st 2024, 6:30:00 pm
41.21%
Financial Progress

3rd Expenditure
of ₹ 33670 (0.34 Lacs ) done.
Cummulative ₹ 235.00Lacs ( against 570.28Lacs )

2 years ago

on Friday, February 23rd 2024, 4:52:09 am
<span class="4">Picture Id:41386</span>
PWD Uttarakahnd
Photo (ID 41386) from Site Received
Uploader : Madhavi Kanojiya, Assistant Engineer Civil ,PD Pauri
Landmark : Km 6
Remark : Road safety work in progress in adwani nahsen motor road

2 years ago

on Sunday, February 25th 2024, 6:30:00 pm
49.97%
Financial Progress

6th Expenditure
of ₹ 4897000 (48.97 Lacs ) done.
Cummulative ₹ 284.98Lacs ( against 570.28Lacs )

2 years ago

on Sunday, March 3rd 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Monday, March 11th 2024, 6:30:00 pm
67.51%
Financial Progress

7th Expenditure
of ₹ 10000000 (100.00 Lacs ) done.
Cummulative ₹ 384.98Lacs ( against 570.28Lacs )

2 years ago

on Saturday, April 6th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Friday, May 17th 2024, 6:30:00 pm
79.86%
Financial Progress

8th Expenditure
of ₹ 7047153 (70.47 Lacs ) done.
Cummulative ₹ 455.45Lacs ( against 570.28Lacs )

a year ago

on Friday, May 17th 2024, 6:30:00 pm
88.36%
Financial Progress

9th Expenditure
of ₹ 4843074 (48.43 Lacs ) done.
Cummulative ₹ 503.88Lacs ( against 570.28Lacs )

a year ago

on Thursday, June 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Thursday, December 26th 2024, 6:30:00 pm
98.98%
Financial Progress

10th Expenditure
of ₹ 6060480 (60.60 Lacs ) done.
Cummulative ₹ 564.49Lacs ( against 570.28Lacs )

8 months ago

on Sunday, March 30th 2025, 6:30:00 pm
99.04%
Financial Progress

11th Expenditure
of ₹ 33000 (0.33 Lacs ) done.
Cummulative ₹ 564.82Lacs ( against 570.28Lacs )

4 months ago

on Tuesday, July 22nd 2025, 6:30:00 pm
99.48%
Financial Progress

12th Expenditure
of ₹ 247800 (2.48 Lacs ) done.
Cummulative ₹ 567.29Lacs ( against 570.28Lacs )

a month ago

on Wednesday, October 15th 2025, 6:30:00 pm
100.35%
Financial Progress

16th Expenditure
of ₹ 121303 (1.21 Lacs ) done.
Cummulative ₹ 572.26Lacs ( against 570.28Lacs )

a month ago

on Wednesday, October 15th 2025, 6:30:00 pm
100.13%
Financial Progress

15th Expenditure
of ₹ 121303 (1.21 Lacs ) done.
Cummulative ₹ 571.04Lacs ( against 570.28Lacs )

a month ago

on Wednesday, October 15th 2025, 6:30:00 pm
99.92%
Financial Progress

14th Expenditure
of ₹ 126851 (1.27 Lacs ) done.
Cummulative ₹ 569.83Lacs ( against 570.28Lacs )

a month ago

on Wednesday, October 15th 2025, 6:30:00 pm
99.70%
Financial Progress

13th Expenditure
of ₹ 126851 (1.27 Lacs ) done.
Cummulative ₹ 568.56Lacs ( against 570.28Lacs )

15 days ago

on Thursday, October 30th 2025, 6:30:00 pm
100.35%
Financial Progress

17th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 572.26Lacs ( against 570.28Lacs )

AI layer

AI Road
AI Bridge
10000 km