4 years ago

on Friday, December 10th 2021, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा से0 324/2015 के अन्तर्गत जनपद पौॅडी गढवाल के विधानसभा क्षेत्र चैबट्टाखाल के अन्तर्गत विकासखण्ड पोखडा में कुण्जखाल - बरसुण्ड मोटर मार्ग का निर्माण कार्य। (द्वितीय चरण स्टेज-।)

4 years ago

on Sunday, February 27th 2022, 6:30:00 pm
1.02%
Financial Progress

1st Expenditure
of ₹ 112452 (1.12 Lacs ) done.
Cummulative ₹ 1.12Lacs ( against 109.76Lacs )

3 years ago

on Tuesday, January 10th 2023, 6:30:00 pm
3.54%
Financial Progress

2nd Expenditure
of ₹ 275601 (2.76 Lacs ) done.
Cummulative ₹ 3.88Lacs ( against 109.76Lacs )

3 years ago

on Thursday, January 19th 2023, 10:32:43 am

Technical Sanction
of ₹ 109.76 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6425/1108 yata-12 / 2022-23

3 years ago

on Sunday, February 12th 2023, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Monday, March 13th 2023, 6:30:00 pm
3.75%
Financial Progress

3rd Expenditure
of ₹ 23500 (0.23 Lacs ) done.
Cummulative ₹ 4.12Lacs ( against 109.76Lacs )

2 years ago

on Tuesday, October 10th 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Thursday, November 2nd 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Monday, November 13th 2023, 6:30:00 pm
19.53%
Financial Progress

4th Expenditure
of ₹ 1731789 (17.32 Lacs ) done.
Cummulative ₹ 21.43Lacs ( against 109.76Lacs )

2 years ago

on Wednesday, November 15th 2023, 6:30:00 pm
26.29%
Financial Progress

5th Expenditure
of ₹ 742292 (7.42 Lacs ) done.
Cummulative ₹ 28.86Lacs ( against 109.76Lacs )

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Friday, December 15th 2023, 6:30:00 pm
40.72%
Financial Progress

6th Expenditure
of ₹ 1583721 (15.84 Lacs ) done.
Cummulative ₹ 44.69Lacs ( against 109.76Lacs )

2 years ago

on Thursday, December 21st 2023, 6:30:00 pm
61.80%
Financial Progress

7th Expenditure
of ₹ 2313298 (23.13 Lacs ) done.
Cummulative ₹ 67.83Lacs ( against 109.76Lacs )

2 years ago

on Wednesday, January 31st 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 5th time

2 years ago

on Thursday, February 1st 2024, 6:30:00 pm
74.45%
Financial Progress

8th Expenditure
of ₹ 1389266 (13.89 Lacs ) done.
Cummulative ₹ 81.72Lacs ( against 109.76Lacs )

2 years ago

on Tuesday, February 13th 2024, 6:30:00 pm
75.34%
Financial Progress

9th Expenditure
of ₹ 97492 (0.97 Lacs ) done.
Cummulative ₹ 82.69Lacs ( against 109.76Lacs )

2 years ago

on Tuesday, February 20th 2024, 6:30:00 pm
75.34%
Financial Progress

10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 82.69Lacs ( against 109.76Lacs )

a year ago

on Sunday, March 24th 2024, 6:30:00 pm
84.79%
Financial Progress

11th Expenditure
of ₹ 1036630 (10.37 Lacs ) done.
Cummulative ₹ 93.06Lacs ( against 109.76Lacs )

a year ago

on Monday, June 24th 2024, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 6th time

a year ago

on Monday, August 5th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 7th time

a year ago

on Thursday, September 26th 2024, 6:30:00 pm
85.00%
Financial Progress

12th Expenditure
of ₹ 23250 (0.23 Lacs ) done.
Cummulative ₹ 93.29Lacs ( against 109.76Lacs )

10 months ago

on Thursday, November 21st 2024, 6:30:00 pm
86.30%
Financial Progress

13th Expenditure
of ₹ 142943 (1.43 Lacs ) done.
Cummulative ₹ 94.72Lacs ( against 109.76Lacs )

10 months ago

on Thursday, November 21st 2024, 6:30:00 pm
86.55%
Financial Progress

14th Expenditure
of ₹ 28000 (0.28 Lacs ) done.
Cummulative ₹ 95.00Lacs ( against 109.76Lacs )

7 months ago

on Wednesday, February 19th 2025, 6:30:00 pm
78.20%
Financial Progress

15th Expenditure
of ₹ -917000 (-9.17 Lacs ) done.
Cummulative ₹ 85.83Lacs ( against 109.76Lacs )

6 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
82.73%
Financial Progress

16th Expenditure
of ₹ 496929 (4.97 Lacs ) done.
Cummulative ₹ 90.80Lacs ( against 109.76Lacs )

6 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
86.34%
Financial Progress

17th Expenditure
of ₹ 396511 (3.97 Lacs ) done.
Cummulative ₹ 94.77Lacs ( against 109.76Lacs )

3 months ago

on Wednesday, June 11th 2025, 6:30:00 pm
86.51%
Financial Progress

18th Expenditure
of ₹ 19000 (0.19 Lacs ) done.
Cummulative ₹ 94.96Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
97.84%
Financial Progress

25th Expenditure
of ₹ 177787 (1.78 Lacs ) done.
Cummulative ₹ 107.39Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
88.81%
Financial Progress

19th Expenditure
of ₹ 251620 (2.52 Lacs ) done.
Cummulative ₹ 97.47Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
90.41%
Financial Progress

20th Expenditure
of ₹ 175637 (1.76 Lacs ) done.
Cummulative ₹ 99.23Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
91.62%
Financial Progress

21st Expenditure
of ₹ 133505 (1.34 Lacs ) done.
Cummulative ₹ 100.56Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
92.93%
Financial Progress

22nd Expenditure
of ₹ 143310 (1.43 Lacs ) done.
Cummulative ₹ 102.00Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
94.67%
Financial Progress

23rd Expenditure
of ₹ 191565 (1.92 Lacs ) done.
Cummulative ₹ 103.91Lacs ( against 109.76Lacs )

24 days ago

on Friday, August 29th 2025, 6:30:00 pm
96.22%
Financial Progress

24th Expenditure
of ₹ 169806 (1.70 Lacs ) done.
Cummulative ₹ 105.61Lacs ( against 109.76Lacs )

22 days ago

on Sunday, August 31st 2025, 6:30:00 pm
98.95%
Financial Progress

26th Expenditure
of ₹ 122259 (1.22 Lacs ) done.
Cummulative ₹ 108.61Lacs ( against 109.76Lacs )