Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड खिर्सू के अन्तर्गत मुसोली-तैलाधार-जखोटखाल मोटर मार्ग का मुसोली गांव तक डामरीकरण का कार्य। (द्वितीय चरण)
on Monday, August 19th 2024, 6:30:00 pm
5.58%
Financial Progress
1st Expenditure
of ₹ 48746 (0.49 Lacs ) done.
Cummulative ₹ 0.49Lacs ( against 8.73Lacs )
on Tuesday, August 20th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, September 19th 2024, 6:30:00 pm
20.59%
Financial Progress
2nd Expenditure
of ₹ 131000 (1.31 Lacs ) done.
Cummulative ₹ 1.80Lacs ( against 8.73Lacs )
on Monday, February 10th 2025, 6:30:00 pm
34.44%
Financial Progress
3rd Expenditure
of ₹ 120898 (1.21 Lacs ) done.
Cummulative ₹ 3.01Lacs ( against 8.73Lacs )
on Wednesday, February 19th 2025, 6:30:00 pm
34.44%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 3.01Lacs ( against 8.73Lacs )
on Monday, March 17th 2025, 6:30:00 pm
46.55%
Financial Progress
5th Expenditure
of ₹ 105765 (1.06 Lacs ) done.
Cummulative ₹ 4.06Lacs ( against 8.73Lacs )
on Monday, May 12th 2025, 6:30:00 pm
67.16%
Financial Progress
6th Expenditure
of ₹ 179884 (1.80 Lacs ) done.
Cummulative ₹ 5.86Lacs ( against 8.73Lacs )