on Wednesday, May 3rd 2023, 6:30:00 pm
Work Sanctioned
खनिज न्यास के अंतर्गत कपकोट के बागेश्वर कपकोट तेजम मो0मा0 के किमी0 18 से दोफाड मो0मा0 के किमी0 3 में सी0सी0 एवं पक्की नाली का कार्य।
on Saturday, October 7th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Monday, October 30th 2023, 6:30:00 pm
36.30%
Financial Progress
1st Expenditure
of ₹ 1286297 (12.86 Lacs ) done.
Cummulative ₹ 12.86Lacs ( against 35.44Lacs )
on Sunday, November 5th 2023, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, December 3rd 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, December 15th 2023, 7:29:32 am
PWD UttarakahndPhoto (ID 32271) from Site Received
Uploader : Gayatri Arya, Additional Assistant Engineer Civil ,CD Almora
Landmark : Dofar km 3
Remark : Cc&drain
on Friday, December 15th 2023, 7:31:39 am
PWD UttarakahndPhoto (ID 32272) from Site Received
Uploader : Gayatri Arya, Additional Assistant Engineer Civil ,CD Almora
Landmark : Km3
Remark : Cc
on Tuesday, March 26th 2024, 6:30:00 pm
75.00%
Financial Progress
2nd Expenditure
of ₹ 1371703 (13.72 Lacs ) done.
Cummulative ₹ 26.58Lacs ( against 35.44Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
87.05%
Financial Progress
3rd Expenditure
of ₹ 427153 (4.27 Lacs ) done.
Cummulative ₹ 30.85Lacs ( against 35.44Lacs )