Work Sanctioned
ग्रामसभा जगथाना के अंतर्गत ध्याड़ागाड़ को जाने हेतु 15 मी0 पैदल पुलिया का निर्माण कार्य।

2 years ago

on Tuesday, March 5th 2024, 6:30:00 pm
1%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Saturday, April 13th 2024, 6:30:00 pm
8%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Monday, September 30th 2024, 6:30:00 pm
31.04%
Financial Progress

1st Expenditure
of ₹ 931064 (9.31 Lacs ) done.
Cummulative ₹ 9.31Lacs ( against 30Lacs )

a year ago

on Thursday, October 3rd 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 3rd time

8 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
63.31%
Financial Progress

2nd Expenditure
of ₹ 968119 (9.68 Lacs ) done.
Cummulative ₹ 18.99Lacs ( against 30Lacs )

7 months ago

on Thursday, February 20th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 4th time

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
64.09%
Financial Progress

3rd Expenditure
of ₹ 23488 (0.23 Lacs ) done.
Cummulative ₹ 19.23Lacs ( against 30Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
66.03%
Financial Progress

4th Expenditure
of ₹ 58283 (0.58 Lacs ) done.
Cummulative ₹ 19.81Lacs ( against 30Lacs )

4 months ago

on Thursday, April 24th 2025, 6:30:00 pm
70.62%
Financial Progress

10th Expenditure
of ₹ 11498 (0.11 Lacs ) done.
Cummulative ₹ 21.19Lacs ( against 30Lacs )

4 months ago

on Thursday, April 24th 2025, 6:30:00 pm
66.80%
Financial Progress

5th Expenditure
of ₹ 23045 (0.23 Lacs ) done.
Cummulative ₹ 20.04Lacs ( against 30Lacs )

4 months ago

on Thursday, April 24th 2025, 6:30:00 pm
67.57%
Financial Progress

6th Expenditure
of ₹ 23045 (0.23 Lacs ) done.
Cummulative ₹ 20.27Lacs ( against 30Lacs )

4 months ago

on Thursday, April 24th 2025, 6:30:00 pm
68.34%
Financial Progress

7th Expenditure
of ₹ 23045 (0.23 Lacs ) done.
Cummulative ₹ 20.50Lacs ( against 30Lacs )

4 months ago

on Thursday, April 24th 2025, 6:30:00 pm
69.34%
Financial Progress

8th Expenditure
of ₹ 30000 (0.30 Lacs ) done.
Cummulative ₹ 20.80Lacs ( against 30Lacs )

4 months ago

on Thursday, April 24th 2025, 6:30:00 pm
70.24%
Financial Progress

9th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 21.07Lacs ( against 30Lacs )