4 years ago

on Sunday, July 4th 2021, 6:30:00 pm
Work Sanctioned
खर्ककानातोली के बासानी तोक हेतु 60मी0 पैदल झूलापुल के सुपर स्ट्रक्चर का निर्माण कार्यं

2 years ago

on Saturday, April 15th 2023, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Sunday, March 31st 2024, 6:30:00 pm
0%

Physical Progress
Physical Progress Reported at 2nd time

7 months ago

on Thursday, February 20th 2025, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 3rd time

6 months ago

on Sunday, March 30th 2025, 6:30:00 pm
33.82%
Financial Progress

1st Expenditure
of ₹ 2028963 (20.29 Lacs ) done.
Cummulative ₹ 20.29Lacs ( against 60Lacs )