Work Sanctioned
वित्तीय वर्ष 2022-23 में राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र लैन्सडौन के विकासखण्ड रिखणीखाल के अन्तर्गत जुई मोटर मार्ग में डामरीकरण का कार्य।
on Friday, July 14th 2023, 12:13:11 pm
Technical Sanction
of ₹ 286.77 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE 3939/12(181) Yata Pauri/2023 dated 14-07-2023
on Tuesday, November 28th 2023, 6:30:00 pm
0.01%
Financial Progress
1st Expenditure
of ₹ 1800 (0.02 Lacs ) done.
Cummulative ₹ 0.02Lacs ( against 286.77Lacs )
on Thursday, December 28th 2023, 6:30:00 pm
0.03%
Financial Progress
2nd Expenditure
of ₹ 8122 (0.08 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 286.77Lacs )
on Thursday, December 28th 2023, 6:30:00 pm
0.05%
Financial Progress
3rd Expenditure
of ₹ 3150 (0.03 Lacs ) done.
Cummulative ₹ 0.13Lacs ( against 286.77Lacs )
on Monday, January 29th 2024, 6:30:00 pm
0.10%
Financial Progress
4th Expenditure
of ₹ 15708 (0.16 Lacs ) done.
Cummulative ₹ 0.29Lacs ( against 286.77Lacs )
on Tuesday, February 27th 2024, 6:30:00 pm
10.68%
Financial Progress
5th Expenditure
of ₹ 3034512 (30.35 Lacs ) done.
Cummulative ₹ 30.63Lacs ( against 286.77Lacs )
on Thursday, February 29th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Monday, March 25th 2024, 6:30:00 pm
18.75%
Financial Progress
6th Expenditure
of ₹ 2313814 (23.14 Lacs ) done.
Cummulative ₹ 53.77Lacs ( against 286.77Lacs )
on Saturday, April 13th 2024, 6:53:02 am
PWD UttarakahndPhoto (ID 37441) from Site Received
Uploader : Vishnu O O, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : 0.000
Remark : Inter coat g2 work
on Wednesday, April 24th 2024, 7:16:24 am
PWD UttarakahndPhoto (ID 37552) from Site Received
Uploader : Amit Kumar Saini, Assistant Engineer Civil ,PD Lansdown
Landmark : Km 0.900
Remark : WBM G-2 Work in progress from Jui sampark marge in state sector
on Wednesday, April 24th 2024, 7:17:32 am
PWD UttarakahndPhoto (ID 37553) from Site Received
Uploader : Vishnu O O, Additional Assistant Engineer Civil ,CD Ramnagar
Landmark : .900
Remark : Inter coat collection work is progress
on Tuesday, May 21st 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, June 12th 2024, 6:30:00 pm
44.69%
Financial Progress
7th Expenditure
of ₹ 7437901 (74.38 Lacs ) done.
Cummulative ₹ 128.15Lacs ( against 286.77Lacs )
on Monday, June 24th 2024, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, June 26th 2024, 6:30:00 pm
47.69%
Financial Progress
8th Expenditure
of ₹ 860820 (8.61 Lacs ) done.
Cummulative ₹ 136.76Lacs ( against 286.77Lacs )
on Monday, July 8th 2024, 6:30:00 pm
47.86%
Financial Progress
9th Expenditure
of ₹ 49088 (0.49 Lacs ) done.
Cummulative ₹ 137.25Lacs ( against 286.77Lacs )
on Sunday, July 21st 2024, 6:30:00 pm
48.03%
Financial Progress
10th Expenditure
of ₹ 47554 (0.48 Lacs ) done.
Cummulative ₹ 137.72Lacs ( against 286.77Lacs )
on Sunday, September 1st 2024, 6:30:00 pm
65%
Physical Progress
Physical Progress Reported at 4th time
on Tuesday, September 24th 2024, 6:30:00 pm
62.48%
Financial Progress
11th Expenditure
of ₹ 4145702 (41.46 Lacs ) done.
Cummulative ₹ 179.18Lacs ( against 286.77Lacs )
on Monday, October 14th 2024, 6:30:00 pm
62.66%
Financial Progress
12th Expenditure
of ₹ 49560 (0.50 Lacs ) done.
Cummulative ₹ 179.68Lacs ( against 286.77Lacs )
on Tuesday, October 15th 2024, 6:30:00 pm
64.05%
Financial Progress
13th Expenditure
of ₹ 400000 (4.00 Lacs ) done.
Cummulative ₹ 183.68Lacs ( against 286.77Lacs )
on Wednesday, December 25th 2024, 6:30:00 pm
68.44%
Financial Progress
14th Expenditure
of ₹ 1259676 (12.60 Lacs ) done.
Cummulative ₹ 196.27Lacs ( against 286.77Lacs )
on Thursday, March 20th 2025, 6:30:00 pm
68.60%
Financial Progress
15th Expenditure
of ₹ 45537 (0.46 Lacs ) done.
Cummulative ₹ 196.73Lacs ( against 286.77Lacs )
on Sunday, April 6th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 5th time
on Monday, May 19th 2025, 6:30:00 pm
94.76%
Financial Progress
16th Expenditure
of ₹ 7500818 (75.01 Lacs ) done.
Cummulative ₹ 271.74Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
94.87%
Financial Progress
18th Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 272.07Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
94.82%
Financial Progress
17th Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 271.90Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
94.93%
Financial Progress
19th Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 272.24Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
94.99%
Financial Progress
20th Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 272.40Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
95.05%
Financial Progress
21st Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 272.57Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
95.11%
Financial Progress
22nd Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 272.74Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
95.22%
Financial Progress
23rd Expenditure
of ₹ 31860 (0.32 Lacs ) done.
Cummulative ₹ 273.06Lacs ( against 286.77Lacs )
on Monday, June 9th 2025, 6:30:00 pm
95.32%
Financial Progress
24th Expenditure
of ₹ 30090 (0.30 Lacs ) done.
Cummulative ₹ 273.36Lacs ( against 286.77Lacs )
on Friday, June 20th 2025, 6:30:00 pm
95.52%
Financial Progress
26th Expenditure
of ₹ 24426 (0.24 Lacs ) done.
Cummulative ₹ 273.92Lacs ( against 286.77Lacs )
on Friday, June 20th 2025, 6:30:00 pm
95.43%
Financial Progress
25th Expenditure
of ₹ 31860 (0.32 Lacs ) done.
Cummulative ₹ 273.67Lacs ( against 286.77Lacs )
on Wednesday, July 23rd 2025, 6:30:00 pm
95.67%
Financial Progress
27th Expenditure
of ₹ 44285 (0.44 Lacs ) done.
Cummulative ₹ 274.36Lacs ( against 286.77Lacs )