@
Refresh data
Refresh data

17 years ago

on Thursday, July 24th 2008, 6:30:00 pm
Work Sanctioned
बागेश्वर में हरसीला-पुडकुनी मोटर मार्ग से चचई तक मोटर मार्ग निर्माण सेतु सहित।

12 years ago

on Friday, February 28th 2014, 6:30:00 pm
0.01%
Financial Progress

1st Expenditure
of ₹ 6000 (0.06 Lacs ) done.
Cummulative ₹ 0.06Lacs ( against 455.75Lacs )

8 years ago

on Wednesday, May 31st 2017, 6:30:00 pm
0.17%
Financial Progress

2nd Expenditure
of ₹ 69694 (0.70 Lacs ) done.
Cummulative ₹ 0.76Lacs ( against 455.75Lacs )

7 years ago

on Sunday, June 17th 2018, 6:30:00 pm

Technical Sanction
of ₹ 268.77 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1737/507Yata-A/2018

7 years ago

on Tuesday, July 31st 2018, 6:30:00 pm
1.68%
Financial Progress

3rd Expenditure
of ₹ 688306 (6.88 Lacs ) done.
Cummulative ₹ 7.64Lacs ( against 455.75Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
4.82%
Financial Progress

4th Expenditure
of ₹ 1432919 (14.33 Lacs ) done.
Cummulative ₹ 21.97Lacs ( against 455.75Lacs )

6 years ago

on Wednesday, July 31st 2019, 6:30:00 pm
10.22%
Financial Progress

5th Expenditure
of ₹ 2462850 (24.63 Lacs ) done.
Cummulative ₹ 46.60Lacs ( against 455.75Lacs )

4 years ago

on Monday, July 5th 2021, 6:30:00 pm
26%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Friday, July 30th 2021, 6:30:00 pm
10.49%
Financial Progress

6th Expenditure
of ₹ 122321 (1.22 Lacs ) done.
Cummulative ₹ 47.82Lacs ( against 455.75Lacs )

4 years ago

on Sunday, January 30th 2022, 6:30:00 pm
30.48%
Financial Progress

7th Expenditure
of ₹ 9108317 (91.08 Lacs ) done.
Cummulative ₹ 138.90Lacs ( against 455.75Lacs )

4 years ago

on Tuesday, March 1st 2022, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Wednesday, March 30th 2022, 6:24:00 am
<span class="4">Picture Id:5084</span>
PWD Uttarakahnd
Photo (ID 5084) from Site Received
Uploader : Sanjay Kumar Pandey, Executive Engineer Civil ,PD Bageshwar
Landmark : Km 1 h p bend
Remark : Chaichai road

3 years ago

on Wednesday, April 6th 2022, 5:39:41 pm
<span class="4">Picture Id:5225</span>
PWD Uttarakahnd
Photo (ID 5225) from Site Received
Uploader : Harish Chandra Joshi, Assistant Engineer Civil ,CD Almora
Landmark : . 1
Remark : Hill side cutting

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
42.51%
Financial Progress

8th Expenditure
of ₹ 5484258 (54.84 Lacs ) done.
Cummulative ₹ 193.75Lacs ( against 455.75Lacs )

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
42.95%
Financial Progress

9th Expenditure
of ₹ 199918 (2.00 Lacs ) done.
Cummulative ₹ 195.75Lacs ( against 455.75Lacs )

3 years ago

on Wednesday, September 28th 2022, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 3rd time

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
44.66%
Financial Progress

10th Expenditure
of ₹ 781376 (7.81 Lacs ) done.
Cummulative ₹ 203.56Lacs ( against 455.75Lacs )

3 years ago

on Friday, January 27th 2023, 4:41:52 am

Technical Sanction
of ₹ 449.59 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 245/YATA-A/2022 Dt 27-01-2023

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
47.00%
Financial Progress

11th Expenditure
of ₹ 1066518 (10.67 Lacs ) done.
Cummulative ₹ 214.22Lacs ( against 455.75Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
47.54%
Financial Progress

12th Expenditure
of ₹ 244557 (2.45 Lacs ) done.
Cummulative ₹ 216.67Lacs ( against 455.75Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
50.58%
Financial Progress

13th Expenditure
of ₹ 1383497 (13.83 Lacs ) done.
Cummulative ₹ 230.51Lacs ( against 455.75Lacs )

2 years ago

on Monday, July 3rd 2023, 6:30:00 pm
55.53%
Financial Progress

14th Expenditure
of ₹ 2256831 (22.57 Lacs ) done.
Cummulative ₹ 253.07Lacs ( against 455.75Lacs )

2 years ago

on Sunday, July 30th 2023, 6:30:00 pm
55.70%
Financial Progress

15th Expenditure
of ₹ 77202 (0.77 Lacs ) done.
Cummulative ₹ 253.85Lacs ( against 455.75Lacs )

2 years ago

on Tuesday, August 8th 2023, 10:34:52 am
<span class="4">Picture Id:23396</span>
PWD Uttarakahnd
Photo (ID 23396) from Site Received
Uploader : Govind Ballabh Joshi, Assistant Engineer Civil ,CD Nainital
Landmark : 0.400
Remark : Inspection of 24 meter span moter bridge abutment by EE

2 years ago

on Tuesday, August 15th 2023, 6:30:00 pm
55.76%
Financial Progress

16th Expenditure
of ₹ 30000 (0.30 Lacs ) done.
Cummulative ₹ 254.15Lacs ( against 455.75Lacs )

2 years ago

on Tuesday, August 15th 2023, 6:30:00 pm
55.81%
Financial Progress

17th Expenditure
of ₹ 20302 (0.20 Lacs ) done.
Cummulative ₹ 254.35Lacs ( against 455.75Lacs )

2 years ago

on Tuesday, August 15th 2023, 6:30:00 pm
55.85%
Financial Progress

18th Expenditure
of ₹ 21000 (0.21 Lacs ) done.
Cummulative ₹ 254.56Lacs ( against 455.75Lacs )

2 years ago

on Wednesday, August 30th 2023, 6:30:00 pm
56.09%
Financial Progress

19th Expenditure
of ₹ 105022 (1.05 Lacs ) done.
Cummulative ₹ 255.61Lacs ( against 455.75Lacs )

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
56.21%
Financial Progress

20th Expenditure
of ₹ 55000 (0.55 Lacs ) done.
Cummulative ₹ 256.16Lacs ( against 455.75Lacs )

2 years ago

on Wednesday, November 29th 2023, 6:30:00 pm
56.25%
Financial Progress

21st Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 256.34Lacs ( against 455.75Lacs )

2 years ago

on Tuesday, February 27th 2024, 6:30:00 pm
57.16%
Financial Progress

22nd Expenditure
of ₹ 414812 (4.15 Lacs ) done.
Cummulative ₹ 260.49Lacs ( against 455.75Lacs )

2 years ago

on Wednesday, March 6th 2024, 6:30:00 pm
59.72%
Financial Progress

23rd Expenditure
of ₹ 1167560 (11.68 Lacs ) done.
Cummulative ₹ 272.16Lacs ( against 455.75Lacs )

2 years ago

on Tuesday, March 19th 2024, 6:30:00 pm
59.72%
Financial Progress

24th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 272.16Lacs ( against 455.75Lacs )

2 years ago

on Tuesday, March 19th 2024, 6:30:00 pm
65.13%
Financial Progress

25th Expenditure
of ₹ 2468577 (24.69 Lacs ) done.
Cummulative ₹ 296.85Lacs ( against 455.75Lacs )

a year ago

on Thursday, March 28th 2024, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Friday, April 19th 2024, 6:30:00 pm
74%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Friday, August 16th 2024, 6:30:00 pm
72.67%
Financial Progress

27th Expenditure
of ₹ 3433735 (34.34 Lacs ) done.
Cummulative ₹ 331.19Lacs ( against 455.75Lacs )

a year ago

on Friday, August 16th 2024, 6:30:00 pm
65.13%
Financial Progress

26th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 296.85Lacs ( against 455.75Lacs )

a year ago

on Wednesday, September 11th 2024, 6:30:00 pm
72.69%
Financial Progress

28th Expenditure
of ₹ 8496 (0.08 Lacs ) done.
Cummulative ₹ 331.27Lacs ( against 455.75Lacs )

a year ago

on Sunday, September 29th 2024, 6:30:00 pm
72.70%
Financial Progress

29th Expenditure
of ₹ 6564 (0.07 Lacs ) done.
Cummulative ₹ 331.34Lacs ( against 455.75Lacs )

a year ago

on Sunday, October 27th 2024, 6:30:00 pm
72.74%
Financial Progress

30th Expenditure
of ₹ 16922 (0.17 Lacs ) done.
Cummulative ₹ 331.51Lacs ( against 455.75Lacs )

5 months ago

on Friday, May 2nd 2025, 6:30:00 pm
72.87%
Financial Progress

31st Expenditure
of ₹ 60251 (0.60 Lacs ) done.
Cummulative ₹ 332.11Lacs ( against 455.75Lacs )

4 months ago

on Monday, May 19th 2025, 6:30:00 pm
72.89%
Financial Progress

32nd Expenditure
of ₹ 9330 (0.09 Lacs ) done.
Cummulative ₹ 332.20Lacs ( against 455.75Lacs )

3 months ago

on Thursday, July 3rd 2025, 6:30:00 pm
78.32%
Financial Progress

33rd Expenditure
of ₹ 2474276 (24.74 Lacs ) done.
Cummulative ₹ 356.94Lacs ( against 455.75Lacs )

3 months ago

on Monday, July 7th 2025, 6:30:00 pm
78.35%
Financial Progress

34th Expenditure
of ₹ 12730 (0.13 Lacs ) done.
Cummulative ₹ 357.07Lacs ( against 455.75Lacs )

3 months ago

on Monday, July 7th 2025, 6:30:00 pm
78.38%
Financial Progress

35th Expenditure
of ₹ 12319 (0.12 Lacs ) done.
Cummulative ₹ 357.19Lacs ( against 455.75Lacs )

3 months ago

on Monday, July 7th 2025, 6:30:00 pm
78.40%
Financial Progress

36th Expenditure
of ₹ 12730 (0.13 Lacs ) done.
Cummulative ₹ 357.32Lacs ( against 455.75Lacs )

3 months ago

on Monday, July 7th 2025, 6:30:00 pm
78.42%
Financial Progress

37th Expenditure
of ₹ 6000 (0.06 Lacs ) done.
Cummulative ₹ 357.38Lacs ( against 455.75Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors